Sub topic 5
Measuring earned value: 0/100, 50/50, weighted milestones and percent complete
This chapter covers how to assign earned value (EV) to a work package. It assumes you know the following:
- What planned value (PV), EV and actual cost (AC) mean.
- That budget at completion (BAC) is the total budget.
- How a work breakdown structure (WBS) splits a project into work packages.
EV is the budgeted value of the work actually completed. The budget is fixed. The judgment is how much of it you have "earned" while a package is still in progress. The rule you choose changes SPI and CPI, so you should pick it before work starts.
Why the method matters
Take a work package with a budget of 10,000. It is half done by effort, but nothing has been delivered. Depending on the rule, its EV could be 0, 5,000 or something else. SPI is EV divided by PV, and CPI is EV divided by AC. Both indices move with that choice.
A good method has three properties:
- It is objective. Two people looking at the same evidence reach the same EV.
- It is cheap to apply. Status reporting should not cost more than the value it provides.
- It is hard to game. Reported progress should not rise just because someone is optimistic.
The four common methods
0/100 rule
The package earns nothing until it is complete. At completion it earns 100% of its budget.
- Use it for short packages, such as those under one reporting period, and for discrete deliverables like a purchased item or a signed approval.
- Strength: no subjective progress estimate.
- Weakness: on long packages, EV stays at 0 while AC grows, so CPI looks terrible until the finish.
50/50 rule
The package earns 50% when it starts and the other 50% when it finishes.
- Use it for medium-length packages, usually one to two reporting periods, where starting is a real event.
- Strength: it is simple, and it gives some credit for progress.
- Weakness: it gives credit for starting, so SPI and CPI can look better than the real progress. It also hides the state of a package that is "started" but stuck.
Some organizations use variants such as 25/75 or 20/80. The idea is the same: a fixed share at the start and the rest at completion.
Weighted milestones
You split the package into milestones that can be verified. Each milestone gets a share of the package budget. EV is the sum of the shares of the milestones completed.
- Use it for longer packages, usually longer than two reporting periods, where intermediate outputs can be checked.
- Strength: credit is tied to evidence, such as an approved design or a passed test.
- Weakness: the weights need care. A milestone weight should reflect the effort behind it, not how easy it is to declare done.
Example: a 20,000 package for a report module.
| Milestone | Weight | Budget | Done? | EV |
|---|---|---|---|---|
| Design approved | 20% | 4,000 | Yes | 4,000 |
| Code complete | 40% | 8,000 | Yes | 8,000 |
| Tests passed | 25% | 5,000 | No | 0 |
| Accepted by client | 15% | 3,000 | No | 0 |
EV is 12,000, which is 60% of the package. A milestone earns nothing until it is finished. Half-done testing earns 0 until the tests pass.
Percent complete
Someone estimates the percentage of work done, and EV is that percentage multiplied by the package budget.
- Use it when no verifiable milestones exist, for example for level-of-effort-like technical work, but apply it carefully.
- Strength: it is flexible and works for any package.
- Weakness: it is subjective. People often report 90% for a long time, a pattern known as the "90% syndrome", where the last 10% takes as long as the first 90%.
You can reduce the subjectivity by calculating percent complete from measurable units, such as meters of cable laid out of the total required, or test cases passed out of the total. This is sometimes called the units-completed method. It is more objective than a gut estimate.
Choosing a method
| Package characteristic | Suggested method |
|---|---|
| Duration under one period, single deliverable | 0/100 |
| One to two periods, clear start event | 50/50 |
| Longer than two periods, verifiable interim outputs | Weighted milestones |
| Countable units of output | Units completed (percent complete) |
| No verifiable outputs | Percent complete with a cap or review |
Worked example: same work, four methods
A 10,000 package has run for one period. The plan called for PV of 6,000 at this date. The team spent AC of 5,000. The work has started, and the first two of four equal milestones are done. By effort, the team judges it 45% complete.
| Method | EV | SPI (EV / 6,000) | CPI (EV / 5,000) |
|---|---|---|---|
| 0/100 | 0 | 0.000 | 0.000 |
| 50/50 | 5,000 | 0.833 | 1.000 |
| Weighted milestones (2 of 4, 25% each) | 5,000 | 0.833 | 1.000 |
| Percent complete (45%) | 4,500 | 0.750 | 0.900 |
The same work yields a CPI between 0.000 and 1.000. The data did not change. Only the rule did.
