Sub topic 6
Schedule and Cost Variance as Absolute Differences
This chapter assumes you know the three earned value measurements from the earlier chapters: planned value (PV), earned value (EV) and actual cost (AC). It also assumes you are comfortable with positive and negative numbers and with percentages. Here you will turn those measurements into schedule variance and cost variance, learn how to read them, and see where they stop being useful.
What a variance is
A variance is the plain difference between two of the three measurements, taken at the same status date. It is expressed in currency, not as a ratio. Two variances cover the whole earned value picture:
- Schedule variance (SV) compares the work accomplished with the work planned.
- Cost variance (CV) compares the work accomplished with what that work cost.
EV appears in both formulas. EV is the budgeted value of the work actually completed, so it works as the common yardstick. Each variance asks how far EV is from a different reference point: PV for schedule, AC for cost.
SV = EV - PV
CV = EV - ACBoth formulas put EV first. Because of that, a negative result is always bad news and a positive result is always good news.
Sign convention
| Result | Schedule variance | Cost variance |
|---|---|---|
| Positive | EV is above PV: more work done than planned | EV is above AC: the work cost less than its budgeted value |
| Zero | Work done equals work planned | Cost equals budgeted value of the work |
| Negative | EV is below PV: behind schedule | EV is below AC: over budget |
Some older texts and tools define variance as plan minus actual, which flips the sign. Check the formula in any report before you read its numbers. The convention in this chapter is the one used by the PMI Standard for Earned Value Management and the PMBOK Guide.
A worked example
Take a project with a budget at completion (BAC) of 100,000. At the status date:
- PV = 40,000. The baseline says 40,000 of work should be finished by now.
- EV = 35,000. The work actually completed is worth 35,000 at its budgeted rate.
- AC = 42,000. Spending to date has been 42,000.
The calculations:
- SV = 35,000 − 40,000 = −5,000
- CV = 35,000 − 42,000 = −7,000
The project has completed 5,000 less budgeted work than planned, so it is behind schedule. It has also paid 7,000 more than the budgeted value of the work it completed, so it is over budget.
Variances are in money, not time
SV is the least intuitive of the two. A schedule variance of −5,000 does not mean the project is 5,000 days late, or any number of days late. It is a value of work, the budgeted value of work not yet done. Converting that into a delay requires knowing how fast the plan expects work to be earned. If the plan earns about 10,000 per period around this point, then 5,000 is roughly half a period of lag. That conversion is an estimate and depends on the shape of the plan. The earned schedule chapter later in this tutorial gives a more rigorous way to measure time directly.
CV has no such problem. It is already a cost figure, so a CV of −7,000 means 7,000 more has been spent than the completed work was budgeted to cost.
Absolute versus relative: why variances alone can mislead
Because variances are absolute differences, the same number can mean very different things on different projects. Compare two projects, both with SV = −5,000.
| Project | PV | EV | SV | SV as % of PV | SPI |
|---|---|---|---|---|---|
| A (small) | 10,000 | 5,000 | −5,000 | −50% | 0.50 |
| B (large) | 500,000 | 495,000 | −5,000 | −1% | 0.99 |
Project A has done half of what it planned. Project B is essentially on plan. The variance is identical, but the situation is not. This is why the next chapters introduce the indices SPI and CPI, which divide by a baseline and so give a size-independent signal.
If you need a relative figure while staying with variances, use a percent variance:
- SV% = SV / PV
- CV% = CV / EV
For the worked example, SV% = −5,000 / 40,000 = −12.5%, and CV% = −7,000 / 35,000 = −20%. Note that the denominators differ. Check which one your organization uses before comparing numbers across reports.
