Sub topic 13
Earned schedule: a time-based alternative to SPI
This chapter assumes you can compute PV, EV, AC, SV and SPI from earlier chapters. You should also be comfortable reading a cumulative planned value (S-curve) table and doing simple linear interpolation. Earned schedule (ES) is a technique, first proposed by Walt Lipke, that replaces the dollar-based schedule measures with time-based ones. It uses the same three EVM inputs and needs no new data collection.
The problem ES solves
SPI is EV divided by PV, so it compares money with money. Schedule variance (SV = EV − PV) is also in money. A schedule question is really a time question: how many weeks are we ahead or behind?
The money-based measures also fail at the end of a project. Planned value stops growing once it reaches the budget at completion (BAC). A late project keeps earning value until EV also reaches BAC. At that moment EV = PV = BAC, so SV = 0 and SPI = 1.0, even if the project finished months late. The previous chapter covered this drift. ES removes it by asking a different question.
The idea
Earned value answers "how much work is done?" ES asks when the plan said that much work should have been done.
- Take the current EV.
- Find the point on the planned value curve where cumulative PV equals that EV.
- Read the time at that point. This time is the earned schedule (ES).
ES is the amount of planned time you have "earned" so far. Compare it with actual time (AT), the time that has elapsed on the calendar.
| Measure | Formula | Meaning |
|---|---|---|
| Earned schedule | ES = time at which PV = current EV | Planned time worth of work completed |
| Schedule variance (time) | SV(t) = ES − AT | Periods ahead (+) or behind (−) |
| Schedule performance index (time) | SPI(t) = ES / AT | Planned time earned per period elapsed |
| Independent EAC (time) | IEAC(t) = PD / SPI(t) | Forecast total duration, where PD is planned duration |
SV(t) is in the same units as your calendar, such as days, weeks or months. Read it as "we are 0.3 periods behind plan."
Calculating ES by interpolation
PV is normally reported at period ends, so you rarely have a point where PV equals EV exactly. You find the last period whose cumulative PV is at or below EV, then interpolate linearly inside the next period:
ES = C + (EV − PVC) / (PV(C+1) − PV_C)
Here C is the number of whole periods whose cumulative PV is less than or equal to EV, and PVC is the cumulative PV at the end of period C. PV(C+1) is the cumulative PV at the end of the next period.
Take the running example. The planned cumulative PV at the end of periods 1 to 6 is 10,000; 25,000; 40,000; 60,000; 80,000; and 100,000. At the end of period 3, EV is 35,000.
- Cumulative PV at the end of period 2 is 25,000, which is below 35,000.
- Cumulative PV at the end of period 3 is 40,000, which is above 35,000.
- So C = 2, and ES = 2 + (35,000 − 25,000) / (40,000 − 25,000) = 2.667 periods.
With AT = 3, SPI(t) = 2.667 / 3 = 0.889 and SV(t) = 2.667 − 3 = −0.333 periods. The project has earned about 2.667 periods of planned progress in 3 periods, so it is about a third of a period behind.
The classic SPI for the same status is 35,000 / 40,000 = 0.875, and SV is −5,000. The two indices are close here because the project is mid-stream. They separate near the end.
Code
This script computes ES, SPI(t) and SV(t), alongside classic SPI, for a seven-period history. The plan ends at period 6, and the project actually finishes at period 7.
def earned_schedule(cum_pv, ev):
"""Earned schedule in periods, using linear interpolation.
cum_pv[i] is the cumulative planned value at the end of period i + 1.
"""
prev = 0.0
for i, pv in enumerate(cum_pv):
if ev <= pv:
return i + (ev - prev) / (pv - prev)
prev = pv
return float(len(cum_pv))
cum_pv = [10_000, 25_000, 40_000, 60_000, 80_000, 100_000]
ev_history = [8_000, 20_000, 35_000, 52_000, 68_000, 85_000, 100_000]
planned_duration = len(cum_pv)
print("AT ES SPI(t) SV(t) SPI")
for at, ev in enumerate(ev_history, start=1):
pv = cum_pv[min(at, planned_duration) - 1] # PV is capped at BAC
es = earned_schedule(cum_pv, ev)
print(f"{at} {es:.3f} {es / at:.3f} {es - at:+.3f} {ev / pv:.3f}")
final_spi_t = earned_schedule(cum_pv, ev_history[-1]) / len(ev_history)
print(f"IEAC(t) at period 7 = {planned_duration / final_spi_t:.2f} periods")Running it gives these values, with ES, SPI(t), SV(t) and SPI rounded to three decimals:
| AT | EV | ES | SPI(t) | SV(t) | SPI |
|---|---|---|---|---|---|
| 1 | 8,000 | 0.800 | 0.800 | −0.200 | 0.800 |
| 2 | 20,000 | 1.667 | 0.833 | −0.333 | 0.800 |
| 3 | 35,000 | 2.667 | 0.889 | −0.333 | 0.875 |
| 4 | 52,000 | 3.600 | 0.900 | −0.400 | 0.867 |
| 5 | 68,000 | 4.400 | 0.880 | −0.600 | 0.850 |
| 6 | 85,000 | 5.250 | 0.875 | −0.750 | 0.850 |
| 7 | 100,000 | 6.000 | 0.857 | −1.000 | 1.000 |
At period 7 the script prints "IEAC(t) at period 7 = 7.00 periods", which matches the actual finish.
