Sub topic 1
The baseline that everything is measured against
Prerequisites
This chapter assumes you already know the following:
- Basic project management vocabulary: scope, schedule, budget, and work breakdown structure (WBS).
- How to read a project schedule and a budget.
- Simple arithmetic with ratios and percentages.
- Some Python, if you want to run the code. It is short and uses only the standard library.
You do not need to know earned value yet. This chapter sets up what the later chapters measure against.
Why the baseline comes first
The Schedule Performance Index (SPI) and the Cost Performance Index (CPI) are ratios. Each compares what happened with what you agreed to do. If the agreement is vague, out of date, or quietly edited, the ratios look precise but mean nothing.
That agreement is the performance measurement baseline (PMB). It is the approved, time-phased plan against which earned value performance is measured. Planned value, earned value, and actual cost, which the next three chapters cover, all depend on it. An index can only be as trustworthy as the baseline behind it.
What the baseline contains
The PMB combines three approved baselines into one integrated view.
| Component | What it fixes | Typical source |
|---|---|---|
| Scope baseline | What work is in the project | Approved scope statement, WBS, WBS dictionary |
| Schedule baseline | When each piece of work is planned to happen | Approved schedule with activity dates and durations |
| Cost baseline | How much budget is assigned to each piece of work, and when it is spent | Approved time-phased budget |
The three must agree with each other. A work package that exists in the WBS but has no dates or no budget cannot produce planned value. A budget line with no matching scope cannot be earned.
Budget at completion
The budget at completion (BAC) is the total budget assigned to all the work in the baseline. It is the sum of the budgets of every work package (and planning package, described below). It is the number that the completed project would have earned if everything went exactly to plan.
BAC is a budget for work, not a forecast of what the project will cost. The forecast is the estimate at completion (EAC), which a later chapter covers. If you confuse the two, you will read a CPI of 0.83 as a failure of the budget rather than as a signal about performance.
In this tutorial's running example, the project has a BAC of 100,000.
How the baseline is built
Earned value works at the level where scope, schedule, and cost meet. Three structures matter.
- Work package. The lowest level of the WBS. It has a defined scope, a budget, and scheduled dates. Work packages are the unit where you will later measure earned value.
- Control account. A management point where one or more work packages are grouped. A control account has a single owner, and scope, budget, actual cost, and schedule are compared there.
- Planning package. Work that is known but not yet detailed enough to split into work packages. It holds a budget and a rough time window. As the date approaches, the planning package is broken into work packages with detailed schedules. This is rolling-wave planning.
Planning packages matter for measurement. Their budget is in BAC, but until they are detailed, the planned value they produce is only an approximation. Do not report fine-grained SPI for work that is still a planning package.
Time-phasing: turning budget into a curve
BAC alone says how much. Time-phasing says when. You spread each work package's budget across the periods in which its work is scheduled. Adding up all packages period by period gives the planned spend per period. Accumulating those values gives the cumulative curve. Plotted, this curve is the familiar S-curve. It starts slowly, rises steeply through the main work, and flattens at the end. It ends at BAC.
The next chapter defines planned value as the point on this curve at the status date. Here we only build the curve.
The following code builds a cumulative planned curve from four work packages. It spreads each budget evenly across its scheduled periods. That is the simplest spreading rule, and real projects may use front-loaded or back-loaded profiles instead.
from itertools import accumulate
# (work package, budget, first period, last period), periods numbered from 1
work_packages = [
("Requirements", 10_000, 1, 1),
("Design", 30_000, 2, 3),
("Build", 40_000, 4, 5),
("Test", 20_000, 6, 6),
]
def time_phase(packages, periods):
"""Spread each budget evenly over its periods and return per-period values."""
