Sub topic 12
Pitfalls and How to Report a Forecast
This chapter assumes you can compute BAC, PV, EV, AC, CPI, SPI, the three formula-based EAC methods, ETC, VAC, and TCPI. Here you will learn where those numbers go wrong and how to present a forecast so stakeholders can trust it and act on it.
All examples use the running project: BAC 100,000, PV 50,000, EV 40,000, AC 48,000. That gives CPI 0.8333 and SPI 0.8.
Why the formulas are the easy part
Every EAC formula is one line of arithmetic. The forecast is only as good as three things:
- the earned value (EV) figure, which depends on how progress is measured,
- the actual cost (AC) figure, which depends on how quickly costs reach the books,
- the method choice, which depends on a judgement about the future.
Most bad forecasts come from one of these three, not from the arithmetic.
Data quality pitfalls
Optimistic or unmeasurable EV
EV is BAC times the percent complete of the work. If the percent complete is a guess, every ratio built on it inherits the guess. The common failure is the "90% done" syndrome. A task reports 90% complete for weeks while the remaining 10% absorbs most of the effort.
Defences:
- Use objective rules for crediting progress, such as 0/100 (credit only when finished), 50/50 (half at start, half at finish), or weighted milestones.
- Define done by a deliverable that can be inspected, not by effort spent.
- Never credit EV for effort alone. Effort spent is AC, not EV.
AC that lags reality
AC should include everything incurred to date. In practice, invoices arrive late, timesheets are approved weeks after the work, and contractor accruals are missed. Understated AC makes CPI look better than it is, so the forecast comes out too low. The error is largest at the point when you most need accuracy, because the unbooked costs arrive later as a sudden jump.
Before each reporting cycle, confirm the cut-off date for AC and the EV status date. They must be the same date. Comparing EV as of Friday with AC as of last month's close produces a meaningless CPI.
A baseline that moved without a record
BAC and PV must come from the same approved baseline. Two things quietly break this:
- Approved scope changes added to the budget in some places but not others.
- Informal changes that add work but leave BAC untouched. The new work then shows up as cost with no matching EV.
If scope changes are approved, update BAC and PV together through change control. If the baseline is so out of date that variances no longer mean anything, re-baseline. Record the old figures and the reason, so the history can still be read.
Method and interpretation pitfalls
Treating SPI as a late-project signal
SPI is EV divided by PV, measured in money. When a project finishes, EV equals BAC and PV equals BAC, so SPI is exactly 1.0 even if the project finished months late. Late in a project, SPI drifts toward 1 and stops measuring schedule. The same effect weakens the cost-and-schedule EAC late in the project: its SPI term no longer describes real schedule delay.
| Month | Planned finish | PV | EV | SPI |
|---|---|---|---|---|
| 6 | Month 10 | 60,000 | 45,000 | 0.75 |
| 10 | Month 10 | 100,000 | 80,000 | 0.80 |
| 12 | Month 10 | 100,000 | 100,000 | 1.00 |
The project in the table finished two months late, but month 12 shows a perfect SPI. For schedule claims late in a project, compare dates with the baseline or use earned schedule, which expresses schedule variance in time units instead of money.
Using the typical method too early
BAC/CPI assumes the current CPI will persist. Early in a project, EV and AC are small, a few percent of BAC, and one invoice or one setup cost can swing CPI sharply. As a rule of thumb, CPI becomes stable after roughly 15–20% of the work is complete. Before that, treat a CPI-based EAC as a warning, not a number to commit to.
Picking the method to fit the answer you want
If the atypical method gives a number inside budget and the typical method does not, there is a temptation to pick the one that looks better. Choose the method from the evidence, before computing the results: what caused the variance, and will that cause continue? Write down the reason. A method chosen to produce a target is a budget figure dressed as a forecast.
Stacking pessimism
The cost-and-schedule formula divides remaining work by CPI times SPI. If both indices are below 1, the product falls further. In the running example it gives 138,000, 38% over budget. That is defensible only when schedule slippage truly drives cost, for example when delayed work means paying for idle crews or extended rentals. When the schedule delay is unrelated to cost, this formula double-counts the problem.
Reading TCPI without comparing it to CPI
TCPI says what efficiency the remaining work must achieve. By itself it does not tell you whether that efficiency is realistic. Compare it with the efficiency achieved so far:
- TCPI against BAC is 60,000 / 52,000 = 1.1538. The team has delivered 0.8333 so far and must now deliver 1.1538, about 38% better than its record.
- TCPI against EAC is 0.8333 for the typical method. This matches CPI by construction, so it is no evidence that the forecast is right. It only shows the forecast is consistent with itself.
If the TCPI needed to hit BAC is far above the CPI achieved so far, the budget is unlikely to hold unless something concrete changes, such as a different team, a revised scope, or removed blockers. "We will work harder" is not a concrete change.
When AC has already reached or passed BAC, the TCPI against BAC has a zero or negative denominator and has no meaning. Report that the budget has been exhausted and move to a TCPI against EAC.
