Actual cost: what the work has cost so far
This chapter assumes you know what a work breakdown structure (WBS) and a budget are, and that you have met planned value and earned value in the previous chapters. It covers the third measurement, actual cost (AC): what it includes, how to cut it off at the status date, and the errors that make a cost index wrong before any division happens.
What actual cost measures
Actual cost is the total cost incurred for the work accomplished up to a status date. It is cumulative, so it starts at zero and only grows. It is also expressed in the same currency, and over the same scope, as planned value (PV) and earned value (EV).
The three measurements answer three different questions:
| Measurement | Question it answers | Source |
|---|---|---|
| PV | How much work should be done by now? | The schedule and budget baseline |
| EV | How much work is actually done, valued at its budget? | Progress reports and measurement rules |
| AC | How much did the work we did cost us? | Accounting, timesheets, invoices |
Only AC comes from outside the plan. PV and EV are both valued in budgeted money. AC is real money. This is why AC is the only one of the three that can surprise you in the finance system.
The phrase "for the work accomplished" matters. AC is not "everything we have spent on the project." It is the cost of the work that EV credits. If EV counts three work packages, AC must count the cost of those same three packages and nothing else.
What goes into AC
AC should include every cost category that your budget includes, and no others. The most common categories are:
- Labor. Hours booked to the project multiplied by the loaded rate used in the budget.
- Materials and equipment. Purchased or consumed items, or rental charges for the period used.
- Subcontractors and vendors. Work performed by outside parties.
- Allocated costs. Overhead or shared services, but only if the budget includes them.
The rule is consistency with the baseline. If the budget at completion (BAC) was built from fully loaded labor rates, AC must use loaded rates. If the budget excluded travel, AC must exclude travel, or the cost index will show a gap that is not real.
Incurred, not paid
AC records cost when the work is performed or the item is received, not when cash leaves the bank. This is accrual thinking. Three situations show the difference:
- Work done, invoice not yet received. A subcontractor finished a task on 20 November and will invoice in December. The cost belongs in November's AC. Leaving it out is called an unrecorded accrual, and it makes the project look cheaper than it is.
- Invoice paid, work not yet done. A deposit paid in advance is not AC. It is a prepayment. The cost is incurred as the work is delivered.
- Committed but not incurred. A signed purchase order is a commitment. It matters for cash planning, but it is not AC until goods or services arrive.
Some organizations track AC on a cash basis because their systems cannot do better. If so, say so in the report, because a cash-basis AC lags the real cost and flatters the CPI.
The status date cut-off
PV, EV and AC must all describe the same moment. Choose a status date, such as the close of business on Friday, and include only costs dated on or before it in AC. Progress for EV must also be measured at that date.
Three cut-off problems appear repeatedly:
- Late timesheets. Hours worked in the period but entered the following Monday are missing from a naive report. Either close the period after timesheets are in, or accrue an estimate and correct it next period.
- Invoice lag. Vendors often invoice 30 days later. Without accruals, AC trails EV, and the project looks efficient for a month or two before costs catch up.
- Mismatched dates. EV is measured on Friday but AC is pulled from a ledger closed at the previous month-end. The numerator and denominator of the cost index then describe different periods.
A worked example
The numbers below continue the example used throughout this tutorial: a project with a BAC of 100,000, a PV of 40,000 and an EV of 35,000. The status date is Friday 27 November 2026. The cost ledger holds these entries:
| Date | Work package | Amount | Description |
|---|---|---|---|
| 15 Sep | 1.1 | 12,000 | Labor |
| 2 Oct | 1.1 | 6,000 | Materials |
| 20 Oct | 1.2 | 15,000 | Labor |
| 20 Nov | 1.2 | 5,000 | Subcontractor work, accrued, invoice not yet received |
| 25 Nov | 1.3 | 4,000 | Labor |
| 2 Dec | 1.3 | 3,000 | Labor (after the status date) |
The December entry is dated after the cut-off, so it is excluded. The accrued subcontractor entry is included even though no invoice exists. The sum of the remaining five entries is 42,000, so AC = 42,000.
