TCPI: the efficiency the remaining work requires
This chapter assumes you can calculate CPI and SPI from PV, EV and AC, and that you know how EAC is forecast from CPI. Here you will learn to compute the To-Complete Performance Index (TCPI), to read it, and to spot the cases where it misleads.
What TCPI answers
CPI looks backward. It says how much value each unit of money has produced so far. EAC looks forward under an assumption. TCPI links the two by asking a different question: what cost efficiency must the remaining work achieve to finish within a chosen financial target?
TCPI is the ratio of the work left to the money left:
TCPI = work remaining / funds remainingWork remaining is measured in budgeted value, so it is BAC minus EV. Funds remaining depends on the target you choose. Because of that choice, TCPI comes in two forms.
| Form | Target | Formula | Use it when |
|---|---|---|---|
| TCPI to BAC | Original budget | (BAC − EV) / (BAC − AC) | The budget is still the commitment |
| TCPI to EAC | Revised forecast | (BAC − EV) / (EAC − AC) | The sponsor has accepted a new total |
A TCPI of 1.0 means the remaining work must be done exactly as efficiently as planned. A value above 1.0 means you must spend less than budgeted per unit of work from now on. A value below 1.0 means you can afford to spend more than budgeted per unit and still hit the target.
Worked example: TCPI to BAC
Use the numbers from the earlier chapters: BAC 100,000, PV 40,000, EV 35,000, AC 42,000.
- Work remaining: 100,000 − 35,000 = 65,000 of budgeted value.
- Funds remaining: 100,000 − 42,000 = 58,000.
- TCPI = 65,000 / 58,000 = 1.121.
The project has earned 0.833 of value per unit spent (CPI). To finish on the original budget, it must earn 1.121 for every unit spent from now on. That is a 35% jump in efficiency over the current CPI (1.121 / 0.833 ≈ 1.345). The gap between those two numbers shows how demanding the original budget has become.
Worked example: TCPI to EAC
Suppose you forecast the final cost by assuming current efficiency continues. EAC = BAC / CPI = 120,000. Then:
- Funds remaining: 120,000 − 42,000 = 78,000.
- TCPI = 65,000 / 78,000 = 0.833.
The result equals CPI. This is not a coincidence. When EAC is defined as BAC / CPI, the remaining work is forecast to cost 78,000 for 65,000 of value, which is the current ratio. TCPI to EAC under that formula only restates the assumption you made. It tells you nothing new, so use it as a consistency check and not as evidence.
The comparison becomes useful when EAC comes from another method, such as a bottom-up estimate by the team:
| EAC method | Formula | EAC | TCPI to EAC |
|---|---|---|---|
| Current CPI continues | BAC / CPI | 120,000 | 0.833 |
| Past variance was a one-off | AC + (BAC − EV) | 107,000 | 1.000 |
| Cost and schedule both drive the rest | AC + (BAC − EV) / (CPI × SPI) | 131,143 | 0.741 |
| Bottom-up re-estimate (example) | Supplied by the team | 110,000 | 0.956 |
Read the last column against CPI of 0.833. The one-off variance forecast needs TCPI of 1.000, a 20% improvement over the actual record. The bottom-up forecast needs 0.956, a 15% improvement. If nothing about the project has changed, those forecasts are optimistic. TCPI makes the optimism visible as a number you can challenge.
Computing TCPI in code
The function below handles both forms through an optional target, and it guards the edge cases covered in the next section.
def tcpi(bac, ev, ac, target=None):
"""To-complete performance index against a target total cost.
target defaults to BAC. Pass EAC to get TCPI to EAC.
Returns 0.0 when no work remains and inf when work remains
but no funds remain under the target.
"""
target = bac if target is None else target
work_remaining = bac - ev
funds_remaining = target - ac
if work_remaining <= 0:
return 0.0
if funds_remaining <= 0:
return float("inf")
return work_remaining / funds_remaining
bac, ev, ac = 100_000, 35_000, 42_000
cpi = ev / ac
for label, target in [("BAC", 100_000), ("EAC (BAC/CPI)", bac / cpi),
("Bottom-up EAC", 110_000), ("Overspent target", 40_000)]:
print(f"TCPI to {label}: {tcpi(bac, ev, ac, target):.3f}")
print(f"Current CPI: {cpi:.3f}")Running it prints 1.121, 0.833, 0.956 and inf for the four targets, then a CPI of 0.833.
