Sub topic 3
What EAC and ETC are, and how they fit together
This chapter defines Estimate at Completion (EAC) and Estimate to Complete (ETC), shows how they relate to actual cost, and explains why every forecasting method in the later chapters is a different way of estimating the same thing. It assumes you know the four earned value inputs from the earlier chapters (BAC, PV, EV, AC) and the indices CPI and SPI. It also assumes you are comfortable with basic ratios and know what a project baseline is.
Two questions about the future
Earned value analysis mostly describes the past. CV and SV tell you where the project stands today. The EAC and ETC forecasts answer two questions about the future:
- What will the project cost in total when it finishes? This is the Estimate at Completion (EAC).
- How much more money will it take to finish from here? This is the Estimate to Complete (ETC).
The two questions are the same question split at today's date. Money already spent is a fact. Money still to be spent is a forecast. Adding them gives the total:
EAC = AC + ETCEverything else in this chapter follows from that equation.
The definitions
- AC (Actual Cost) is what the project has spent to date, for the work done to date. It is a measured fact and does not change.
- ETC (Estimate to Complete) is the forecast cost of the work that has not yet been done. It looks forward only.
- EAC (Estimate at Completion) is the forecast total cost of the project at completion. It is the sum of what has been spent and what you expect to spend.
- BAC (Budget at Completion) is the original approved budget for the whole project. It is the baseline against which EAC is judged.
BAC is a plan and EAC is a forecast. If the project is on track, the two are equal. If it is not, the gap between them is the Variance at Completion, which a later chapter covers.
Three kinds of "remaining"
Newcomers often confuse three different remaining amounts. They have different meanings and different values.
| Quantity | Formula | What it tells you |
|---|---|---|
| Remaining budget | BAC − AC | Money still available if you stick to the original budget |
| Remaining work, at budgeted value | BAC − EV | The budgeted value of the work not yet done |
| ETC | EAC − AC | The forecast cost to finish that remaining work |
Take a project with BAC = 100,000, EV = 40,000, and AC = 48,000. The remaining budget is 52,000. The budgeted value of the remaining work is 60,000. Those two numbers already disagree, because the project has spent more than it earned. The ETC is a third number that depends on your forecast. It is not necessarily either of the other two.
How EAC and ETC fit together
The relationship runs in both directions, and you can start from either side:
- If you pick a way to forecast the remaining cost, you get ETC, and then EAC = AC + ETC.
- If you pick a way to forecast the total cost, you get EAC, and then ETC = EAC − AC.
The following diagram shows the time split and the baseline comparison.
The choice of forecasting method decides the ETC. The AC half of the sum never changes, so the whole disagreement between methods sits in the ETC term.
The core idea: methods differ in one assumption
Every EAC formula in the next chapters is the same sum, AC plus a forecast of the remaining cost. The formulas differ only in how they estimate the cost of the remaining work. The starting point is the budgeted value of that remaining work, BAC − EV, and each method decides whether to apply it as is or adjust it:
| Assumption about the remaining work | ETC | EAC |
|---|---|---|
| The overrun so far was a one-off; the rest costs what was budgeted | BAC − EV | AC + (BAC − EV) |
| Current cost efficiency continues | (BAC − EV) / CPI | AC + (BAC − EV) / CPI, which equals BAC / CPI |
| Both cost and schedule efficiency drive the outcome | (BAC − EV) / (CPI × SPI) | AC + (BAC − EV) / (CPI × SPI) |
| The remaining work is re-estimated from scratch | A new bottom-up estimate | AC + new estimate |
You can see the pattern: in each row the EAC is AC plus an ETC. The next chapters derive each row in detail. Here the goal is to see that they share one structure.
Worked example in code
The first example computes ETC under two assumptions and builds EAC from each. It uses the same project data as the earlier chapters: BAC = 100,000, EV = 40,000, AC = 48,000.
bac, ev, ac = 100000, 40000, 48000
cpi = ev / ac # 0.8333...
remaining_work = bac - ev # budgeted value of work not yet done
scenarios = {
"one-off overrun": remaining_work, # remaining work costs its budgeted value
"performance continues": remaining_work / cpi,
}
for name, etc in scenarios.items():
eac = ac + etc # the defining identity: EAC = AC + ETC
print(f"{name}: ETC={etc:.0f} EAC={eac:.0f}")The output is:
one-off overrun: ETC=60000 EAC=108000
performance continues: ETC=72000 EAC=120000The same project, with the same facts, produces two forecasts 12,000 apart. The gap comes entirely from the ETC assumption. The 48,000 already spent is identical in both.
