Sub topic 7
Schedule Performance Index: EV divided by PV
What this chapter assumes
You should already know what planned value (PV) and earned value (EV) are, and how each is read from the performance measurement baseline. You should also be comfortable with ratios and percentages. Actual cost (AC) is not needed here. SPI uses only PV and EV.
By the end you will be able to calculate SPI, read what a value above, at, or below 1.0 says, avoid the usual calculation mistakes, and judge when a single SPI figure should not be trusted.
The definition
The Schedule Performance Index (SPI) is the ratio of earned value to planned value at the same status date:
SPI = EV / PV
PV is the budgeted cost of work that was scheduled to be finished by the status date. EV is the budgeted cost of work that has actually been finished by that date. Both are expressed in budget currency, so the ratio is unitless.
You can read SPI as "how much of the planned work did we accomplish, per unit of work we planned." An SPI of 0.875 means the project has accomplished 87.5 cents of planned work for every dollar of planned work it should have finished.
Two things follow from this definition:
- SPI measures progress against the baseline, not against some ideal pace. If the baseline is unrealistic, SPI will faithfully report that you are behind an unrealistic plan.
- SPI is measured in budget value, not in time. A ratio of 0.875 does not mean you are 12.5% late in calendar terms. This distinction matters later in the chapter.
Reading the value
| SPI | Meaning | Example reading |
|---|---|---|
| Greater than 1.0 | More work done than planned | Ahead of schedule |
| Equal to 1.0 | Work done matches the plan | On schedule |
| Less than 1.0 | Less work done than planned | Behind schedule |
SPI and schedule variance (SV = EV - PV) always agree in sign. If SV is negative, SPI is below 1.0. If SV is zero, SPI is exactly 1.0. The difference is that SV is an absolute amount, while SPI is relative. A 5,000 shortfall means something very different on a 50,000 project than on a 5,000,000 project. SPI makes the two comparable.
A worked example
Take a project with a budget at completion (BAC) of 100,000. At the end of period 3, the baseline says 40,000 of work should be finished, so PV = 40,000. The team has finished work with a budgeted value of 35,000, so EV = 35,000.
- SV = 35,000 - 40,000 = -5,000
- SPI = 35,000 / 40,000 = 0.875
The project has completed 87.5% of the work it planned to complete by now. It is behind schedule.
The following function computes the core metrics for this status date, including the cost-side figures used in later chapters. Only SV and SPI matter here.
def performance_indices(bac, pv, ev, ac):
"""Return the core earned value metrics for one status date."""
sv = ev - pv # schedule variance
cv = ev - ac # cost variance
spi = ev / pv # schedule performance index
cpi = ev / ac # cost performance index
eac = bac / cpi # forecast assuming current cost efficiency continues
etc = eac - ac # estimate to complete
tcpi = (bac - ev) / (bac - ac) # efficiency needed to finish on BAC
return {"SV": sv, "CV": cv, "SPI": spi, "CPI": cpi,
"EAC": eac, "ETC": etc, "TCPI": tcpi}
m = performance_indices(bac=100_000, pv=40_000, ev=35_000, ac=42_000)
for name, value in m.items():
print(f"{name}: {value:,.3f}")Running it prints SV as -5,000.000 and SPI as 0.875, matching the hand calculation. The same run gives CV of -7,000, CPI of 0.833, EAC of 120,000, ETC of 78,000 and TCPI of 1.121, so the project is also over budget. SPI alone does not tell you that. It says nothing about cost.
Where PV and EV come from
SPI is only as good as its two inputs, so errors usually start there.
PV comes from the time-phased baseline
PV is read from the cumulative planned value curve, often called the S-curve. You find the status date on the horizontal axis and read the cumulative budget scheduled up to that point. If the schedule is re-baselined, the PV curve changes, and SPI values before and after are not directly comparable.
EV comes from a measurement rule
EV is the budgeted value of completed work, based on the rules chosen for each work package: 0/100, 50/50, weighted milestones, or percent complete. The choice affects SPI directly. A work package credited only at completion (0/100) produces a lumpy EV and a jumpy SPI. A package credited by subjective percent complete tends to produce an optimistic SPI that drops sharply once the work is inspected.
Both must use the same status date and the same budget basis
SPI divides two numbers that must describe the same moment and the same unit of value. EV is always valued at the budgeted rate, never at what the work actually cost.
Common errors
- Using AC in place of PV. Dividing EV by actual cost gives CPI, not SPI.
- Mismatched dates. Taking PV at the end of the month and EV from a status report collected two weeks earlier makes the project look behind when it may not be.
- Valuing EV at actual cost. If a task was budgeted at 10,000 and cost 14,000, its EV on completion is 10,000. Using 14,000 inflates SPI.
- Reading SPI as a percentage of time. An SPI of 0.8 does not mean the project will finish 25% late.
- Averaging SPI across work packages. Always sum EV and sum PV first, then divide. An unweighted average of package SPIs gives small packages the same influence as large ones.
- Dividing by zero. Before the first scheduled work, PV is zero and SPI is undefined. Report it as not applicable rather than as 0 or infinity.
- Mixing in non-critical work. Ahead-of-plan work on tasks with float can hide delays on the critical path, as discussed below.
