Sub topic 10
Forecasting final cost with EAC and ETC
This chapter assumes you can compute planned value (PV), earned value (EV), actual cost (AC), and the Cost Performance Index (CPI = EV / AC) and Schedule Performance Index (SPI = EV / PV). It also assumes you know that BAC is the budget at completion, the total of the performance measurement baseline. Here you turn those measurements into a forecast of what the project will cost when it finishes.
Why forecast at all
CPI and SPI describe the past. A sponsor usually wants to know three things: what the project will cost in total, how much more money is needed, and whether it will finish inside the approved budget. Earned value management answers these with three quantities.
| Quantity | Name | Meaning |
|---|---|---|
| EAC | Estimate at completion | Forecast total cost of the project when it ends |
| ETC | Estimate to complete | Forecast cost of the work still to be done |
| VAC | Variance at completion | BAC − EAC. A negative value is a forecast overrun |
The relationships between them are simple:
- EAC = AC + ETC. What you have spent plus what you expect to spend.
- ETC = EAC − AC.
- VAC = BAC − EAC.
The hard part is estimating ETC, because it depends on a judgment: will the remaining work be performed at the same efficiency as the work so far?
The running example
The same status date is used throughout:
- BAC = 100,000
- PV = 40,000
- EV = 35,000
- AC = 42,000
So CPI = 35,000 / 42,000 = 0.833 and SPI = 35,000 / 40,000 = 0.875. The project has earned 35,000 of work and spent 42,000 to do it. The work remaining, in budget terms, is BAC − EV = 65,000.
Three assumptions, three formulas
The PMBOK Guide family of standards lists several EAC formulas. Each encodes a different assumption about the future. Choosing between them is the main skill in this chapter.
Atypical variance: EAC = AC + (BAC − EV)
Use this when the overrun so far came from a one-off event that will not repeat, such as a rejected delivery, a rework cycle, or a price spike that has since ended. You assume the remaining work will be done at the original budgeted rate.
With the example: 42,000 + 65,000 = 107,000. The overrun of 7,000 so far is kept, and nothing more is added.
Typical variance: EAC = BAC / CPI
Use this when the cost efficiency so far is representative of the future. This is the most common default. It is the same as EAC = AC + (BAC − EV) / CPI, so the remaining work is also done at the current CPI.
With the example: 100,000 / 0.833 = 120,000. Then ETC = 120,000 − 42,000 = 78,000, which is 65,000 / 0.833. The remaining 65,000 of budgeted work is expected to cost 78,000.
Cost and schedule both matter: EAC = AC + (BAC − EV) / (CPI × SPI)
Use this when the schedule delay itself drives cost. Examples are a team on a fixed monthly burn that must be kept longer, or a crash schedule that pays overtime to recover time. The product CPI × SPI is a blended efficiency.
With the example: CPI × SPI = 0.833 × 0.875 = 0.729. Remaining work: 65,000 / 0.729 ≈ 89,143. EAC ≈ 42,000 + 89,143 = 131,143.
Bottom-up: EAC = AC + a new estimate for the remaining work
When the original estimate is no longer credible, the people doing the work re-estimate what is left, task by task. This takes more effort than a formula and is the most defensible when the baseline has been overtaken by events, such as a scope change or a technology switch. Use the formula results as a sanity check on the bottom-up number. If they differ widely, find out why.
Choosing a formula
Whatever you choose, record the assumption next to the number. A forecast of 120,000 means little unless the reader knows it assumes the current efficiency continues.
Computing the forecasts in code
The script below calculates all three formula-based forecasts, plus ETC and VAC for each.
def eac_forecasts(bac, pv, ev, ac):
"""Return EAC, ETC and VAC for each formula-based assumption."""
cpi = ev / ac
spi = ev / pv
remaining = bac - ev # budgeted value of the work still to do
eac = {
"atypical (AC + BAC - EV)": ac + remaining,
"typical (BAC / CPI)": bac / cpi,
"CPI x SPI": ac + remaining / (cpi * spi),
}
return {
name: {"EAC": value, "ETC": value - ac, "VAC": bac - value}
for name, value in eac.items()
}
results = eac_forecasts(bac=100_000, pv=40_000, ev=35_000, ac=42_000)
for name, r in results.items():
print(f"{name:26} EAC={r['EAC']:>9,.0f} ETC={r['ETC']:>8,.0f} VAC={r['VAC']:>8,.0f}")The output is:
atypical (AC + BAC - EV) EAC= 107,000 ETC= 65,000 VAC= -7,000
typical (BAC / CPI) EAC= 120,000 ETC= 78,000 VAC= -20,000
CPI x SPI EAC= 131,143 ETC= 89,143 VAC= -31,143The range from 107,000 to 131,143 is the useful message. Even with the same data, the forecast depends on what you believe about the future. Presenting the range, with the assumption behind each end, is more honest than presenting one number with false precision.
