Sub topic 3
Earned value: what has actually been accomplished
Prerequisites and scope
This chapter assumes you know basic project management vocabulary: scope, schedule, budget and work breakdown structure (WBS). It also assumes you can read a project schedule and budget, and that you are comfortable with ratios and percentages.
Earlier chapters defined the performance measurement baseline and planned value (PV). This chapter covers the second of the three measurements, earned value (EV). It shows how to calculate EV, why it is the hardest of the three numbers to get right, and how to avoid the common errors. Actual cost (AC), the choice among measurement methods, and the indices built from EV come in later chapters.
What earned value measures
Earned value is the budgeted value of the work that has actually been completed as of the status date. It answers one question: "How much of the approved budget have we earned by finishing work?"
Three points define the idea.
- EV is expressed in money (or labor hours), not in time. A project that has finished work worth 35,000 of its budget has an EV of 35,000.
- EV uses the budget, not what was spent. If a task was budgeted at 5,000 and finished at a cost of 8,000, it earns 5,000. The extra 3,000 appears in AC, not EV.
- EV is measured against the same baseline as PV. Both use the same budget for each work package, so the two numbers can be compared directly.
Because EV and PV share a unit and a baseline, the difference between them tells you whether the project is ahead of or behind plan. EV and AC share the same scope of work, so comparing them tells you whether you paid more or less than planned for what you got. EV is the pivot between the other two measurements.
The basic formula
For one work package, the calculation is:
EV = percent complete × budget for that work package
For the whole project, EV is the sum of the EV of every work package at the status date. When a project reaches 100% completion, EV equals the budget at completion (BAC).
A worked example with four work packages shows the calculation.
| Work package | Budget | Percent complete | EV |
|---|---|---|---|
| Requirements | 10,000 | 100% | 10,000 |
| Design | 15,000 | 100% | 15,000 |
| Build | 40,000 | 25% | 10,000 |
| Test | 35,000 | 0% | 0 |
| Total | 100,000 | 35,000 |
The project has an EV of 35,000 out of a BAC of 100,000, so it has earned 35% of its budget. That is the same EV used in the worked example throughout this tutorial (BAC 100,000, PV 40,000, EV 35,000, AC 42,000). Since PV is 40,000, the project has earned less than planned.
def project_ev(packages):
"""Sum earned value across work packages.
Each package is a (budget, fraction_complete) pair.
"""
return sum(budget * fraction for budget, fraction in packages)
packages = [
(10_000, 1.00), # Requirements
(15_000, 1.00), # Design
(40_000, 0.25), # Build
(35_000, 0.00), # Test
]
ev = project_ev(packages)
print(f"EV = {ev:,.0f} of BAC {sum(b for b, _ in packages):,.0f}")Running this prints EV = 35,000 of BAC 100,000.
Where EV sits among the three measurements
EV links the plan and the actual spending. The diagram shows how each measurement feeds the comparisons that later chapters build.
EV appears in both comparisons. That is why an error in EV spoils both the schedule view and the cost view at once.
Earned value is not money spent
The most frequent misunderstanding is to treat EV as a spending figure. Consider two statements about the example project.
- "We have spent 42,000." This is AC.
- "We have accomplished work that the plan valued at 35,000." This is EV.
Both statements are true at the same time, and the gap between them is the point. The project paid 42,000 for work budgeted at 35,000. A report that says only "we have spent 42% of the budget" says nothing about progress, and a project can spend 90% of its budget while having done 50% of the work.
Likewise, EV is not the elapsed share of the schedule. A project that is 3 of 6 periods into its timeline has not necessarily earned 50% of its budget. EV counts finished work, not the calendar.
Assigning credit: what counts as accomplished
The formula needs a percent complete for every work package, and this is where most of the difficulty lies. A good rule is that credit should come from observable results, not from effort expended or from a team member's feeling that a task is nearly done.
Several habits distort percent complete.
- Effort-based credit. Reporting "80% complete" because 80% of the planned hours have been used. This measures consumption of resources, which is AC territory, and it hides overruns.
- The 90% syndrome. A task reaches 90% quickly and then stays at 90% for a long time. Optimistic estimates make early EV too high and then stall.
- Credit for work not meeting the acceptance criteria. If a deliverable needs rework before it can be accepted, the rework portion has not been earned.
- Credit for materials or deliverables not yet usable. Buying parts is a cost event. Whether it earns value depends on the rules you set for that work package.
To limit these problems, define the criteria for each work package in advance. Write down what "done" means, who confirms it, and which interim steps carry credit. A later chapter compares the standard measurement rules (0/100, 50/50, weighted milestones and percent complete) and when to choose each. For now, remember that the rule must be fixed before work starts, so that credit cannot be adjusted to make the numbers look better.
