Trends, thresholds and honest reporting
This chapter assumes you can already calculate SPI, CPI, SV and CV from PV, EV and AC. It also assumes you know how EAC is forecast from CPI. Here the question changes from how to calculate the numbers to how to report them so that readers draw the right conclusion.
Why one data point is not a status
A single SPI or CPI value is a ratio of two cumulative totals on one date. It says nothing about direction. A CPI of 0.92 can belong to a project that is recovering from 0.80 or to one that is sliding from 1.05. The two projects need different responses, but the single number looks the same.
Index values are also noisy. A supplier invoice booked one week late makes AC look low, so CPI looks better than it is. The next week the invoice arrives and CPI drops. Reading either week alone gives the wrong impression.
For these reasons, report each index as a series over time, never as a single value.
Cumulative and period indices
Two versions of each index are in common use.
- The cumulative index uses totals from the project start to the status date. It is the standard form, and it is the one used for EAC forecasts.
- The period index (or rolling index) uses only the work and cost inside a recent window, such as the last three periods. It reacts quickly to change.
Cumulative values are stable, but they carry the whole history and so respond slowly. A project that was badly over budget early and is now efficient will show a cumulative CPI below 1.0 for a long time. A rolling CPI shows the recovery sooner. The opposite case is more dangerous: a cumulative CPI that still looks acceptable can hide a recent slide that the rolling CPI shows at once.
Report both, and label each clearly.
Computing a trend table
The script below computes cumulative SPI, cumulative CPI and a three-period rolling CPI for six weekly status dates. It also assigns a status colour using thresholds. The figures describe a project with a budget at completion of 100,000.
BAC = 100_000
PV = [8_000, 18_000, 30_000, 44_000, 60_000, 76_000]
EV = [8_000, 17_000, 27_000, 38_000, 51_000, 64_000]
AC = [8_000, 17_500, 29_000, 42_000, 57_000, 73_000]
WINDOW = 3
def rag(index, amber=0.95, red=0.90):
"""Map an index to GREEN, AMBER or RED using fixed thresholds."""
index = round(index, 3) # compare at the precision we report
if index >= amber:
return "GREEN"
if index >= red:
return "AMBER"
return "RED"
def window_ratio(ev0, ac0, k, window):
"""EV earned divided by cost spent in the last `window` periods."""
base = max(0, k - window)
return (ev0[k] - ev0[base]) / (ac0[k] - ac0[base])
ev0 = [0] + EV # prepend the zero at project start
ac0 = [0] + AC
print("Week SPI CPI CPI(3wk) Status")
for k in range(1, len(PV) + 1):
spi = EV[k - 1] / PV[k - 1]
cpi = EV[k - 1] / AC[k - 1]
rolling = window_ratio(ev0, ac0, k, WINDOW)
status = rag(min(spi, cpi))
print(f"{k:>4} {spi:6.3f} {cpi:6.3f} {rolling:8.3f} {status}")
final_cpi = EV[-1] / AC[-1]
print(f"EAC at cumulative CPI: {BAC / final_cpi:,.0f}")
print(f"EAC at 3-week CPI: {BAC / window_ratio(ev0, ac0, 6, WINDOW):,.0f}")Running it gives these values:
| Week | SPI | CPI | CPI (3 weeks) | Status |
|---|---|---|---|---|
| 1 | 1.000 | 1.000 | 1.000 | GREEN |
| 2 | 0.944 | 0.971 | 0.971 | AMBER |
| 3 | 0.900 | 0.931 | 0.931 | AMBER |
| 4 | 0.864 | 0.905 | 0.882 | RED |
| 5 | 0.850 | 0.895 | 0.861 | RED |
| 6 | 0.842 | 0.877 | 0.841 | RED |
The last two lines of output are the forecasts: an EAC of about 114,063 from the cumulative CPI and about 118,919 from the three-week CPI.
Notice that the rolling CPI falls faster than the cumulative CPI. By week 6 the recent efficiency (0.841) is clearly worse than the cumulative figure (0.877). The cumulative number alone understates how bad the current run rate is.
The chart makes the pattern plain: six consecutive declines. No single weekly row shows this as clearly as the picture does.
Thresholds
A threshold is a pre-agreed index value that triggers a defined response. Thresholds turn the numbers into decisions, because they decide who has to act and when.