per_period = [0.0] * periods
for name, budget, first, last in packages:
if not 1 <= first <= last <= periods:
raise ValueError(f"{name}: periods {first}-{last} outside 1-{periods}")
share = budget / (last - first + 1)
for p in range(first - 1, last):
per_period[p] += share
return per_period
per_period = time_phase(work_packages, periods=6)
cumulative = list(accumulate(per_period))
bac = sum(budget for _, budget, _, _ in work_packages)
print(f"BAC = {bac:,}")
for period, (spend, cum) in enumerate(zip(per_period, cumulative), start=1):
print(f"Period {period}: planned {spend:>8,.0f} cumulative {cum:>8,.0f}")
assert abs(cumulative[-1] - bac) < 1e-9, "curve must end at BAC"The output ends with a cumulative value of 100,000, equal to BAC. The cumulative values are 10,000, 25,000, 40,000, 60,000, 80,000, and 100,000. These are the same numbers the earned schedule example uses later in this tutorial. The assertion at the end is a useful habit: if the curve does not end at BAC, some budget has no dates or some dates have no budget.
Reserves: what is inside the baseline and what is not
Projects hold money for uncertainty in two ways, and the difference affects your numbers.
- Contingency reserve covers identified risks, the "known unknowns". Practice varies. Some organizations include it in the cost baseline, and others hold it at project level and release it to work packages through change control. Whichever convention you use, apply it consistently and state it in your reporting.
- Management reserve covers unidentified risks, the "unknown unknowns". It is not part of the PMB. It is added to the baseline to form the project budget. It is released into the baseline only through a formal change.
Management reserve is excluded for a reason. If it sat inside BAC, it would inflate planned value and earned value, and every ratio would drift. Including it would also hide overruns that the reserve was meant to expose.
Keeping the baseline stable
A baseline is useful because it does not move casually. Three rules keep it that way.
- Change only through approved change control. When scope, schedule, or budget changes by decision, the baseline changes by decision too. Record the approval, the date, and the amount.
- Do not edit the baseline to match performance. If a late project gets its dates pushed to remove the lateness, SPI returns to 1.0 and the problem is still there.
- Rebaseline rarely and with care. A full rebaseline is justified when the plan is so far from reality that comparisons no longer inform decisions. It resets the variances, so keep the old baseline on file. Without that history, stakeholders cannot see how far the project has drifted from the original commitment.
Approved scope changes are legitimate. When the client adds work and funds it, BAC rises by the budget of the new work, and planned value rises with it. That is an honest adjustment. The error is adjusting the baseline to absorb poor performance.
Common errors
| Error | Effect on SPI and CPI |
|---|---|
| Work packages with no dates or no budget | Planned value is wrong from the start, so both indices are skewed |
| Budget set from the total cost forecast instead of the work | BAC contains padding or missing work, so CPI misleads |
| Management reserve included in BAC | Planned and earned value inflate and overruns are hidden |
| Baseline edited without approval | Variances disappear, and trends cannot be compared across periods |
| Planning packages reported like detailed work | SPI looks precise when the schedule is only an estimate |
| Scope change not reflected in BAC | A funded addition shows up as a false cost overrun |
Summary
The PMB combines the approved scope, schedule, and cost baselines. Its total is BAC. Spread across time, it forms the planned curve that the next chapter turns into planned value. Reserves stay outside the measurement or are handled by a stated convention. The baseline changes only through controlled decisions, because every later ratio assumes it stays put.
Exercise
A project has four work packages with budgets of 8,000, 12,000, 20,000 and 10,000. The management reserve is 5,000. A manager proposes to set BAC to 55,000 so that the reserve is "available for the team". What BAC should the performance baseline use, and why is the proposal a problem?
Show answer
BAC is 8,000 + 12,000 + 20,000 + 10,000 = 50,000. The management reserve of 5,000 belongs in the project budget (55,000 in total) but outside the performance measurement baseline. Setting BAC to 55,000 would add planned value for work that does not exist. That distorts the planned curve and weakens every later SPI and CPI. If the reserve is needed, it should be released into the baseline through formal change control, and BAC would then rise with the approved change.
Exercise
A work package has a budget of 30,000 and is scheduled for periods 2 and 3, with the budget spread evenly. What planned value does it contribute in each of periods 1, 2 and 3, and what is its cumulative planned value at the end of period 3?
Show answer
It contributes 0 in period 1, 15,000 in period 2 and 15,000 in period 3. Its cumulative planned value at the end of period 3 is 30,000, its full budget.