EAC when the overrun was a one-off
This chapter assumes you can already compute BAC, PV, EV, AC, CV, SV, CPI and SPI from earlier in the tutorial. It also assumes you know that Estimate at Completion (EAC) is the forecast of total project cost. Here you will learn the first of the EAC formulas, the one for variances that will not repeat. You will also learn what that formula assumes, how to check it, and where it fails.
The idea: the past cost is sunk, the future costs the plan
Every EAC has two parts: what you have already spent, and what you expect to spend on the rest. Actual cost (AC) is the first part. The methods differ only in how they estimate the second part, the Estimate to Complete (ETC).
Suppose the project is over budget so far, but the cause was a single event that will not happen again. Examples are a one-time vendor penalty, a corrected estimating error, a rework caused by a defective delivery, or a price spike that has already ended. In that case there is no reason to expect the remaining work to cost more than planned. The remaining work is worth BAC − EV in budget terms, and you assume it will cost exactly that.
The formula is:
EAC = AC + (BAC − EV)
- AC is the money already spent, including the overrun.
- BAC − EV is the budgeted value of the work not yet done.
- The CPI does not appear. You are deliberately ignoring past cost efficiency when forecasting the remaining work.
Some references call this the "atypical variance" formula. The exam-style wording is: "use this when current variances are seen as atypical and are not expected to continue."
A worked example
Use the same project data as the rest of this tutorial.
| Measure | Value |
|---|---|
| BAC | 100,000 |
| PV | 50,000 |
| EV | 40,000 |
| AC | 48,000 |
The project has spent 48,000 and earned 40,000 of value. It is 8,000 over cost. The remaining work is budgeted at 100,000 − 40,000 = 60,000.
EAC = 48,000 + 60,000 = 108,000.
The same calculation in code:
def eac_atypical(bac, ev, ac):
return ac + (bac - ev)
def etc_from_eac(eac, ac):
return eac - ac
bac, ev, ac = 100000, 40000, 48000
eac = eac_atypical(bac, ev, ac)
etc = etc_from_eac(eac, ac)
cv = ev - ac
vac = bac - eac
print(eac, etc, cv, vac) # 108000 60000 -8000 -8000Two results are worth noticing in the output.
- ETC is 60,000, which is exactly BAC − EV. Under this method the remaining work costs what was budgeted for it.
- VAC (BAC − EAC) is −8,000, which equals the current cost variance. The forecast overrun at completion is the overrun you have already incurred, no more and no less.
The algebra behind the shortcut
Substitute the formula into the definition of VAC:
VAC = BAC − EAC = BAC − (AC + BAC − EV) = EV − AC = CV
So under the atypical method, VAC always equals CV. That gives you a quick consistency check. If you computed an atypical EAC and VAC does not equal CV, you made an arithmetic error.
The identity also tells you what the method is claiming. You are saying the project will finish exactly as far over budget as it is today. Any further drift is ruled out by assumption.
When this method is justified
The method is only as good as the claim that the overrun will not recur. Before you use it, ask three questions.
- Can you name a specific cause? "Costs were higher than expected" is not a cause. "The supplier shipped the wrong units and we paid for rework in March" is.
- Is the cause finished? A cause that is still active, such as an ongoing shortage of skilled staff, will keep producing variance.
- Does the remaining plan not depend on the same conditions? If the rework happened because of a design flaw, check whether the remaining work contains the same flaw.
Document the answers. The method is a statement of judgment, and a stakeholder reading "EAC = 108,000" deserves to know what it rests on.
Partial one-offs: separating the event from the trend
Real overruns are often mixed. Part comes from a single event and part from a general cost-efficiency problem. Applying the atypical formula to the whole variance would understate the forecast, and applying the typical formula would overstate it.
A practical approach is to remove the one-off amount from AC to get a normalised actual cost, compute a CPI from that, and apply it to the remaining work. Take a project with BAC 200,000, EV 80,000 and AC 95,000. Of the 15,000 overrun, 10,000 was a one-time penalty and 5,000 is ordinary inefficiency.
bac, ev, ac = 200000, 80000, 95000
one_off = 10000
# Fully atypical: assume none of the overrun repeats
eac_all_one_off = ac + (bac - ev)
# Fully typical: assume the whole variance reflects a trend
eac_all_trend = bac / (ev / ac)
# Mixed: strip out the one-off, keep the remaining efficiency trend
cpi_normalised = ev / (ac - one_off)
eac_mixed = ac + (bac - ev) / cpi_normalised
print(round(eac_all_one_off)) # 215000
print(round(eac_all_trend)) # 237500
print(round(eac_mixed)) # 222500The mixed result sits between the two pure methods, as it should. This is a judgment-based variant rather than a textbook formula, so label it clearly in a report and show the one-off amount you removed. In the full method-selection chapter later in this tutorial you will see how to justify a choice like this one.
