Sub topic 8
Cost Performance Index: EV divided by AC
This chapter assumes you can already compute planned value (PV), earned value (EV) and actual cost (AC) for a status date, and that you know the cost variance formula, CV = EV − AC. Here we turn those into a ratio, the Cost Performance Index (CPI), and look at how it behaves in practice.
What CPI measures
CPI is the amount of work value you have earned for each unit of money you have spent:
CPI = EV / ACEV is the budgeted value of the work actually completed. AC is what that work really cost. If CPI is 0.83, each 1.00 spent has produced 0.83 of planned value.
CV and CPI use the same two inputs but answer different questions:
- CV = EV − AC is an absolute difference in currency. It tells you how much money you are ahead or behind.
- CPI = EV / AC is a unitless ratio. It tells you how efficiently you are spending, so you can compare a 20,000 work package with a 20 million program.
A cost variance of −7,000 means something very different on a 100,000 project than on a 10 million one. The same two projects with the same CPI of 0.83 are spending equally efficiently.
Worked example
Use the running data from this tutorial: BAC (budget at completion) 100,000, PV 40,000, EV 35,000, AC 42,000.
- CPI = 35,000 / 42,000 = 0.833
- CV = 35,000 − 42,000 = −7,000
The team has spent 42,000 to earn 35,000 of value. Every 1.00 of planned work is costing about 1.20, which is AC / EV, the reciprocal of CPI. That reciprocal is a useful way to explain the result to a sponsor: "this work is costing us 20% more than budgeted."
Notice that PV does not appear anywhere in the CPI formula. CPI says nothing about whether you are on schedule. That is the job of SPI.
Reading the value
| CPI | CV | Meaning | Example (EV 35,000) |
|---|---|---|---|
| Greater than 1.0 | Positive | Under budget for the work done | AC 28,000 gives CPI 1.25 |
| Equal to 1.0 | Zero | On budget | AC 35,000 gives CPI 1.00 |
| Less than 1.0 | Negative | Over budget for the work done | AC 42,000 gives CPI 0.83 |
The sign of CV and the side of 1.0 for CPI always agree. If they do not, one of your inputs is wrong.
Computing CPI in code
The function below computes CPI with guards for the edge cases covered later. It also compares the cumulative CPI with the CPI of each individual period, which matters for trend reading.
def cpi(ev, ac):
"""Cost Performance Index. Undefined when no cost has been recorded."""
if ac <= 0:
raise ValueError("CPI is undefined when actual cost is zero or negative")
return ev / ac
period_ev = [10_000, 12_000, 13_000]
period_ac = [10_000, 14_000, 18_000]
cum_ev = 0
cum_ac = 0
for n, (ev, ac) in enumerate(zip(period_ev, period_ac), start=1):
cum_ev += ev
cum_ac += ac
print(f"Period {n}: cumulative CPI = {cpi(cum_ev, cum_ac):.3f}, "
f"period CPI = {cpi(ev, ac):.3f}")
print(f"CV at period 3 = {cum_ev - cum_ac:,}")Running it prints:
Period 1: cumulative CPI = 1.000, period CPI = 1.000
Period 2: cumulative CPI = 0.917, period CPI = 0.857
Period 3: cumulative CPI = 0.833, period CPI = 0.722
CV at period 3 = -7,000The cumulative values at period 3 match the worked example: EV 35,000, AC 42,000, CPI 0.833.
Look at the gap between the two columns. The cumulative CPI fell from 1.000 to 0.833, but the period CPI fell from 1.000 to 0.722. The cumulative figure smooths out recent behavior, so it understates how bad the latest period was.
Cumulative CPI versus period CPI
Most reports show the cumulative CPI, calculated from project start to the status date. Some also show a period CPI (sometimes called current or periodic CPI), calculated from only that period's EV and AC. Use them for different purposes:
- Cumulative CPI summarizes performance to date and is the usual basis for forecasting EAC.
- Period CPI shows what is happening now. A cumulative CPI of 0.92 with period CPIs of 0.86, then 0.72, describes a project that is getting worse, not one that is stable at 0.92.
