Sub topic 9
Reading SPI and CPI together
This chapter assumes you can compute planned value (PV), earned value (EV) and actual cost (AC). It also assumes you know that SPI is EV divided by PV and CPI is EV divided by AC. Here you learn to read the two indices as a pair, check what they leave out, and turn them into a status statement you can defend.
Why one index is not enough
SPI and CPI use the same numerator, EV, but different denominators. SPI compares work accomplished with work planned. CPI compares work accomplished with money spent. Each index answers one question, and neither answers the other.
- SPI answers: "Did we accomplish as much as we planned to by now?"
- CPI answers: "How much value did we get for each unit of money spent?"
A project can score well on one and badly on the other. A team that adds people can raise SPI and lower CPI in the same period. A team that cuts costs by pausing work can do the opposite. The status is only clear when you look at both.
The four basic combinations
For each index, a value above 1.0 is favorable, 1.0 is on plan, and below 1.0 is unfavorable. Combining the two gives four situations.
| SPI | CPI | Status | Typical cause |
|---|---|---|---|
| Above 1.0 | Above 1.0 | Ahead of schedule, under budget | Good estimates, productive team, or padded baseline |
| Above 1.0 | Below 1.0 | Ahead of schedule, over budget | Overtime, extra staff, or expensive resources used to buy speed |
| Below 1.0 | Above 1.0 | Behind schedule, under budget | Under-staffing, waiting on dependencies, or work not yet started |
| Below 1.0 | Below 1.0 | Behind schedule, over budget | Underestimated scope, rework, or low productivity |
The table gives a starting hypothesis. The cause column lists common explanations, and you still have to check which one applies.
A worked example
Take a project with a budget at completion (BAC) of 100,000. At the status date, PV is 40,000, EV is 35,000 and AC is 42,000.
- SPI = 35,000 / 40,000 = 0.875
- CPI = 35,000 / 42,000 = 0.833
- SV = EV − PV = −5,000
- CV = EV − AC = −7,000
Both indices are below 1.0, so the project is behind schedule and over budget. In plain terms, the team has done 87.5% of the work it planned to do. Each unit of money spent has produced about 0.83 units of planned value.
The two measures are related but not the same. The schedule gap is 5,000 of work. The cost gap is 7,000. The cost gap is larger because the project is both behind and paying more than planned for the work it did finish.
The next four cases show how the same information changes the story.
| Case | PV | EV | AC | SPI | CPI | Reading |
|---|---|---|---|---|---|---|
| A | 60,000 | 66,000 | 55,000 | 1.100 | 1.200 | Ahead, under budget |
| B | 50,000 | 55,000 | 62,000 | 1.100 | 0.887 | Ahead, over budget |
| C | 50,000 | 45,000 | 40,000 | 0.900 | 1.125 | Behind, under budget |
| D | 40,000 | 35,000 | 42,000 | 0.875 | 0.833 | Behind, over budget |
Cases B and C show why a single index misleads. In case B the schedule looks healthy, but each unit of progress costs more than planned. In case C the budget looks healthy, but the project may have saved money only because work has not been done.
Classifying status in code
The function below turns a pair of indices into a status sentence. It uses a tolerance band, because an index of 0.98 usually does not justify a different report from 1.00.
SCHEDULE = {"above": "ahead of schedule",
"on": "on schedule",
"below": "behind schedule"}
COST = {"above": "under budget",
"on": "on budget",
"below": "over budget"}
def band(index, tol=0.05):
"""Place an index in a band around 1.0."""
if index > 1 + tol:
return "above"
if index < 1 - tol:
return "below"
return "on"
def status(spi, cpi, tol=0.05):
return f"{SCHEDULE[band(spi, tol)]}, {COST[band(cpi, tol)]}"
cases = {
"A": (60_000, 66_000, 55_000),
"B": (50_000, 55_000, 62_000),
"C": (50_000, 45_000, 40_000),
"D": (40_000, 35_000, 42_000),
}
for name, (pv, ev, ac) in cases.items():
spi, cpi = ev / pv, ev / ac
print(f"{name}: SPI {spi:.3f}, CPI {cpi:.3f} -> {status(spi, cpi)}")The tolerance is a policy choice, not a mathematical fact. Many organizations set it per project in the performance reporting plan, often with separate amber and red thresholds.