Atypical versus typical, side by side
The two methods share the same AC. They differ only in the forecast for remaining work. Using the first example:
| Method | Remaining work forecast (ETC) | EAC | VAC |
|---|---|---|---|
| Atypical: AC + (BAC − EV) | 60,000 | 108,000 | −8,000 |
| Typical: BAC / CPI | 72,000 | 120,000 | −20,000 |
The typical method will be covered in the next chapter. It assumes the remaining 60,000 of work will be done at the same CPI of 0.8333, so it costs 60,000 / 0.8333 = 72,000. The gap between the two forecasts, 12,000, is the price of the assumption. Choosing between the methods is the same as choosing whether you believe the project's cost efficiency has changed for good.
Edge cases and gotchas
The project is under budget
If EV is greater than AC, CV is positive and the formula produces an EAC below BAC. Check the first example with AC 36,000 and EV 40,000: EAC = 36,000 + 60,000 = 96,000, a VAC of +4,000. The formula is symmetrical, but the justification needs more care. Underspending can come from a one-off, such as a discount or a delayed invoice. It can also come from costs that have been incurred but not yet recorded. Confirm that AC is complete before locking in a forecast that shows savings.
EV is zero or very small
Early in a project, EV may be 0. The atypical formula still works, giving EAC = AC + BAC, which means the entire BAC remains. However, the early numbers carry little information about whether anything is a one-off. Be cautious about claiming that an early overrun will not recur when the project has barely started.
Schedule slippage is not covered
The formula uses only cost variance. If SPI is well below 1, the project may need extra months of staff, equipment hire or overhead. Those costs will add to the remaining spend even if the cost efficiency of each task is fine. A late project with a one-off cost overrun can still need a larger forecast than this method gives. The cost-and-schedule formula in a later chapter handles that case.
Treating a convenient story as a cause
The method rewards optimism. A project manager who wants a lower forecast can label any variance as a one-off. Guard against it by requiring evidence, such as an approved change request, an incident record, or an invoice, and by checking whether similar variances have happened before. Three "one-off" events in four months are a trend.
Mixing up BAC with a revised budget
If the budget was formally re-baselined after the overrun, BAC is the new baseline and EV is measured against it. Do not use the original BAC with the new EV, or the reverse. The formula is only meaningful when BAC, EV and AC all refer to the same baseline.
A quick procedure
- Compute CV = EV − AC and confirm the project is over (or under) cost.
- Identify the cause of the variance and decide whether it is finished.
- If it is a finished one-off, compute EAC = AC + (BAC − EV).
- Derive ETC = EAC − AC and VAC = BAC − EAC. Check that VAC = CV.
- Record the cause and the assumption beside the forecast.
Exercises
Exercise
A project has BAC = 250,000, PV = 120,000, EV = 100,000 and AC = 115,000. The overrun came entirely from a single penalty payment that will not be repeated. Compute EAC, ETC and VAC using the atypical method, and state what VAC should equal as a check.
Show answer
EAC = AC + (BAC − EV) = 115,000 + 150,000 = 265,000. ETC = EAC − AC = 150,000, which equals BAC − EV. VAC = BAC − EAC = −15,000. As a check, VAC should equal CV = EV − AC = 100,000 − 115,000 = −15,000, and it does.
Exercise
A project has BAC = 90,000, EV = 30,000 and AC = 27,000, so it is under budget. A colleague uses the atypical formula and reports an EAC of 87,000. Is the arithmetic right, and what should you verify before accepting the saving?
Show answer
The arithmetic is right: EAC = 27,000 + (90,000 − 30,000) = 87,000, and VAC = +3,000, equal to CV. Before accepting the saving, verify that the underspend is a one-off, such as a discount, and not caused by costs that have been incurred but not yet recorded in AC. If AC is incomplete, the forecast is too low.
Exercise
For BAC = 200,000, EV = 80,000 and AC = 95,000, the atypical EAC is 215,000 and the typical EAC (BAC / CPI) is 237,500. A manager says 8,000 of the 15,000 overrun was a one-time penalty and the rest reflects ongoing inefficiency. Compute the mixed EAC by removing the one-off from AC, and say whether it falls between the two pure forecasts.
Show answer
Normalised AC = 95,000 − 8,000 = 87,000. CPI = 80,000 / 87,000 = 0.9195. Remaining work = 120,000, so remaining cost = 120,000 / 0.9195 = 130,500. EAC = 95,000 + 130,500 = 225,500. This lies between 215,000 and 237,500, as expected for a partly one-off, partly trend overrun.