What SPI does not tell you
It does not know which work is late
SPI is an aggregate. EV is the sum of completed value across all work packages, so finishing 10,000 of non-critical work early offsets 10,000 of critical work that is late. The result can be an SPI of 1.0 while the critical path slips. For this reason, SPI should be read alongside the critical path schedule, not instead of it.
It does not forecast a finish date
SPI says how much work is behind in budget terms. Turning that into a date requires the schedule network, remaining durations, and logic. A rule of thumb such as dividing the remaining duration by SPI is a rough estimate at best.
It drifts toward 1.0 near the end
This is the most important limitation. When a project finishes, all of the BAC has been earned, so EV equals BAC. PV also reaches BAC at the planned completion date and stays there afterward. Therefore, once the project passes its planned end date, PV is fixed at BAC. If the project finishes late, EV eventually reaches BAC too, and SPI becomes exactly 1.0 on a project that was late by any amount.
Consider the project's last weeks. The planned end is period 6, but the project is running behind. At period 6, PV is 100,000. EV might be 90,000, giving SPI of 0.9. In period 7, PV is still 100,000 and EV rises to 96,000, giving 0.96. SPI seems to be recovering even though the project is already past its deadline and getting later by the day.
The effect arises because SPI is value-based. The same missing 4,000 of work counts for a lot when the plan is at 40,000 and for little once the plan is at 100,000. The metric loses its power to flag lateness exactly when lateness is most costly.
A time-based check: earned schedule
Earned schedule is covered in a later chapter, but a short preview shows the idea. Instead of comparing EV and PV in money, ask at which period the baseline PV equaled today's EV. That period is the earned schedule (ES). The time-based index is ES divided by actual time (AT).
def earned_schedule(cum_pv, ev):
"""Earned schedule in periods, using linear interpolation.
cum_pv[i] is the cumulative planned value at the end of period i + 1.
"""
prev = 0.0
for i, pv in enumerate(cum_pv):
if ev <= pv:
return i + (ev - prev) / (pv - prev)
prev = pv
return float(len(cum_pv))
cum_pv = [10_000, 25_000, 40_000, 60_000, 80_000, 100_000]
actual_time = 3
es = earned_schedule(cum_pv, ev=35_000)
print(f"ES = {es:.3f} periods, SPI(t) = {es / actual_time:.3f}")The EV of 35,000 falls between the cumulative PV at period 2 (25,000) and at period 3 (40,000). Interpolating gives ES = 2 + (35,000 - 25,000) / (40,000 - 25,000) = 2.667 periods. After 3 periods, SPI(t) = 2.667 / 3 = 0.889. This is close to the cost-based 0.875 here, but the two diverge near the end of a project, where SPI(t) keeps reflecting lateness and the cost-based SPI does not.
How SPI moves over time
The curve shows the pattern to watch for. The dip in periods 3 to 5 reflects real delay. The recovery in periods 6 and 7 is mostly the arithmetic effect described above, not a recovery in the schedule.
Practical guidance
- Compute SPI from totals, at the level you will report. Do not average lower-level indices.
- Record the status date next to every SPI value.
- Use SV alongside SPI. SV tells you the size of the gap in currency. SPI tells you the proportion.
- Check the critical path whenever SPI is near 1.0 but milestones are slipping.
- Once the planned finish date passes, switch to a time-based measure such as SPI(t), or report remaining duration from the schedule network.
- Treat one data point cautiously. A single low SPI could be a timing artifact from a 0/100 work package that is due to be credited next period. Look at the trend over several periods.
Summary
SPI is EV divided by PV. A value above 1.0 means ahead of plan, 1.0 means on plan, and below 1.0 means behind plan. It is a ratio of budgeted values, so it measures progress in value, not in time. It ignores the critical path, says nothing about cost, and drifts to 1.0 as a project ends, even a late one. Use it with SV, the schedule network, and a time-based index.
Exercise
At the end of period 4, a project has PV = 60,000 and EV = 54,000. (a) Calculate SV and SPI. (b) The project's planned finish is period 6 with BAC = 100,000. In period 8 the project is still running, with EV = 98,000. What is SPI in period 8, and why is it misleading?
Show answer
(a) SV = 54,000 - 60,000 = -6,000. SPI = 54,000 / 60,000 = 0.90, so the project is behind schedule. (b) After period 6, PV stays at BAC, which is 100,000. SPI = 98,000 / 100,000 = 0.98. This looks nearly on schedule, but the project is two periods past its planned finish and has not completed. SPI is misleading because PV can no longer grow, so the ratio approaches 1.0 as EV approaches BAC regardless of how late the work is.
Exercise
A project has two work packages at the status date. Package A has PV = 20,000 and EV = 10,000. Package B has PV = 5,000 and EV = 6,000. What is the project SPI, and why is it wrong to average the two package SPIs?
Show answer
Total PV = 25,000 and total EV = 16,000, so project SPI = 16,000 / 25,000 = 0.64. The package SPIs are 0.5 and 1.2, and their simple average is 0.85. That figure overstates performance because it gives the small package B the same weight as the large package A. Always sum EV and PV first, then divide.