What the combination can hide
The pair of indices is a good summary, but it has blind spots.
Cost and schedule are linked by money
An overspend on a task that is ahead of schedule and an overspend on a task that is behind schedule give the same CPI contribution. The index does not say which tasks produced the variance. Always drill down from the total to the control accounts or work packages where the variance sits.
SPI is measured in money, not time
SPI compares two cost-based quantities. EV and PV are both expressed as budget. A work package with a large budget moves SPI more than a small one, even if the small one is on the critical path. A project can show an SPI of 1.0 while a critical task is late, because other, non-critical work is ahead. Check SPI against the schedule network, not instead of it.
SPI drifts toward 1.0 at the end
When a project finishes, EV reaches BAC and PV also reaches BAC, so SPI becomes exactly 1.0 even if the project finished months late. Late in a project, an SPI near 1.0 therefore says very little. A later chapter covers this problem and the earned schedule method that corrects it. For now, treat late-project SPI with caution.
CPI is more stable than SPI
Studies of completed projects show that CPI tends to stay within a narrow range once a project is about 20% complete. A CPI of 0.83 at that point is a strong warning that the final cost will also run about 20% over. This is why CPI is used to forecast final cost, covered in the forecasting chapter.
Quality of EV decides quality of the indices
Both indices depend on how EV is measured. If the team claims 90% complete on a task that is really 60% complete, SPI and CPI will both be too high. A bad EV figure distorts both indices in the same direction, so their agreement with each other does not confirm that they are right.
From reading to action
Use the pair of indices to decide where to look first, not what to do.
- Behind and over budget: look for scope that was underestimated or work that needed rework. Check whether CPI has been low for several periods, which means the cost problem is a trend and not a one-off.
- Ahead and over budget: check whether the extra cost bought the schedule gain on purpose. If it did not, ask whether the gain is real or whether early work is being claimed too generously.
- Behind and under budget: check whether people or materials are missing. The underspend is not a saving if the work is waiting.
- Ahead and under budget: check the baseline. A plan that is consistently beaten may have been padded, and the result may reflect the estimate and not good performance.
Common errors
- Reading CPI below 1.0 as "behind schedule." CPI is about cost, and SPI is about schedule.
- Reading SPI above 1.0 as good news without checking CPI. Faster work that costs more may or may not be wanted.
- Treating 0.99 and 1.01 as different statuses. Use a tolerance band.
- Comparing indices from different projects without checking that they use the same EV method.
- Using SPI as the only schedule check late in a project.
Exercise
A project has PV = 80,000, EV = 72,000 and AC = 66,000 at the status date. Compute SPI, CPI, SV and CV, and state the status in one sentence.
Show answer
SPI = 72,000 / 80,000 = 0.900. CPI = 72,000 / 66,000 = 1.091. SV = 72,000 − 80,000 = −8,000. CV = 72,000 − 66,000 = +6,000. The project is behind schedule and under budget. Before treating the underspend as a saving, check whether work is waiting for people or materials.
Exercise
Near the end of a project, SPI is 1.00 and CPI is 0.80. A stakeholder says "the schedule is fine, so we only have a cost problem." What two points would you make in reply?
Show answer
First, CPI of 0.80 means each unit of money spent has produced only 0.80 units of planned value, so the final cost is likely to run about 25% over the plan if the trend continues (1 / 0.80 = 1.25). Second, SPI drifts toward 1.0 as a project ends because EV and PV both converge on BAC, so an SPI of 1.00 this late does not prove the schedule is fine. The critical path and a time-based measure such as earned schedule should be checked.