Sub topic 1
The inputs: BAC, PV, EV, and AC
Every earned value forecast starts from four numbers. If any of them is wrong, every later result is wrong too: the variances, the indices, the Estimate at Completion (EAC) and the Estimate to Complete (ETC). This chapter defines each input, shows where its value comes from, and gives you checks to catch bad data before it reaches a formula.
Prerequisites
This chapter assumes you know:
- Basic project management vocabulary: scope, budget, schedule, work package.
- Simple arithmetic and ratios, including percentages.
- What a project baseline is: the approved scope, schedule, and cost plan that you measure progress against.
You do not need to know any earned value formulas yet. This chapter only covers the inputs, and the next chapter uses them.
The four inputs at a glance
Earned value management (EVM) compares three views of the same project at one point in time. It asks what you planned to have done, what you actually got done, and what you paid for it. Those views correspond to three of the four inputs. The fourth input, BAC, is the total budget the other three are measured against.
| Input | Name | Question it answers | Unit |
|---|---|---|---|
| BAC | Budget at Completion | What is the total approved budget for all the work? | Money (or hours) |
| PV | Planned Value | How much of the budget should be earned by the status date? | Money |
| EV | Earned Value | How much of the budget does the completed work represent? | Money |
| AC | Actual Cost | How much have we actually spent on that work so far? | Money |
PV, EV, and AC are all measured at the same status date, which is the "as of" date of your report. BAC does not depend on the status date. It is fixed by the baseline.
BAC: Budget at Completion
BAC is the sum of the baselined budgets for all the work in the project. It is the cost plan for the whole job, not the cost so far.
Three points are easy to miss:
- BAC covers the performance measurement baseline only. It excludes management reserve, the money held back for unknown unknowns. Contingency reserve for identified risks is a separate matter. Whether it sits inside BAC depends on how your organization builds its baseline, so check the cost baseline document.
- BAC changes only through formal change control. If the customer adds scope and the change is approved, BAC rises. If the team simply overspends, BAC stays the same.
- Every work package's budget must add up to BAC. If it does not, the baseline has a gap or an overlap.
In this tutorial, BAC is the number the forecast is eventually compared with. A forecast of 120,000 against a BAC of 100,000 means a projected overrun of 20,000.
PV: Planned Value
PV is the budgeted cost of the work that was scheduled to be finished by the status date. It comes from the baseline schedule combined with the baseline budget. Nothing about actual progress enters it.
If a task has a budget of 50,000 and the schedule says it should be 60% done by the status date, its PV is 30,000. Add up the PV of every task and you get the project's PV.
PV over time forms the planned spending curve, often called the S-curve because it starts slowly, speeds up in the middle, and flattens at the end. At the last day of the project, PV equals BAC.
PV is not the money you planned to spend. It is the budget value of the work you planned to complete. The two are close in practice but conceptually different, and EVM relies on the second meaning.
EV: Earned Value
EV is the budgeted cost of the work actually completed by the status date. It is the value of progress, expressed in baseline money.
The key idea is that EV uses budgeted prices, not what you paid. If a task was budgeted at 20,000 and is 100% complete, it has earned 20,000. That holds even if it cost you 25,000 or 15,000 to do it. The difference between what you earned and what you spent is what later chapters analyze.
To compute EV you need a rule for deciding how complete each work package is. Common rules:
| Rule | How it works | Typical use |
|---|---|---|
| 0/100 | Earn nothing until the work is done, then earn 100% | Short tasks, or work with no meaningful partial state |
| 50/50 | Earn 50% at start, 50% at completion | Short tasks where you want some early credit |
| Percent complete | Earn budget times estimated percent complete | Longer tasks with measurable progress |
| Weighted milestones | Each milestone carries a share of the budget | Long work packages with clear checkpoints |
Whichever rule you choose, agree on it before the project starts and apply it consistently. Changing rules mid-project makes trends meaningless.
Where EV goes wrong
EV is the most subjective of the four inputs, because someone has to judge progress. Watch for these problems:
- The 90% syndrome. A task sits at "90% complete" for weeks. Percent complete estimates tend to be optimistic. Prefer rules with objective evidence, such as milestones passed or units installed.
- Counting effort instead of progress. Hours worked are not progress. Ten days of effort on a task does not mean the task is half done.
- Crediting unaccepted work. If the work still has to pass review or testing, decide in advance whether it earns value before or after acceptance.
- EV above BAC. EV can never exceed BAC. If it does, the percent complete figures are wrong or the baseline was changed without updating.
AC: Actual Cost
AC is the total cost actually incurred for the work done so far. It comes from accounting records, timesheets, and invoices.
For AC to be useful, it must be comparable with EV. That requires:
- Same scope. AC must cover the same work that EV measures. If the baseline covers only labor and materials, do not load AC with overhead that the baseline never included.
- Same cutoff date. AC must be as of the status date. A late invoice for work already finished belongs in AC, even if it has not been paid. Record such work as an accrual, which is a cost recognized when the work is done and not when the payment is made.