Cumulative values and status dates
EV, like PV and AC, is normally tracked as a cumulative figure. The value at a status date is the total earned from the start of the project to that date, not the amount earned in the latest period.
Suppose the project records these period results.
| Period | EV earned in period | Cumulative EV |
|---|---|---|
| 1 | 8,000 | 8,000 |
| 2 | 9,000 | 17,000 |
| 3 | 18,000 | 35,000 |
At the end of period 3, the cumulative EV is 35,000. That is the number compared with cumulative PV (40,000) and cumulative AC (42,000) at the same date. Mixing a period figure for one measurement with a cumulative figure for another is a common spreadsheet mistake and produces meaningless ratios.
All three measurements must also use the same status date. If AC comes from an accounting close on the 25th and EV from a progress review on the 30th, the comparison covers different slices of work.
Edge cases
Several situations call for a deliberate decision rather than a default.
- Approved changes to scope. When a change is approved, the baseline and BAC change, and PV and EV must be restated consistently. If you add the new work to BAC but earn nothing for it until it is done, the numbers stay honest. If you change the baseline to hide a variance, they do not.
- Rework. Work that was credited and later fails inspection should not be credited a second time. Decide in advance whether to reverse the earlier credit or to record the rework as extra cost with no added EV. The second approach keeps EV non-decreasing, which is easier to audit, but both must be documented.
- Level of effort activities. Project management, quality oversight and similar support work have no discrete output. Many organizations set their EV equal to PV, so they never produce a schedule variance on their own. Keep these activities separate in reporting so they do not dilute the signal from measurable work.
- Work done out of sequence. EV counts completed work regardless of order. Finishing easy, low-budget tasks first raises the count of tasks done but not necessarily EV, which is weighted by budget. The measure rewards finishing the valuable work, not the quantity of tasks.
- Completed work with zero budget. Work with no budget in the baseline cannot earn value. If it is necessary, it is a scope change, and it should go through change control.
Common errors
- Using spent money in place of EV.
- Using hours consumed in place of progress made.
- Reporting EV from a different date than PV or AC.
- Giving credit for partial work on a package that uses an all-or-nothing rule.
- Letting EV exceed the work package budget, which is impossible for a single package and signals a data entry error.
- Changing the percent complete rule after problems appear.
A simple check is to confirm, for each package, that 0 ≤ EV ≤ budget, and that cumulative EV never falls without a documented reason.
def check_ev(packages_ev, packages_budget, previous_total_ev):
"""Return a list of problems found in reported EV values."""
problems = []
for name, ev in packages_ev.items():
budget = packages_budget[name]
if ev < 0 or ev > budget:
problems.append(f"{name}: EV {ev:,.0f} outside 0..{budget:,.0f}")
total = sum(packages_ev.values())
if total < previous_total_ev:
problems.append(
f"Total EV fell from {previous_total_ev:,.0f} to {total:,.0f}"
)
return problems
budgets = {"Requirements": 10_000, "Design": 15_000, "Build": 40_000, "Test": 35_000}
reported = {"Requirements": 10_000, "Design": 15_000, "Build": 10_000, "Test": 0}
print(check_ev(reported, budgets, previous_total_ev=17_000) or "No problems found")This prints No problems found because every package lies within its budget and total EV rose from 17,000 to 35,000.
Why this matters for SPI and CPI
EV is the numerator of both indices. SPI is EV divided by PV, and CPI is EV divided by AC. If EV is overstated by 10%, both indices rise by the same 10%, and a project that is in trouble looks healthy. An index is only as reliable as the progress data behind it, so the most valuable effort in earned value practice goes into measuring EV honestly.
Exercise
A work package has a budget of 20,000 and is judged 60% complete. The team has spent 15,000 on it. What is its EV, and what does the 15,000 represent?
Show answer
EV = 0.60 × 20,000 = 12,000. The 15,000 is the actual cost (AC) of the package. It does not change EV, which depends only on the budget and the percent complete. Here the package has cost 3,000 more than the value earned.
Exercise
A project reports, at the end of period 4, a period EV of 6,000 and a cumulative PV of 55,000. A analyst divides 6,000 by 55,000 to get an index of 0.11 and concludes the project is badly behind. What mistake was made, and what should be compared instead?
Show answer
The analyst compared a period figure (EV earned in period 4) with a cumulative figure (PV to date). Both must be cumulative at the same status date. The correct comparison uses cumulative EV through period 4 divided by cumulative PV of 55,000.