The second example shows the two directions of the relationship as small reusable functions, and checks that they agree.
def eac_from_etc(ac, etc):
return ac + etc
def etc_from_eac(eac, ac):
return eac - ac
ac = 48000
etc = 72000
eac = eac_from_etc(ac, etc)
print(eac) # 120000
print(etc_from_eac(eac, ac)) # 72000, recovers the original ETCBecause the two functions are inverses, a number reported as an EAC can always be converted into an ETC, and the other way round, as long as you know AC.
Edge cases and sanity checks
A few properties hold for any sensible forecast. Checking them catches many mistakes.
- EAC can never be below AC. Money already spent cannot be un-spent. If your formula gives an EAC smaller than AC, the ETC came out negative and something is wrong, usually a bad CPI or a mixed-up input.
- ETC is non-negative. Finishing the remaining work costs zero at the least. A negative ETC means the inputs do not describe the same point in time.
- At 100% complete, EV equals BAC. The remaining work is then zero, so ETC is zero and EAC equals AC. In the one-off formula, AC + (BAC − EV) becomes AC, which is a useful check.
- At the start, AC is zero and EV is zero. The ETC is the whole forecast, and with no performance history there is no meaningful CPI. Methods that divide by CPI cannot be used until some work has been earned. Dividing by CPI also fails when AC is zero, because CPI = EV / AC is then undefined.
- A very small CPI inflates the forecast. Early in a project, EV and AC are both small, so CPI can swing widely. A forecast based on BAC / CPI inherits that noise. Treat early forecasts of this kind with caution.
- EAC and ETC are for the current baseline. If a change request has been approved and BAC revised, compute EAC against the revised BAC. Mixing an old BAC with new actuals produces a forecast for a project that no longer exists.
What EAC and ETC include and exclude
Both figures are built from the same cost definitions as AC and BAC, so they are only comparable if those definitions are consistent.
- AC covers the costs charged to the project to date. If invoices for work already done have not been booked yet, AC is understated, and so is EAC, even though ETC may look reasonable. Include accrued costs.
- ETC covers only work still in scope and not yet done. Scope removed from the project should leave the ETC, and approved additions should enter it.
- Management reserve is usually held outside the performance baseline, so it is normally not part of BAC and not part of a standard EAC. Contingency reserves held inside the baseline are part of BAC. State which one your forecast uses, so readers do not compare unlike numbers.
- Remaining cost may not scale with efficiency. A fixed-price subcontract signed at a known rate will not become more expensive because your internal team has a poor CPI. Applying CPI to that part of the ETC overstates it. This is one reason a later chapter covers bottom-up estimating.
Reading the pair together
EAC and ETC are most useful reported together, because each answers a different audience's question. A sponsor deciding whether the project is still worth funding asks about the total, which is EAC. A finance lead planning cash asks how much more money is needed, which is ETC. A project manager gives both from one calculation, so the numbers always reconcile: EAC − ETC equals AC.
A good reporting habit is to state the ETC assumption in the same line as the figure. "EAC is 120,000, assuming cost performance continues at the current CPI of 0.83" is a complete statement. "EAC is 120,000" invites the question of where it came from. The final two chapters return to this, covering how to choose a method and how to justify it.
Summary
- EAC is the forecast total cost. ETC is the forecast cost of the remaining work. AC is the fact already spent.
- EAC = AC + ETC, and equivalently ETC = EAC − AC.
- Remaining budget (BAC − AC), remaining work value (BAC − EV), and ETC are three different quantities.
- All EAC methods share the same structure and differ only in how they estimate the remaining cost.
- A forecast should satisfy simple checks: EAC at least AC, ETC at least zero, and ETC of zero at 100% complete.
Exercise
A project has BAC = 200,000, AC = 90,000, and EV = 80,000. Assume the overrun so far was a one-off, so the remaining work will cost its budgeted value. Then assume instead that the current cost efficiency will continue. For each assumption, give ETC and EAC. Also say what number someone would get by computing BAC − AC, and why it is not the ETC.
Show answer
One-off overrun: ETC = BAC − EV = 120,000, so EAC = 90,000 + 120,000 = 210,000. Cost efficiency continues: CPI = 80,000 / 90,000 = 0.8889, so ETC = 120,000 / 0.8889 = 135,000 and EAC = 90,000 + 135,000 = 225,000, which also equals BAC / CPI. BAC − AC = 110,000 is only the money left in the original budget. It is lower than both ETCs because it ignores that the project has spent 10,000 more than it has earned, so it is not a forecast of what the remaining work will cost.
Exercise
A team reports an EAC of 95,000 for a project whose AC is 98,000. What does this tell you, and what should you check?
Show answer
An EAC below AC implies a negative ETC of −3,000, which is impossible because spent money cannot come back. The forecast is wrong. Check for a mistyped AC or BAC, a CPI calculated from data at a different date than the AC, or a formula applied to a revised baseline with old actuals. Recompute from consistent inputs so that EAC is at least AC.