- Same units. If the budget is in dollars, AC is in dollars. If the budget is in hours, AC is in hours. Do not mix currencies or mix money with hours.
- Costs incurred, not committed. A signed purchase order is a commitment, not an actual cost. AC includes the portion of the order for which work has been delivered.
The usual failure is a lag between work and accounting. If timesheets are entered two weeks late, AC looks lower than reality, and the project looks healthier than it is.
How the three measures relate over time
Plotted cumulatively, PV, EV, and AC give a picture of project health at a glance. In the chart below, the planned curve is the highest at first, the earned curve trails it, and the actual cost curve ends above the earned curve. That pattern means less work was completed than planned, and the work done cost more than its budget.
The three lines, from first to third, are PV, EV, and AC. At the end of month 4, which is the status date, the values are PV = 50,000, EV = 40,000, and AC = 48,000. The next section builds exactly these numbers from task-level data.
Worked example: building the inputs from task data
Consider a project with four work packages and a BAC of 100,000. The status date is the end of month 4. For each work package we know the budget, the percent that the schedule says should be complete, the percent actually complete, and the cost recorded so far.
| Work package | Budget | Planned % complete | Actual % complete | Actual cost |
|---|---|---|---|---|
| Design | 20,000 | 100 | 100 | 21,000 |
| Build | 50,000 | 60 | 40 | 27,000 |
| Test | 20,000 | 0 | 0 | 0 |
| Launch | 10,000 | 0 | 0 | 0 |
The calculations are:
- BAC = 20,000 + 50,000 + 20,000 + 10,000 = 100,000.
- PV = 20,000 × 100% + 50,000 × 60% = 20,000 + 30,000 = 50,000.
- EV = 20,000 × 100% + 50,000 × 40% = 20,000 + 20,000 = 40,000.
- AC = 21,000 + 27,000 = 48,000.
Design is a good example of the EV rule: it cost 21,000 but earned only its budget of 20,000. Build has earned 20,000 while costing 27,000. The same calculation in Python:
work_packages = [
# name, budget, planned_pct, actual_pct, actual_cost
("Design", 20000, 100, 100, 21000),
("Build", 50000, 60, 40, 27000),
("Test", 20000, 0, 0, 0),
("Launch", 10000, 0, 0, 0),
]
bac = sum(budget for _, budget, _, _, _ in work_packages)
pv = sum(budget * planned // 100 for _, budget, planned, _, _ in work_packages)
ev = sum(budget * actual // 100 for _, budget, _, actual, _ in work_packages)
ac = sum(cost for _, _, _, _, cost in work_packages)
print("BAC", bac) # BAC 100000
print("PV", pv) # PV 50000
print("EV", ev) # EV 40000
print("AC", ac) # AC 48000These four values, BAC 100,000, PV 50,000, EV 40,000, and AC 48,000, are the running example for the rest of the tutorial.
Sanity checks before you use the numbers
Run these checks every reporting period. They take a minute and catch most data errors.
def check_inputs(bac, pv, ev, ac):
problems = []
if bac <= 0:
problems.append("BAC must be positive")
if pv < 0 or ev < 0 or ac < 0:
problems.append("PV, EV and AC cannot be negative")
if pv > bac:
problems.append("PV exceeds BAC")
if ev > bac:
problems.append("EV exceeds BAC")
if ac == 0 and ev > 0:
problems.append("Work earned value but no cost recorded: check accruals")
return problems
print(check_inputs(100000, 50000, 40000, 48000)) # []
print(check_inputs(100000, 50000, 40000, 0))
# ['Work earned value but no cost recorded: check accruals']Two more checks cannot be coded so easily:
- Do PV, EV, and AC all refer to the same status date?
- Does the scope behind AC match the scope behind the budget?
A note on units and rounding
Keep all four inputs in the same unit and carry full precision until the final report. Round only the figures you show to stakeholders. Rounding PV or EV early introduces small errors that grow when you later divide one number by another.
What comes next
With BAC, PV, EV, and AC in hand and validated, you can compare them. The next chapter subtracts and divides these inputs to get cost and schedule variances and the performance indices CPI and SPI.
Exercise
A project has a BAC of 200,000. At the status date, the schedule says 40% of the work should be complete, but the team has finished only 30%. The team has spent 70,000. Compute PV, EV, and AC. Then explain why EV is not 70,000.
Show answer
PV = 200,000 × 40% = 80,000. EV = 200,000 × 30% = 60,000. AC = 70,000. EV is not 70,000 because EV is the budgeted value of the completed work, not the money spent. The team spent 70,000 to earn 60,000 of budgeted value.
Exercise
A report shows BAC = 150,000, PV = 90,000, EV = 160,000, and AC = 120,000. Which input should you question first, and why?
Show answer
Question EV. It is greater than BAC, which is impossible because the completed work cannot be worth more than the whole budget. The likely causes are overstated percent complete figures or a baseline that was changed without updating BAC.