Reading performance: CV, SV, CPI, and SPI
This chapter assumes you know the four inputs from the previous chapter: Budget at Completion (BAC), Planned Value (PV), Earned Value (EV), and Actual Cost (AC). It also assumes you can work with ratios and know what a baseline is. Here you turn those inputs into four performance measures. Every EAC formula in the rest of the tutorial uses them.
Why compare the inputs at all
PV, EV, and AC are money amounts at one point in time, called the status date. On their own they say little. AC of 48,000 could be good or bad. It depends on how much work that money bought and how much work you planned to have finished.
Two comparisons answer those questions:
- EV against AC compares the value of the work done with what it cost. This is cost performance.
- EV against PV compares the work done with the work planned by the status date. This is schedule performance.
EV is on both sides because it is the only measure of work actually accomplished, expressed in budget dollars. PV is the plan and AC is the spend. EV is the only one of the three that reports progress.
Each comparison can be taken two ways. A subtraction gives a variance in currency. A division gives an index, which is a unitless ratio.
| Measure | Formula | Compares | Unit |
|---|---|---|---|
| Cost Variance (CV) | EV - AC | Work done vs. money spent | Currency |
| Schedule Variance (SV) | EV - PV | Work done vs. work planned | Currency |
| Cost Performance Index (CPI) | EV / AC | Work done per unit of money spent | Ratio |
| Schedule Performance Index (SPI) | EV / PV | Work done per unit of work planned | Ratio |
Cost Variance and Schedule Variance
Cost Variance is the difference between the value you earned and the money you spent to earn it:
CV = EV - AC
- A positive CV means the work done cost less than its budget. You are under budget.
- A negative CV means the work done cost more than its budget. You are over budget.
- Zero means the work cost what it was budgeted to cost.
Schedule Variance is the difference between the value you earned and the value you planned to have earned:
SV = EV - PV
- A positive SV means more work is done than planned. You are ahead of schedule.
- A negative SV means less work is done than planned. You are behind schedule.
- Zero means you are on plan.
Keep the order EV first in both formulas. Some people memorize "actual minus budget" for cost, which flips the sign. Under the EV convention, a negative number is always bad news.
The running example uses BAC = 100,000, PV = 50,000, EV = 40,000, and AC = 48,000:
- CV = 40,000 - 48,000 = -8,000. The work done cost 8,000 more than its budget.
- SV = 40,000 - 50,000 = -10,000. The project has earned 10,000 less value than planned.
The unit of SV needs care. -10,000 is a quantity of budgeted work, not 10,000 of money lost. It does not say how many days late the project is. It says that 10,000 of budgeted work is not yet done.
Percent variances
A variance of -8,000 means different things on a 100,000 project and on a 10 million project. Dividing by a base puts variances on a common scale:
- CV% = CV / EV
- SV% = SV / PV
In the example, CV% = -8,000 / 40,000 = -20%, and SV% = -10,000 / 50,000 = -20%. The bases differ on purpose. Cost variance is measured against the value earned, and schedule variance against the value planned.
Cost Performance Index
CPI is the value you earn for each unit of money you spend:
CPI = EV / AC
- CPI above 1 means you earn more than a dollar of value per dollar spent. You are under budget.
- CPI equal to 1 means you are exactly on budget.
- CPI below 1 means each dollar spent earns less than a dollar of value. You are over budget.
In the example, CPI = 40,000 / 48,000 = 0.8333. Each dollar spent has earned about 83 cents of planned value. Put the other way, the work costs about 1.20 per 1.00 of budget (1 / 0.8333 = 1.2).
CPI is the most important number in the forecasting chapters that follow. The "current performance continues" method for EAC is BAC / CPI. If you misread CPI, every forecast built on it is wrong.
Schedule Performance Index
SPI is the fraction of planned work you have actually completed:
SPI = EV / PV
In the example, SPI = 40,000 / 50,000 = 0.8. The project has done 80% of the work it planned to have done by now.
Read the sign the same way as CPI: above 1 is ahead, below 1 is behind, 1 is on plan.
The signs can disagree
Cost and schedule are independent. A project can be ahead of schedule and over budget, or behind schedule and under budget. This code computes all four measures for three projects.
def evm_performance(pv, ev, ac):
"""Return CV, SV, CPI, and SPI for one status date."""
if ac <= 0:
raise ValueError("AC must be positive to compute CPI")
if pv <= 0:
raise ValueError("PV must be positive to compute SPI")
return {
"cv": ev - ac,
"sv": ev - pv,
"cpi": ev / ac,
"spi": ev / pv,
}
projects = {
"A": (50000, 40000, 48000), # behind schedule, over budget
"B": (40000, 45000, 50000), # ahead of schedule, over budget
"C": (60000, 55000, 50000), # behind schedule, under budget
}
for name, (pv, ev, ac) in projects.items():
r = evm_performance(pv, ev, ac)
print(
f"{name}: CV={r['cv']:+,} SV={r['sv']:+,} "
f"CPI={r['cpi']:.4f} SPI={r['spi']:.4f}"
)
# A: CV=-8,000 SV=-10,000 CPI=0.8333 SPI=0.8000
# B: CV=-5,000 SV=+5,000 CPI=0.9000 SPI=1.1250
# C: CV=+5,000 SV=-5,000 CPI=1.1000 SPI=0.9167Project B shows the common trap. It has done more work than planned (SPI 1.125), but it paid too much for that work (CPI 0.9). A status report that only says "ahead of schedule" hides a cost problem. Project C is the opposite. It spends efficiently but is late.
