Sub topic 2
Planned value: what should be done by now
This chapter covers planned value (PV), the first of the three measurements behind SPI and CPI. It assumes you know basic project management vocabulary (scope, schedule, budget, work breakdown structure). It also assumes you can read a project schedule and budget and do simple arithmetic with ratios and percentages. Other chapters cover earned value, actual cost and the indices built from them, so this chapter stays on PV.
What planned value measures
Planned value is the authorized budget assigned to the work that was scheduled to be finished by a given status date. It answers one question: "According to the plan, how much work should be done by now, expressed in budget?"
Three points in that definition matter.
- PV is a budget amount, not a cost. It is expressed in money (or labor hours) taken from the budget. It is not what anyone has spent.
- PV is tied to a date. The same plan has a different PV at each status date. PV grows as the schedule advances.
- PV comes from the plan. It does not change when the work goes well or badly. Only an approved change to the baseline changes it.
Many people say "PV" and "BCWS" (budgeted cost of work scheduled) interchangeably. BCWS is the older term for the same quantity.
Where PV comes from
PV is read from the performance measurement baseline, the integrated scope, schedule and cost plan described in the previous chapter. Building it takes three steps.
- Take each work package in the work breakdown structure (WBS) and give it a budget.
- Place that budget on the timeline according to when the work package is scheduled.
- Add up the budgets of all work packages, period by period.
The result is a time-phased budget. Summing it from the start gives a cumulative curve, often called the S-curve because it rises slowly, steeply, then slowly again. The final value of the curve is the budget at completion (BAC). PV at any date is a point on this curve.
Worked example: building a PV curve
Suppose a project has a BAC of 100,000 and six monthly periods. The plan spreads the budget as follows.
| Period | Planned spend in period | Cumulative PV at end of period |
|---|---|---|
| 1 | 10,000 | 10,000 |
| 2 | 15,000 | 25,000 |
| 3 | 15,000 | 40,000 |
| 4 | 20,000 | 60,000 |
| 5 | 20,000 | 80,000 |
| 6 | 20,000 | 100,000 |
At the end of period 3, PV is 40,000. This is the number used in the performance example later in this tutorial. The project is meant to have completed work worth 40,000 of its budget by then. Whether it has actually done so is a question for earned value, not for PV.
Calculating PV in code
You can compute PV from a list of work packages. Each one has a budget, a start period and a finish period. The common default assumption is that a work package's budget is spread evenly across its duration. The function below applies that assumption.
def planned_value(work_packages, status_period):
"""Cumulative PV at the end of status_period.
Each work package is (budget, start, finish) with periods numbered
from 1. Budget is spread evenly over start..finish inclusive.
"""
total = 0.0
for budget, start, finish in work_packages:
duration = finish - start + 1
if status_period >= finish:
total += budget
elif status_period >= start:
elapsed = status_period - start + 1
total += budget * elapsed / duration
return total
packages = [
(20_000, 1, 2), # design
(30_000, 2, 4), # build, part 1
(30_000, 4, 6), # build, part 2
(20_000, 5, 6), # test and handover
]
for period in range(1, 7):
print(f"Period {period}: PV = {planned_value(packages, period):,.0f}")Running it prints a PV of 10,000 at period 1, 30,000 at period 2, 50,000 at period 3, 70,000 at period 4, 90,000 at period 5 and 100,000 at period 6. This is a different plan from the table above, but the method is the same. Different work packages overlap, and each contributes a share of its budget in each period it is active.
Edge cases and common errors
Spreading assumptions change PV
The even-spread rule is a modeling choice. A work package whose cost is concentrated at the end, such as equipment delivered in its final week, has a different PV curve if you phase it that way. Phase the budget the way the work is actually expected to consume it. A poor spread makes PV wrong at every date between start and finish, even if the totals match. A wrong PV produces wrong SV and SPI.