Checking the forecast with TCPI
The To-Complete Performance Index states the efficiency the remaining work must achieve to hit a target:
- To finish on the original budget: TCPI = (BAC − EV) / (BAC − AC) = 65,000 / 58,000 = 1.121.
- To finish on a revised forecast: TCPI = (BAC − EV) / (EAC − AC).
With the typical forecast, (BAC − EV) / (EAC − AC) = 65,000 / 78,000 = 0.833, which equals the current CPI. That is not a coincidence: the typical formula is defined by assuming future CPI equals current CPI.
TCPI gives a plausibility test. The project is at CPI 0.833, and finishing on budget needs 1.121 for the rest of the work. That is a 35 percent improvement in efficiency (1.121 / 0.833 ≈ 1.35). Projects rarely achieve such a jump, so the BAC target is probably unrealistic unless something concrete has changed.
Common errors
- Using BAC / CPI when the baseline is stale. If scope has been approved but the BAC has not been updated, every formula inherits the error. Fix the baseline first.
- Forgetting that EAC includes AC. ETC is the remaining cost only. Reporting ETC as the total forecast understates the cost by the amount already spent.
- Applying the typical formula very early. CPI in the first few percent of a project is based on little work. A few early invoices, or a single package, can swing it. Treat early forecasts as provisional.
- Mixing units. EV, AC and BAC must all be in the same currency or labor-hour unit, at the same point in time. Mixing hours for AC with money for BAC gives a meaningless CPI.
- Ignoring accruals. AC that omits received but uninvoiced work makes CPI look better than it is, and the forecast comes out too low.
- Dividing by zero. CPI is undefined when AC is 0, and TCPI is undefined when BAC equals AC. Guard for these cases in tools and spreadsheets.
- Treating EAC as a commitment. It is a forecast. Update it at every status date, and keep the previous values so you can show how it moved.
Working with partial information
Sometimes only some of the baseline is usable. Two common situations:
- A fixed-price contract. The customer pays a fixed amount, so the forecast that matters to the contractor is margin, not total cost. Compare EAC with the contract price. VAC measured against price shows the expected profit or loss.
- A deliverable with a known remaining cost. If a supplier quotes 30,000 for the remaining part of a work package, use that quote as the ETC for the package and add it to AC. Mix quotes and formulas across work packages, then sum for a project-level EAC.
In both cases the identity EAC = AC + ETC holds. Only the source of ETC changes.
Summary of the chapter's formulas
| Situation | EAC formula | Example result |
|---|---|---|
| Overrun was a one-off | AC + (BAC − EV) | 107,000 |
| Current efficiency continues | BAC / CPI | 120,000 |
| Schedule and cost both drive the outcome | AC + (BAC − EV) / (CPI × SPI) | 131,143 |
| Baseline no longer valid | AC + new bottom-up ETC | Depends on the estimate |
Exercise
A project has BAC = 200,000, EV = 80,000, AC = 100,000 and PV = 90,000. (a) Compute CPI and the typical-variance EAC (BAC / CPI). (b) Compute ETC and VAC for that EAC. (c) Compute the EAC if the overrun was a one-off.
Show answer
(a) CPI = 80,000 / 100,000 = 0.8. EAC = 200,000 / 0.8 = 250,000. (b) ETC = 250,000 − 100,000 = 150,000, which equals the remaining budgeted work (200,000 − 80,000 = 120,000) divided by 0.8. VAC = 200,000 − 250,000 = −50,000, a forecast overrun of 50,000. (c) One-off: EAC = AC + (BAC − EV) = 100,000 + 120,000 = 220,000, so VAC = −20,000.
Exercise
For the same project in the previous exercise, compute TCPI to finish on the original BAC. Is that target realistic given the current CPI?
Show answer
TCPI = (BAC − EV) / (BAC − AC) = 120,000 / 100,000 = 1.2. The project has run at CPI 0.8, so it would need to work 50 percent more efficiently (1.2 / 0.8 = 1.5) for the rest of the project. That is unlikely without a concrete change, so a forecast of 250,000 or 220,000 is more credible than 200,000.