The code below applies the cut-off and groups cost by work package. It also shows EV for each package next to AC, so you can see where the overrun sits.
from datetime import date
STATUS_DATE = date(2026, 11, 27)
ledger = [
{"date": date(2026, 9, 15), "wp": "1.1", "amount": 12_000, "note": "labor"},
{"date": date(2026, 10, 2), "wp": "1.1", "amount": 6_000, "note": "materials"},
{"date": date(2026, 10, 20), "wp": "1.2", "amount": 15_000, "note": "labor"},
{"date": date(2026, 11, 20), "wp": "1.2", "amount": 5_000, "note": "accrued subcontractor"},
{"date": date(2026, 11, 25), "wp": "1.3", "amount": 4_000, "note": "labor"},
{"date": date(2026, 12, 2), "wp": "1.3", "amount": 3_000, "note": "labor"},
]
# Earned value per work package at the same status date.
ev = {"1.1": 15_000, "1.2": 14_000, "1.3": 6_000}
def actual_cost(entries, status_date):
"""Cumulative cost per work package, counting only entries on or before status_date."""
by_wp = {}
for entry in entries:
if entry["date"] <= status_date:
by_wp[entry["wp"]] = by_wp.get(entry["wp"], 0) + entry["amount"]
return by_wp
ac = actual_cost(ledger, STATUS_DATE)
print(f"Total AC: {sum(ac.values()):,}")
for wp in sorted(ac):
print(f"WP {wp}: AC {ac[wp]:,} EV {ev[wp]:,} EV/AC {ev[wp] / ac[wp]:.3f}")Running it prints:
Total AC: 42,000
WP 1.1: AC 18,000 EV 15,000 EV/AC 0.833
WP 1.2: AC 20,000 EV 14,000 EV/AC 0.700
WP 1.3: AC 4,000 EV 6,000 EV/AC 1.500The EV/AC ratio is the cost performance index, which a later chapter develops fully. Even here it is informative. The total of 0.833 hides a spread. Work package 1.2 is the main problem, and work package 1.3 is ahead of budget. AC is only useful at this level of detail if it is recorded per work package.
Common errors
Counting costs that earned nothing. Money spent on rework, or on work whose output was thrown away, still counts in AC. It does not raise EV, because EV credits only accepted work. This is how a project can spend heavily and show a poor CPI. That is the correct signal.
Lowering AC to make a package look good. Moving hours to another work package or to a "management reserve" code hides the overrun in one place and creates a false underrun in another. AC follows where the work happened, not where the budget room is.
Mixing scopes. If EV excludes a change request that is not yet approved but AC includes the cost of starting it, the index is misleading. Keep AC and EV aligned on the same approved scope.
Mixing cost bases. Comparing loaded-rate AC against a budget built on base salary, or the reverse, shifts the index by a fixed percentage on every report.
Ignoring the lag. In the first weeks after a status date, AC is normally understated, because late invoices and timesheets arrive afterward. A CPI that improves right after a period closes, then drops when costs catch up, usually signals missing accruals and not real efficiency.
Handling adjustments and corrections
Ledgers change after the fact. A misposted invoice is moved, a credit note arrives, or a timesheet is corrected. Treat corrections as new entries dated when they are made, or restate the affected period and note the restatement in the report. Whichever you choose, apply it consistently, because silently rewriting history makes trend charts impossible to trust.
Credits and refunds reduce AC only when they genuinely reverse a cost. A vendor refund for a returned item reduces AC. A discount for early payment is handled according to how your budget treated it. When in doubt, ask finance which treatment the baseline assumed.
Summary of the working model
- AC is the cumulative, incurred cost of the work that EV credits, at one status date.
- Include the same cost categories and rates that the budget used.
- Record cost when work is done or goods are received, with accruals for unbilled work.
- Cut off all three measurements at the same status date.
- Keep AC per work package so overruns can be located.
Exercise
A project's status date is 30 April. The ledger shows 50,000 of invoiced cost dated on or before 30 April. A subcontractor also completed 8,000 of work in April and will invoice in May. A 5,000 deposit was paid in April for equipment that will be delivered in June. A further 2,000 of timesheet cost is dated 2 May. What is AC at the 30 April status date, and why?
Show answer
AC is 58,000. It is the 50,000 invoiced cost plus the 8,000 of subcontractor work that was done in April but not yet invoiced, because cost is counted when the work is performed. The 5,000 deposit is excluded because the equipment has not been received, so no cost has been incurred. The 2,000 of timesheet cost is excluded because it is dated after the status date and belongs in the next period.
Exercise
A project manager moves 4,000 of labor hours from an overrunning work package to a package that is under budget, so that the overrunning package looks better. Which measurement is being distorted, and what effect does the move have on the cost index of each package?
Show answer
Actual cost is being distorted. Moving the cost lowers AC on the overrunning package, which raises its apparent cost index, and raises AC on the other package, which lowers its apparent cost index. The project total is unchanged, but the report now points attention at the wrong package. AC must follow where the work was actually done.