Edge cases
TCPI is a ratio, so its denominator causes most of the failures.
- Funds remaining is zero or negative. If AC equals or exceeds the target while work remains, the denominator is zero or negative. No efficiency can finish the work within the target. Report the target as unreachable. Do not report a negative or infinite number without comment.
- Work remaining is zero. When EV equals BAC, the numerator is zero. TCPI is 0, which only says the work is done.
- EV above BAC. This usually signals a measurement or scope error and should be investigated.
- Funds remaining is tiny. A small denominator produces a very large TCPI. A project with 1,000 left in the budget and 20,000 of work remaining gives TCPI of 20. The number is mathematically correct and practically meaningless as a performance target.
Judging whether the requirement is credible
Compare TCPI with CPI. The simplest test is the ratio TCPI / CPI, which shows how much improvement the budget demands.
- TCPI close to CPI. The target matches the current performance. It is a realistic target.
- TCPI modestly above CPI (say, 5–10% above). Achievable with focused corrective action, if you can name the actions.
- TCPI far above CPI, or above 1.0 when CPI has been below 1.0 for several periods. The original budget is probably out of reach. A common rule of thumb treats a TCPI to BAC above about 1.10 as very hard to achieve, though the threshold is a convention and not a law. Your organization may set its own.
Efficiency rarely improves late in a project. The easy work is done first, and rework, integration and testing tend to be costly. A CPI that has stayed stable for the first 20% of a project often stays near that value to the end. Studies of completed projects reported this pattern widely enough that many organizations treat CPI at about 20% complete as a usable predictor of final CPI. Treat that as an observed tendency, not a guarantee.
Common errors
- Using AC in the numerator. Work remaining is BAC − EV, in budgeted value. Using BAC − AC there measures money, not work.
- Reporting TCPI to EAC as independent evidence. As shown above, when EAC is BAC / CPI, TCPI to EAC equals CPI by construction.
- Forgetting which target applies. Always label the number "TCPI to BAC" or "TCPI to EAC". Stakeholders will otherwise compare a figure of 1.12 against one of 0.83 without knowing they used different targets.
- Ignoring schedule. TCPI is a cost measure. A project can have a comfortable TCPI and still be late, so read it with SPI and the trend views covered later in this tutorial.
- Reading one period alone. A single status date with a noisy EV can swing TCPI sharply. Look at several periods.
Summary of the chapter's formulas
| Quantity | Formula | Example value |
|---|---|---|
| Work remaining | BAC − EV | 65,000 |
| Funds remaining (to BAC) | BAC − AC | 58,000 |
| TCPI to BAC | (BAC − EV) / (BAC − AC) | 1.121 |
| TCPI to EAC | (BAC − EV) / (EAC − AC) | 0.833 for EAC of 120,000 |
Exercise
A project has BAC 200,000, EV 80,000 and AC 100,000. (a) Calculate CPI and TCPI to BAC. (b) The team proposes an EAC of 230,000. Calculate TCPI to EAC. (c) Is the original budget credible?
Show answer
(a) CPI = 80,000 / 100,000 = 0.800. TCPI to BAC = (200,000 − 80,000) / (200,000 − 100,000) = 120,000 / 100,000 = 1.200. (b) TCPI to EAC = 120,000 / (230,000 − 100,000) = 120,000 / 130,000 = 0.923. (c) The original budget is not credible. It needs efficiency of 1.20 against a record of 0.80, which is a 50% improvement. Even the proposed EAC of 230,000 needs 0.923, about 15% better than the record, so it is also optimistic. Under a continuing CPI of 0.80 the EAC would be 250,000, which gives TCPI to EAC of 0.800.
Exercise
A project has BAC 50,000, EV 30,000 and AC 52,000. What does TCPI to BAC evaluate to, and what should you report?
Show answer
Funds remaining is 50,000 − 52,000 = −2,000, which is negative while 20,000 of work remains. No efficiency can finish within BAC, so TCPI to BAC is undefined as a usable target (the code returns inf). Report that the original budget is already exceeded and that a new EAC, and a TCPI to that EAC, is needed.