Where the two measures disagree
Look at the last row. The project finished its scope at period 7, one period after the plan said it would. Classic SPI reads 1.000, and SV in money is 0. ES says 6.000 periods earned in 7, so SPI(t) = 0.857 and SV(t) = −1.000 period. The time-based measure keeps reporting the delay correctly, because ES depends on where EV sits on the PV curve, and the curve keeps its shape after the plan ends.
The first line is classic SPI and the second is SPI(t). The jump of the first line at period 7 is the artefact. Nothing about the project's timing improved.
Using ES for forecasting
ES also gives a duration forecast, in the same spirit as EAC for cost. The simplest form assumes the current time efficiency continues:
IEAC(t) = PD / SPI(t)
PD is the planned duration. At period 3 in our example, SPI(t) = 0.889, so IEAC(t) = 6 / 0.889 = 6.75 periods. That is a forecast finish three-quarters of a period after plan. As the project proceeds, this forecast moves, and you can plot it as a trend.
Three cautions apply to the forecast. It assumes past efficiency predicts future efficiency, which fails if the remaining work is different in nature. It also says nothing about the critical path, so a single index cannot replace schedule network analysis. Finally, early in a project the index is noisy, so treat early IEAC(t) values as rough.
Gotchas and edge cases
- Resolution of the PV curve. Linear interpolation assumes PV accrues evenly inside each period. If the plan front-loads work inside a period, ES is slightly off. Use finer period granularity, such as weekly instead of monthly, when accuracy matters.
- Flat PV segments. If cumulative PV does not change across a period (a planned pause), several times map to the same EV. The code returns the earliest one, and the division by (pv − prev) is never reached with a zero denominator for EV above the previous level.
- Baseline changes. If you rebaseline, the PV curve changes, so ES values computed against the old and new baselines are not comparable. Keep the original baseline curve for trend history.
- EV above BAC or negative EV. Neither should occur. If your data produces either, fix the EV measurement before computing ES.
- Not a replacement for the network. ES uses aggregate PV, so work done off the critical path counts the same as critical-path work. A project can show a healthy SPI(t) while a critical task slips. Use ES as an early warning alongside critical path analysis.
Exercise
A project has cumulative planned value at the end of periods 1 to 6 of 10,000; 25,000; 40,000; 60,000; 80,000; and 100,000. At the end of period 4 the earned value is 30,000. Calculate ES, SPI(t) and SV(t), and compare SPI(t) with classic SPI.
Show answer
Cumulative PV at the end of period 2 is 25,000 (below 30,000), and at the end of period 3 it is 40,000 (above 30,000), so C = 2. ES = 2 + (30,000 − 25,000) / (40,000 − 25,000) = 2.333 periods. With AT = 4, SPI(t) = 2.333 / 4 = 0.583 and SV(t) = 2.333 − 4 = −1.667 periods. Classic SPI = EV / PV = 30,000 / 60,000 = 0.500. Both indices show a serious delay. SPI(t) says the project has earned 2.333 periods of planned work in 4 periods, so it is about 1.7 periods behind.
Exercise
A project planned for 6 periods finishes all its scope at the end of period 8. What are classic SPI and SPI(t) at that point, and why do they differ?
Show answer
Classic SPI = EV / PV = 100,000 / 100,000 = 1.0, because PV is capped at BAC after the plan ends and EV has now reached BAC. ES = 6 (the time at which planned value first equals BAC), so SPI(t) = 6 / 8 = 0.75 and SV(t) = −2 periods. They differ because classic SPI compares money at a single moment, and both values equal BAC at completion. ES compares the time the plan needed with the time actually taken, so it still shows the two-period delay.