You can check this in code:
def ev_by_method(budget, method, **kw):
"""Return earned value for one work package under a given rule."""
if method == "0/100":
return budget if kw["complete"] else 0.0
if method == "50/50":
if kw["complete"]:
return budget
return budget * 0.5 if kw["started"] else 0.0
if method == "milestones":
# kw["weights"] maps milestone name -> weight (sum to 1.0)
return budget * sum(w for name, w in kw["weights"].items()
if name in kw["done"])
if method == "percent":
return budget * kw["pct"]
raise ValueError(f"unknown method: {method}")
budget, pv, ac = 10_000, 6_000, 5_000
weights = {"m1": 0.25, "m2": 0.25, "m3": 0.25, "m4": 0.25}
cases = {
"0/100": dict(complete=False),
"50/50": dict(complete=False, started=True),
"milestones": dict(weights=weights, done={"m1", "m2"}),
"percent": dict(pct=0.45),
}
for method, kw in cases.items():
ev = ev_by_method(budget, method, **kw)
print(f"{method:<10} EV={ev:>7,.0f} SPI={ev / pv:.3f} CPI={ev / ac:.3f}")Edge cases and common errors
- Switching methods mid-package. Changing the rule after a poor status makes the history incomparable. Fix the method in the baseline and change it only through formal change control.
- Crediting effort instead of output. Hours spent are not EV. If a team works 200 hours and delivers nothing verifiable, EV under milestones is 0. Compare this with AC, which does record those hours.
- Rework. Rejected work should lose its EV, or its milestone should stay open. Do not keep credit for something that failed acceptance.
- Level-of-effort (LOE) work. Project management or support is measured by time passing. EV equals PV by definition, so it contributes nothing to SPI and distorts the totals. Keep LOE separate when you can, or report with and without it.
- Mixing methods in the total. Project EV is the sum of all package EVs, so a project with many 50/50 packages reports more favorable early numbers than one using 0/100. Compare projects only when the method policy is similar.
- Percent complete creep. A package reported 80% for several periods signals a problem. Set rules such as "no more than 75% credit until the test milestone passes".
Practical guidance
- Define the method for each work package when you create the baseline, and record it in the WBS dictionary or control account plan.
- Prefer 0/100 or milestones over subjective percent complete.
- Keep packages short. Many teams aim for packages no longer than two reporting periods, which makes 0/100 and 50/50 workable.
- Write down the evidence needed for each milestone before work begins.
- Review any package whose reported progress stalls for more than one period.
Exercise
A 12,000 package has four milestones weighted 10%, 30%, 40% and 20%. The first two are complete and the third is "about 75% done". The plan called for PV of 7,000, and AC is 6,000. Using weighted milestones, what are EV, SPI and CPI? What would EV be under percent complete if the team claimed 75% for the whole package?
Show answer
Under weighted milestones, only the first two milestones count: 10% + 30% = 40%, so EV = 0.40 x 12,000 = 4,800. SPI = 4,800 / 7,000 = 0.686. CPI = 4,800 / 6,000 = 0.800. The third milestone earns nothing until it is finished. Under percent complete at 75%, EV = 0.75 x 12,000 = 9,000, giving SPI = 1.286 and CPI = 1.500. The gap shows how a subjective estimate can turn a troubled package into one that looks ahead of plan.
Exercise
A 3,000 package takes five days. The reporting period is one month. Which rule suits it best, and why?
Show answer
0/100. The package starts and finishes inside one reporting period, so it will almost always be either complete or not started at the status date. Partial credit adds subjectivity without improving the picture.