Cumulative CPI becomes harder to move as the project grows. A single good month late in a project barely changes a cumulative figure built on many months of data. For that reason, a poor cumulative CPI in the middle of a project is usually a lasting condition and not a blip. Studies of completed projects, most of them in defense contracting, have often found that final CPI ends up close to the CPI at about 20% completion, and rarely recovers by much. Treat that as a rule of thumb from specific industries, not a law. Still, it is a good reason to take an early low CPI seriously.
Common errors
Dividing by zero or near zero
At the very start of a project, AC may be zero, which makes CPI undefined. When AC is tiny, CPI swings wildly, because a small spend against a small earned value gives a ratio that says little. Many teams do not report CPI until a meaningful amount of work has been done, and show EV and AC alone before that.
If EV is zero but AC is positive, CPI is 0.0. This is legitimate and often real: you have spent money and earned nothing yet, for instance under a 0/100 rule where nothing is credited until a task finishes.
Mismatched cost bases
EV and AC must be in the same units and from the same cutoff date. Common mismatches:
- EV is in budgeted currency but AC is in hours, or the reverse.
- AC includes overhead or contingency but the baseline behind EV does not.
- AC is current through the 30th but EV was assessed on the 25th.
Any of these produces a CPI that looks precise but means nothing.
Unrecorded costs
CPI is only as good as the AC behind it. Invoices not yet received, timesheets not yet submitted, and committed but unbilled costs all make AC too low and CPI too high. The project then appears healthier than it is, and the correction arrives later as a sudden drop. Ask finance whether accruals are included before you trust a good-looking CPI.
Optimistic earned value
CPI can also be inflated from the EV side. If progress is claimed generously, for example "90% done" on a task that stays at 90% for weeks, EV is too high and CPI is too high. This is why the choice of measurement method, such as 0/100 or weighted milestones, matters. Methods that credit value only against verifiable events are harder to inflate.
Treating CPI as a schedule measure
A CPI of 1.05 does not mean the project is on time. A project can be under budget because work is late, and so far not much has been spent. CPI describes cost efficiency of the work performed, nothing more.
Using CPI to forecast
CPI is the standard input for forecasting. If you assume the cost efficiency to date will continue for the remaining work, then:
EAC = BAC / CPI
ETC = EAC − ACWith the running data: EAC = 100,000 / 0.833 = 120,000, and ETC = 120,000 − 42,000 = 78,000. The next chapters cover when this assumption holds and when other formulas are better. For now, notice that CPI is the lever: the lower it is, the larger the forecast overrun, and the forecast overrun is the amount by which BAC is exceeded (here 20,000, or 20%).
Setting thresholds
CPI is only useful for action if you decide in advance what values trigger a response. Typical arrangements are tolerance bands, for example:
- 0.95 to 1.10: normal, report only.
- 0.90 to 0.95: watch, require a short explanation.
- Below 0.90: corrective action plan and sponsor notification.
The numbers are a choice for your organization or contract, not a standard. What matters is that they are set before the data comes in, and that the band is asymmetrical when overspending is the greater risk. A CPI well above 1.0 also deserves a question, because it may signal padded estimates, unrecorded costs or overstated progress.
Summary of the working model
- CPI = EV / AC, using the same cost basis and cutoff date for both.
- Above 1.0 means under budget for the work done, below 1.0 means over budget.
- CPI is a ratio and CV is a difference. Report both.
- CPI says nothing about schedule.
- Cumulative CPI is stable and useful for forecasting. Period CPI shows the direction.
- Check the inputs first: missing AC and generous EV are the two main ways a CPI misleads.
Exercise
A project has BAC 200,000. At the status date, PV is 90,000, EV is 80,000 and AC is 100,000. Calculate CPI and CV, say what they tell you, and give the CPI-based EAC. Then explain why a CPI of 0.80 could still be misleading if the finance team had not yet recorded 15,000 of invoices for work already done.
Show answer
CPI = 80,000 / 100,000 = 0.80. CV = 80,000 − 100,000 = −20,000. The project is over budget: it earns 0.80 of value per 1.00 spent, and has spent 20,000 more than the value earned. EAC = 200,000 / 0.80 = 250,000, a forecast overrun of 50,000. PV is not used in any of this, so nothing is learned about schedule. If 15,000 of invoices are unrecorded, true AC is 115,000, so true CPI is 80,000 / 115,000 = 0.696, and the true CV is −35,000. The reported 0.80 is too optimistic, and the EAC based on it (250,000) understates the forecast of about 287,500.