PV is not forecast spending
PV is not a cash-flow forecast. A purchase may be paid after the work is scheduled, and a contract may bill in advance of the work. PV follows when the work is planned to happen, not when money leaves the bank. Mixing the two makes the later comparison with actual cost meaningless.
Status date versus today
PV must be read at the same status date as earned value and actual cost. If PV is taken at the end of the month but actual cost is collected up to the 20th, every index built from them is distorted. Fix a single data date and read all three measurements to it.
Baseline changes
PV changes only through formal change control. If a customer approves added scope, the baseline is re-planned, BAC rises, and PV is re-phased. Never edit PV to make a variance disappear. Doing that hides the slip instead of reporting it.
Re-baselining is a legitimate step for approved changes. It is a warning sign when it happens repeatedly without an approved change request, because each re-plan resets the comparison and erases the history of the slip.
Level of effort and apportioned work
Not all work has a fixed finish. Level of effort (LOE) work, such as project management or administration, is budgeted as a steady amount per period. It still produces a PV, but its progress cannot be measured by output. This matters when you choose how to measure earned value, which a later chapter covers. For PV itself, treat LOE as a regular spread across its duration.
PV at the end of the project
When the schedule finishes, PV equals BAC. After that date PV stays at BAC. A project running late therefore has PV already at BAC while its earned value is still below it. This is the mechanism behind a limitation of SPI that a later chapter covers.
How PV is used downstream
PV is the denominator of SPI and the reference point for schedule variance.
| Measure | Formula | What PV contributes |
|---|---|---|
| Schedule variance (SV) | EV − PV | The planned amount of progress |
| Schedule Performance Index (SPI) | EV / PV | The divisor, so PV must be greater than zero |
| Earned schedule | Time at which PV equals EV | The curve read in reverse |
If PV is zero at a date, SPI is undefined. This happens at the very start of a project, before any work is scheduled. Report SPI only after the first period with a nonzero PV.
Practical checklist
Before you trust a PV number, check these points.
- The baseline in use is the current approved one.
- Each work package's budget is phased to match when its work consumes effort.
- The total of all work packages equals BAC.
- The status date is the same one used for EV and AC.
- Any approved change has been reflected, and no unapproved edit has been made.
Summary
Planned value is the budgeted amount for the work scheduled to be done by a status date. It is read from the time-phased baseline, it rises along an S-curve until it reaches BAC, and it changes only when the baseline is formally changed. Get PV right and date-consistent, because SV and SPI depend directly on it.
Exercise
A project has a BAC of 120,000. Two work packages are active in period 4. Package A has a budget of 40,000 and is scheduled over periods 3 to 6. Package B has a budget of 20,000 and is scheduled over periods 4 to 5. A third package, C, has a budget of 30,000 and was scheduled over periods 1 to 2. Assuming even spreading, what is the cumulative PV at the end of period 4 from these three packages?
Show answer
Package C finished before period 4, so it contributes its full 30,000. Package A runs four periods (3, 4, 5, 6), and two have elapsed by the end of period 4, so it contributes 40,000 × 2/4 = 20,000. Package B runs two periods (4, 5), and one has elapsed, so it contributes 20,000 × 1/2 = 10,000. The total is 30,000 + 20,000 + 10,000 = 60,000.
Exercise
At the end of period 3, a manager notices the project is behind, so she lowers PV for that date to equal the work completed. What happens to the schedule variance, and why is this wrong?
Show answer
Schedule variance becomes zero, and SPI becomes 1.0, because EV minus PV is zero when the two are equal. This is wrong because PV is the approved plan, not a measure of progress. Changing it without a baseline change hides a real delay. The correct response is to report the delay and, if the plan truly changes, process a formal change request.
Exercise
Why must PV, EV and AC all be read at the same status date?
Show answer
SV, CV, SPI and CPI each compare two of the three measurements. If they refer to different dates, the comparison mixes different amounts of elapsed time and gives a ratio or difference that describes no real state of the project.