| Situation | CPI | SPI | Typical reading |
|---|---|---|---|
| Healthy | above 1 | above 1 | Under budget and ahead |
| Efficient but late | above 1 | below 1 | Cheap work, too little of it |
| Fast but costly | below 1 | above 1 | Work is ahead, bought at a premium |
| Troubled | below 1 | below 1 | Over budget and behind |
The table gives starting hypotheses. The numbers do not explain the cause. Project B might be ahead because it added staff, which would also explain the cost. Only the project team can tell you.
Variance or index: which one to use
Both forms carry the same direction (positive is good, negative is bad), but they answer different questions.
- Use variances to say how much. "We are 8,000 over on the work done so far" is a concrete amount a sponsor can reason about.
- Use indices to compare projects of different sizes and to feed formulas. A CPI of 0.83 means the same thing on a 50,000 project and a 5 million project. EAC formulas need ratios, not currency gaps.
CV and CPI always agree on direction. CV is negative exactly when CPI is below 1. The same holds for SV and SPI. If your report shows a negative CV with a CPI above 1, one of the inputs or formulas is wrong.
Edge cases and gotchas
Zero denominators
CPI is undefined when AC = 0, and SPI is undefined when PV = 0. These happen at the very start of a project, or when a work package has not begun. The function above raises an error rather than returning a misleading number. In a real report, show "n/a" for those items rather than 0 or 1.
Which scope the numbers cover
Every measure can be computed at several levels: a single work package, a phase, or the whole project. Indices at a lower level can be good while the project total is poor, and the reverse. Do not average the CPIs of work packages to get the project CPI. Sum EV and AC first, then divide:
Project CPI = (sum of EV) / (sum of AC)
Averaging ratios gives small packages the same weight as large ones. It produces the wrong answer.
Cumulative versus period values
The examples use cumulative values, meaning everything from the project start to the status date. Cumulative CPI is the number used for forecasting because it reflects the whole history. You can also compute CPI for a single period, such as the last month. A cumulative CPI of 0.83 with a recent-period CPI of 0.95 suggests the project is recovering. The same cumulative CPI with a recent-period CPI of 0.70 suggests it is getting worse. Cumulative CPI alone cannot tell these cases apart.
SPI drifts toward 1 near the end
SV and SPI measure work in money units, not time. As a project finishes, EV approaches BAC and PV also reaches BAC, so SV returns to 0 and SPI returns to 1 whether or not the project was late. A project that finishes two months late ends with SPI = 1.0. SPI and SV are only informative while the project is still running. This is why late in a project many teams supplement them with a time-based schedule measure (earned schedule), which this tutorial does not cover.
Poor EV inputs
All four measures depend on EV, so an error in EV spreads to all of them. If progress is credited too generously, for example by reporting tasks as 90% complete when they are only half done, then EV is too high. CV and SV look better than reality, and CPI and SPI are inflated. Using fixed rules for crediting progress, such as 0/100 or 50/50 for short tasks, protects against this.
Connecting to forecasting
The four measures describe the past: where the project stands today. The forecast methods in the next chapters turn that description into a prediction. They do it by asking what the CPI, and sometimes the SPI, say about the work still to do. In the example project, CPI = 0.8333 will reappear as the divisor in EAC = BAC / CPI = 120,000. The SPI of 0.8 will join CPI in the combined formula that gives 138,000. For now, make sure you can produce the four numbers quickly and read their signs correctly.
Exercise
A project has BAC = 200,000. At the status date, PV = 80,000, EV = 70,000, and AC = 65,000. Calculate CV, SV, CPI, and SPI, and say in one sentence what the numbers mean.
Show answer
CV = EV - AC = 70,000 - 65,000 = +5,000. SV = EV - PV = 70,000 - 80,000 = -10,000. CPI = 70,000 / 65,000 = 1.0769. SPI = 70,000 / 80,000 = 0.875. The project is under budget on the work done (each dollar earns about 1.08 of value) but behind schedule, having completed 87.5% of the planned work.
Exercise
A report shows CV = -3,000 and CPI = 1.05 for the same project at the same date. Can both be correct? Explain, and state the rule you used.
Show answer
No. CV and CPI must agree in direction. A negative CV means EV is less than AC, so CPI = EV / AC must be below 1. A CPI of 1.05 would need EV greater than AC, which gives a positive CV. At least one input or formula in the report is wrong, so check EV and AC first.
Exercise
A project has three work packages with (EV, AC) of (10,000, 8,000), (30,000, 40,000), and (60,000, 52,000). Find the project CPI, and explain why averaging the three package CPIs gives a different result.
Show answer
Sum EV = 100,000 and sum AC = 100,000, so project CPI = 1.0. The package CPIs are 1.25, 0.75, and 1.1538. Their simple average is 1.0513, which is higher than 1.0 because it gives the small, efficient package the same weight as the large ones. The correct project CPI is total EV divided by total AC.