Calculation pitfalls
Most arithmetic slips are one of these:
| Slip | Symptom | Fix |
|---|---|---|
| Swapping the CPI inputs (AC / EV) | CPI above 1 on an overrunning project | CPI = EV / AC; keep a unit test with a known project |
| Using ETC as the total forecast | Final cost looks far too low | Final cost = AC + ETC |
| Subtracting EAC from BAC the wrong way | VAC sign reversed | VAC = BAC − EAC; negative means over budget |
| Dividing by zero (AC = 0, EV = 0, PV = 0) | Crash, or an infinite forecast | Validate inputs; report "not yet forecastable" |
| Mixing currencies or inflation bases | Unexplained variance | Convert before aggregating |
A reporting function should check these in code rather than rely on memory:
def forecast_summary(bac, pv, ev, ac):
if min(bac, pv, ac) <= 0 or ev <= 0:
raise ValueError("BAC, PV, EV and AC must be positive")
if ev >= bac:
raise ValueError("EV has reached BAC, so no work remains to forecast")
cpi, spi = ev / ac, ev / pv
eacs = {
"atypical": ac + (bac - ev),
"typical": bac / cpi,
"cost and schedule": ac + (bac - ev) / (cpi * spi),
}
print(f"CPI {cpi:.4f} SPI {spi:.4f}")
print(f"{'method':<18}{'EAC':>9}{'ETC':>9}{'VAC':>9}{'TCPI':>8}")
for name, eac in eacs.items():
etc = eac - ac
vac = bac - eac
tcpi = (bac - ev) / etc
print(f"{name:<18}{eac:>9,.0f}{etc:>9,.0f}{vac:>9,.0f}{tcpi:>8.4f}")
if ac < bac:
print(f"TCPI to BAC: {(bac - ev) / (bac - ac):.4f}")
else:
print("TCPI to BAC: undefined, actual cost has reached the budget")
forecast_summary(bac=100000, pv=50000, ev=40000, ac=48000)Running it prints:
CPI 0.8333 SPI 0.8000
method EAC ETC VAC TCPI
atypical 108,000 60,000 -8,000 1.0000
typical 120,000 72,000 -20,000 0.8333
cost and schedule 138,000 90,000 -38,000 0.6667
TCPI to BAC: 1.1538Notice that the TCPI column falls as the forecast rises. A higher EAC leaves more money for the same remaining work, so less efficiency is demanded. This is why an optimistic EAC always comes with a high TCPI: the forecast quietly assumes a recovery.
Reporting a forecast
A single number invites false precision. A useful forecast report has five parts.
- The range. Here the formula-based EACs run from 108,000 to 138,000. State the range and say which figure you consider most likely.
- The method and the reason. For example: "We used BAC/CPI because the vendor's rate increase is permanent, so the overrun will continue." One sentence is enough, as long as the reasoning can be challenged.
- The status dates. Give the EV and AC data date, and note any known lag in AC, such as "AC excludes about 4,000 of unbilled contractor work."
- The consistency checks. Report VAC and the TCPI gap: "Meeting the 100,000 budget needs a 1.15 efficiency against 0.83 achieved to date."
- The decisions required. Say what you need from stakeholders: approve contingency, cut scope, or accept a later finish.
Track forecast accuracy
Keep the forecast from each period and compare it with what happens. If your forecasts rise every period, the method is systematically too optimistic, and the team should move to the typical or bottom-up method. A forecast history is also the best defence when a stakeholder asks why the number moved.
Separate the forecast from the targets
Report EAC, the cost you expect, separately from BAC, the cost you approved. If the forecast exceeds BAC, say so, even when a recovery plan exists. A recovery plan changes the forecast only after it takes effect, and its results show up as improved CPI in later periods. Until then, the forecast uses the evidence in hand.
Summary of the main checks
- Measure EV by objective rules and take EV and AC at the same date.
- Keep BAC and PV tied to the current approved baseline.
- Do not trust SPI late in a project, and do not trust CPI-based forecasts very early.
- Choose the EAC method for a recorded reason before looking at the results.
- Compare TCPI with CPI, and treat a large gap as a risk.
- Report a range with assumptions and decisions needed, and keep your forecast history.
Exercise
On the day a project is meant to finish, BAC is 200,000, EV is 200,000, PV is 200,000, and AC is 230,000. The project finished three months late. What do SPI and CPI show, and which figure misleads?
Show answer
SPI is 200,000 / 200,000 = 1.0 and CPI is 200,000 / 230,000 = 0.8696. CPI correctly shows the 15% cost overrun (final cost 230,000, VAC of −30,000). SPI misleads, because it reaches 1.0 whenever all work is earned, regardless of the three-month delay. Schedule lateness must be read from dates or earned schedule.
Exercise
A project has BAC 100,000, EV 40,000, AC 48,000. The sponsor insists on finishing at 100,000. Compute the TCPI against BAC. Then say what you would tell the sponsor if the CPI over the last three periods has been 0.83, 0.84, and 0.83.
Show answer
TCPI to BAC = (100,000 − 40,000) / (100,000 − 48,000) = 60,000 / 52,000 = 1.1538. The team has run at about 0.83 for three periods and would need about 1.15 from now on, roughly 38% better. Stable CPI suggests the typical method is appropriate, giving EAC = 100,000 / 0.8333 = 120,000 and VAC = −20,000. Tell the sponsor that 100,000 is achievable only if a specific change, such as reduced scope or a removed cause of inefficiency, is approved, and report the 120,000 forecast until then.