Computing the variances in code
The function below computes both variances and their percentages, and labels the result. It guards against a zero PV or EV, which happens at the very start of a project.
def variance_report(pv, ev, ac):
"""Return SV, CV and their percentages for one status date."""
sv = ev - pv
cv = ev - ac
sv_pct = sv / pv * 100 if pv else None
cv_pct = cv / ev * 100 if ev else None
def label(value, ahead, behind):
if value > 0:
return ahead
if value < 0:
return behind
return "on plan"
return {
"SV": sv,
"SV%": sv_pct,
"schedule": label(sv, "ahead of schedule", "behind schedule"),
"CV": cv,
"CV%": cv_pct,
"cost": label(cv, "under budget", "over budget"),
}
report = variance_report(pv=40_000, ev=35_000, ac=42_000)
print(f"SV = {report['SV']:,} ({report['SV%']:.1f}%) -> {report['schedule']}")
print(f"CV = {report['CV']:,} ({report['CV%']:.1f}%) -> {report['cost']}")Running it prints:
SV = -5,000 (-12.5%) -> behind schedule
CV = -7,000 (-20.0%) -> over budgetReading the two variances together
The two variances are independent, so four combinations exist.
| SV | CV | Typical reading |
|---|---|---|
| Positive | Positive | Ahead and under budget. Check that EV is not overstated. |
| Positive | Negative | Ahead, but paying more than planned. Possibly buying speed with overtime or extra resources. |
| Negative | Positive | Behind, but spending less than planned. Possibly resources not yet deployed or work slipping. |
| Negative | Negative | Behind and over budget. This is the worked example. |
These readings are hypotheses to investigate, not conclusions. The variance tells you that something differs from the plan, not why.
Edge cases and gotchas
SV converges to zero at the end
PV rises to BAC by the planned finish date. If the project is late, EV is still below BAC at that date, so SV is negative. When the project finally completes, EV reaches BAC and equals PV, so SV becomes exactly zero, even though the project finished late. A zero SV on a finished project says nothing about whether it was on time. The same distortion affects SPI, and a later chapter on its limitations covers it.
CV does not converge
AC is not capped at BAC. At completion, CV = BAC − final AC. This is the final cost overrun or underrun, so CV remains meaningful to the end.
Timing of cost recording
AC only counts costs that are recorded by the status date. If invoices arrive late, AC is understated, and CV looks better than reality. Agree on whether AC includes accruals, meaning costs incurred but not yet invoiced. Without accruals, a strongly positive CV early in a project is often a data artifact.
EV depends on how you measure progress
SV and CV are only as accurate as EV. A generous percent-complete estimate raises EV and improves both variances at once. Fixed-formula methods such as 0/100 are harder to inflate than subjective estimates.
Variance of work not in the baseline
Work that was not in the baseline has no PV and no EV against it. If the team spends effort on it, AC rises and CV drops, but SV is unaffected. Handle such work through change control, which updates the baseline, rather than leaving it to distort the variances.
Cumulative versus period values
Variances are normally reported cumulatively, from the start through the status date. A period variance covers only one reporting period. You can compute it as the change in the cumulative variance, but do not mix the two when comparing reports.
Exercises
Exercise
A project has PV = 80,000, EV = 90,000 and AC = 85,000 at its status date. Calculate SV and CV, state what each means, and calculate CV as a percentage of EV.
Show answer
SV = 90,000 − 80,000 = +10,000, so the project is ahead of schedule. CV = 90,000 − 85,000 = +5,000, so the completed work cost 5,000 less than its budgeted value. CV% = 5,000 / 90,000 ≈ 5.6%.
Exercise
Two projects both report CV = −20,000. Project X has EV = 40,000 and project Y has EV = 2,000,000. Which is in worse financial shape, and why? What does this show about absolute variances?
Show answer
Project X is in worse shape. Its CV% is −20,000 / 40,000 = −50%, so it spent half again as much as the work was worth. Project Y's CV% is −1%. The same absolute variance represents very different severity, which is why ratio measures such as CPI, or percent variances, are needed for comparison across projects.
Exercise
A project finished three months after its planned end date, but its final report shows SV = 0. Explain how both facts can be true.
Show answer
At completion EV equals BAC. After the planned finish date, PV also equals BAC, so SV = EV − PV = 0. SV measures value of work against plan at a date, not elapsed time, so it returns to zero once the work is complete even though the delivery was late.