Sub topic 10
TCPI: the efficiency the remaining work demands
The To-Complete Performance Index (TCPI) is the cost efficiency the team must achieve on the remaining work to hit a chosen financial target. This chapter assumes you can already calculate BAC, PV, EV, AC, CPI, EAC, ETC and VAC from the earlier chapters. It also assumes you know the standard EAC formulas. Here you will learn the two forms of TCPI, how to read each, and where the formula breaks.
The idea: work left versus money left
CPI looks backward. It is earned value divided by actual cost, so it tells you how much value each unit of money has bought so far. TCPI looks forward. It divides the work still to be done by the money still available:
TCPI = (work remaining) / (funds remaining)Work remaining is measured in budgeted terms, so it equals BAC - EV. The funds remaining depend on which target you pick:
- Target is the original budget (BAC): funds remaining = BAC - AC.
- Target is a revised forecast (EAC): funds remaining = EAC - AC, which is the ETC.
This gives two formulas:
TCPI (BAC) = (BAC - EV) / (BAC - AC)
TCPI (EAC) = (BAC - EV) / (EAC - AC)Both numerators are the same. Only the money in the denominator changes.
Reading the number
TCPI is a ratio of budgeted value to money, like CPI. You can compare the two directly.
| TCPI value | Meaning |
|---|---|
| Above 1.0 | Each unit of money must buy more than one unit of budgeted work. The team must be more efficient than planned. |
| Exactly 1.0 | The remaining work must be done at exactly its budgeted cost. |
| Below 1.0 | The team can spend more than the budget per unit of work and still reach the target. |
The practical question is how TCPI compares with the CPI you have achieved so far. A TCPI of 1.15 is a modest ask for a team running at CPI 1.10. It is a large ask for a team running at CPI 0.83.
Worked example from the running project
The running project has BAC = 100,000, PV = 50,000, EV = 40,000 and AC = 48,000. The CPI is 40,000 / 48,000 = 0.8333.
Work remaining is 100,000 - 40,000 = 60,000.
Against the original budget:
TCPI (BAC) = 60,000 / (100,000 - 48,000) = 60,000 / 52,000 = 1.1538The team has spent 48,000 and earned only 40,000. To finish within 100,000, it must earn 1.15 units of value per unit of money for the rest of the project. So far it has managed 0.83. The required efficiency is about 38% higher than the achieved efficiency (1.1538 / 0.8333 = 1.38).
Against the typical-method forecast, EAC = 120,000 and ETC = 72,000:
TCPI (EAC) = 60,000 / (120,000 - 48,000) = 60,000 / 72,000 = 0.8333This result is the same as CPI. That is not a coincidence. The typical formula (BAC / CPI) assumes the remaining work will be done at the current CPI, so the efficiency required to hit that forecast is exactly the current CPI. This gives a useful check: if you compute TCPI against a BAC / CPI forecast and it does not equal CPI, you have an arithmetic error.
Computing TCPI in code
The function below handles both targets. It also refuses to return a number when the denominator is zero or negative, which is the main edge case covered later.
def tcpi(bac, ev, ac, target):
"""Efficiency needed on the remaining work to finish at `target`.
`target` is the total cost you want to finish at: BAC for the
original budget, or an EAC for a revised forecast.
"""
work_remaining = bac - ev
funds_remaining = target - ac
if funds_remaining <= 0:
raise ValueError(
"No funds remain against this target (target <= AC); "
"TCPI is undefined or meaningless."
)
return work_remaining / funds_remaining
bac, pv, ev, ac = 100000, 50000, 40000, 48000
cpi = ev / ac
eac_atypical = ac + (bac - ev) # 108000
eac_typical = bac / cpi # 120000
eac_cost_schedule = ac + (bac - ev) / (cpi * (ev / pv)) # 138000
print("CPI", round(cpi, 4))
print("TCPI vs BAC ", round(tcpi(bac, ev, ac, bac), 4))
print("TCPI vs atypical", round(tcpi(bac, ev, ac, eac_atypical), 4))
print("TCPI vs typical ", round(tcpi(bac, ev, ac, eac_typical), 4))
print("TCPI vs cost+sch", round(tcpi(bac, ev, ac, eac_cost_schedule), 4))The output is:
CPI 0.8333
TCPI vs BAC 1.1538
TCPI vs atypical 1.0
TCPI vs typical 0.8333
TCPI vs cost+sch 0.6667Each EAC method produces a different TCPI, and each one tells a story:
- Atypical (108,000): TCPI is exactly 1.0. The atypical formula assumes the rest of the work goes exactly to budget, so the required efficiency is 1.0.
- Typical (120,000): TCPI equals today's CPI. The forecast assumes nothing improves.
- Cost and schedule (138,000): TCPI is 0.6667, below the current CPI. This forecast assumes things get worse, so the team could be less efficient than today and still meet it.
Notice what this shows. Every EAC formula has an implied TCPI. When someone proposes a forecast, you can compute that TCPI and ask whether the efficiency it assumes is believable.