A common scheme looks like this:
| Index range | Status | Typical response |
|---|---|---|
| 0.95 and above | Green | Report and continue |
| 0.90 to 0.949 | Amber | Project manager investigates and explains the cause |
| Below 0.90 | Red | Escalate to the sponsor with a recovery plan |
Some guidance for setting them:
- Agree them before the project starts. Thresholds chosen after a bad result tend to be chosen to fit the result.
- Do not treat 0.95 and 0.90 as universal. Organisations and contracts set their own. Some government programmes use plus or minus 10 percent; others use tighter bands.
- Define the comparison precisely. Decide whether you compare the cumulative or rolling index, and whether you round first. The script rounds to three decimals, so 0.8996 does not turn amber and red on different days depending on floating-point noise.
- Combine the two indices. The script uses the lower of SPI and CPI. You can also colour schedule and cost separately and show both.
- Allow for project phase. Early in a project, small absolute amounts produce large swings in the ratio. Some teams apply wider bands in the first 10 to 15 percent.
Thresholds are triggers for a conversation, not verdicts. An amber CPI caused by one late invoice needs an explanation. It does not need a recovery plan.
What trends tell you
Look for these patterns.
- Steady decline (as above) points to a systemic cause such as a bad estimate or unrealistic productivity assumptions. It will not fix itself.
- A sudden step down usually points to a discrete event, such as rework, a scope misunderstanding or a price change. Find the event.
- A sudden step up deserves suspicion as much as concern. Check whether EV was claimed early or costs were not yet booked.
- Stable but below 1.0 means a past problem has stopped growing. The overrun is baked in. Use the cumulative CPI for the forecast unless you can show why future work will differ.
Be cautious about expecting recovery. Studies of large defence programmes reported that cumulative CPI by about 20 percent complete rarely improved by more than roughly 10 percent by the end. Treat this as a warning against optimism, not a law. If a team forecasts a CPI well above its history, require evidence for the change.
Honest reporting
The indices are only as reliable as the measurements behind them. Several practices keep reports credible.
- State how EV was measured. For each work package, say whether you used 0/100, 50/50, weighted milestones or percent complete. A report that uses subjective percent complete deserves less trust than one built on 0/100 milestones.
- Check AC completeness. Confirm that accruals cover received but not yet invoiced work. Missing costs flatter CPI.
- Show the forecast range. Give EAC from the cumulative CPI and from the recent CPI, as the script does. A range is more honest than a single number that hides an assumption.
- Watch for the 90 percent syndrome. Work reported as 90 percent complete for several periods is a sign that percent complete is being guessed.
- Be careful with SPI late in the project. As the project ends, SPI drifts toward 1.0 even for late projects, so a good-looking late SPI proves little. Use earned schedule, or check the critical path directly.
- Disclose baseline changes. If the baseline was changed, say so and state the effect. Resetting the baseline to erase a variance and then reporting a clean 1.0 is misleading.
- Keep the history. Do not overwrite earlier status dates. The trend is part of the report.
Common errors
- Reporting only the latest value, with no history.
- Mixing cumulative and period indices in the same table without labels.
- Using a rolling CPI in the EAC formula without saying so.
- Changing thresholds mid-project.
- Reading SPI above 1.0 as good news without checking that the early work was on the critical path.
- Treating a one-period improvement as a recovery.
Exercise
At week 3 the cumulative figures are EV 27,000 and AC 29,000. At week 6 they are EV 64,000 and AC 73,000. Calculate the CPI for weeks 4 to 6 only, and explain why it differs from the week 6 cumulative CPI of 0.877.
Show answer
EV earned in weeks 4 to 6 is 64,000 - 27,000 = 37,000. Cost in those weeks is 73,000 - 29,000 = 44,000. The period CPI is 37,000 / 44,000 = 0.841. It is lower than 0.877 because the cumulative CPI includes the efficient early weeks (week 1 had a CPI of 1.0). The recent work is running at a worse efficiency than the project average, so the cumulative figure understates the current problem.
Exercise
A project reports cumulative CPI of 0.93 in week 8 and a period CPI of 1.08 in week 9. The manager says the project has recovered. What would you check before agreeing, and what is the likely effect on the cumulative CPI?
Show answer
One good period does not make a trend, so check the following weeks and the cause. First check whether week 9 costs were fully accrued, and whether EV was claimed early. Then check whether the improvement comes from a one-off event. A single period at 1.08 only nudges the cumulative CPI upward, and it remains below 1.0 with the earlier overrun still in the totals. The EAC should not change unless there is evidence that the improvement will continue.