A decision flow for TCPI
When the project is ahead
TCPI is not only a warning for troubled projects. Take a project with BAC = 100,000, EV = 60,000 and AC = 50,000. CPI is 1.2.
bac, ev, ac = 100000, 60000, 50000
cpi = ev / ac
tcpi_bac = (bac - ev) / (bac - ac)
print(round(cpi, 4), round(tcpi_bac, 4)) # 1.2 0.8The team needs only 0.8 efficiency to finish on budget. It can slip well below its current performance and still meet BAC. This tells a sponsor there is contingency in the plan, or that the baseline was padded. That is useful when the sponsor asks whether to release unused budget.
Edge cases and limits
Funds remaining is zero or negative
If AC equals BAC, the denominator of TCPI (BAC) is zero. If AC exceeds BAC, the denominator is negative. The formula then returns infinity or a negative number, and neither means anything as an efficiency.
Consider BAC = 100,000, EV = 90,000, AC = 105,000. The project has already overspent its original budget, so:
TCPI (BAC) = 10,000 / (100,000 - 105,000) = 10,000 / -5,000 = -2.0A negative efficiency is impossible. The correct reading is that the original budget can no longer be met. Switch to a revised target. If management approves an EAC of 115,000, then:
TCPI (EAC) = 10,000 / (115,000 - 105,000) = 1.0The team must now do the last 10,000 of work at exactly budget. That is a number a sponsor can discuss.
TCPI against BAC when BAC is still the approved budget
Many organizations require the project to report TCPI (BAC) until the sponsor formally approves a new budget. A forecast EAC above BAC is not an approved budget. Report both: TCPI (BAC) shows the gap to the approved budget, and TCPI (EAC) shows what the new forecast demands.
Small remaining denominators
When the project is nearly finished, funds remaining is small, so TCPI swings widely on small changes in AC. A TCPI of 1.8 on a project with 2% of its budget left is less alarming than the same value at 50% complete, because the absolute amount at stake is small. Always read TCPI alongside the percentage complete and the money involved.
Cost only
TCPI measures cost efficiency. It says nothing about schedule. A project can have an achievable TCPI and still finish late. Check SPI separately, and remember the cost and schedule EAC method already folds both into its forecast.
Quality of EV
TCPI inherits all the weaknesses of the earned value figure. If progress is overclaimed, EV is inflated, work remaining looks smaller, and TCPI looks easier than it is. Late-project TCPI is only as trustworthy as the percent-complete method behind EV.
Using TCPI to challenge a forecast
TCPI gives you a repeatable test for any proposed forecast:
- Compute the TCPI implied by the forecast.
- Compare it with the CPI achieved so far, and with the CPI of the last few reporting periods if you track them.
- If the implied TCPI is well above the achieved CPI, ask what will change. A new tool, a cheaper vendor, or finished rework are valid answers. "We will work harder" is not.
- If no credible change exists, the forecast is optimistic. Move to a method that assumes current performance continues.
The size of the gap that triggers a challenge is a judgment call. Some organizations set a threshold, for example flagging any TCPI more than 10% above CPI. Use your organization's rule if it has one, and state the threshold in the report.
Quick reference
| Question | Formula | Running project |
|---|---|---|
| Efficiency needed to hit the original budget | (BAC - EV) / (BAC - AC) | 1.1538 |
| Efficiency needed to hit the typical EAC | (BAC - EV) / (EAC - AC) | 0.8333 |
| Efficiency needed to hit the atypical EAC | (BAC - EV) / (EAC - AC) | 1.0 |
| Efficiency needed to hit the cost and schedule EAC | (BAC - EV) / (EAC - AC) | 0.6667 |
| Sanity check | TCPI against BAC / CPI equals CPI | 0.8333 |
Exercise
A project has BAC = 200,000, EV = 80,000 and AC = 100,000. (a) Calculate CPI. (b) Calculate TCPI against BAC. (c) The sponsor approves a revised budget of 250,000. Calculate TCPI against that figure. (d) Is the revised budget realistic compared with current performance?
Show answer
(a) CPI = 80,000 / 100,000 = 0.8. (b) Work remaining = 200,000 - 80,000 = 120,000. Funds remaining = 200,000 - 100,000 = 100,000. TCPI = 1.2. (c) Funds remaining = 250,000 - 100,000 = 150,000. TCPI = 120,000 / 150,000 = 0.8. (d) Yes. TCPI equals the current CPI of 0.8, so the revised budget only requires the team to keep performing as it has. Note that 250,000 is also the typical-method EAC (200,000 / 0.8), which is why the two values match.
Exercise
A project has BAC = 50,000, EV = 45,000 and AC = 52,000. Explain why TCPI against BAC cannot be used, and describe what you would do instead.
Show answer
Funds remaining against BAC is 50,000 - 52,000 = -2,000, which is negative. The formula gives 5,000 / -2,000 = -2.5, and a negative efficiency has no meaning. The original budget is already exhausted. Produce a new EAC (for example the typical method: CPI = 45,000 / 52,000 = 0.8654, EAC = 50,000 / 0.8654 = 57,778), get it approved as the new target, and compute TCPI against it: 5,000 / (57,778 - 52,000) = 0.8654.