Sub topic 5
EAC When Current Cost Performance Will Continue
This chapter assumes you can already read the four earned value inputs (BAC, PV, EV, AC) and compute CV, SV, CPI and SPI. It also assumes you know what a baseline is. If CPI as "earned value per dollar spent" is not yet familiar, review the earlier chapters on those measures first.
By the end you will be able to:
- Compute EAC with BAC / CPI.
- Explain why that formula is a statement about the future, not just arithmetic.
- Decide which CPI to feed it.
- Recognize the cases where it breaks.
The idea behind the formula
An Estimate at Completion (EAC) is a forecast of the total cost of the project when it finishes. The formula in this chapter answers one question: what if the rest of the project costs the same per unit of work as the work done so far?
CPI is earned value divided by actual cost. A CPI of 0.8333 means each dollar spent has produced 83.33 cents of planned work. If that rate holds, every remaining dollar of budgeted work will cost 1 / 0.8333 = 1.20 dollars. So the whole project costs 1.20 times its budget:
EAC = BAC / CPIApply this to the running example used throughout the tutorial:
- BAC = 100,000
- PV = 50,000
- EV = 40,000
- AC = 48,000
CPI = 40,000 / 48,000 = 0.8333, so EAC = 100,000 / 0.8333 = 120,000.
The project is forecast to finish 20,000 over budget. Compare this with the previous chapter, where the same data gave 108,000 when the overrun was treated as a one-off. The only difference between the two forecasts is an assumption about the future. The data is identical.
Where BAC / CPI comes from
Many textbooks present this formula in a longer form:
EAC = AC + (BAC - EV) / CPIRead it in two parts:
- AC is what you have already spent. It is a sunk fact.
- (BAC - EV) is the budgeted value of the work still to do. Dividing by CPI converts that budgeted value into the cost you now expect to pay for it.
The two forms are the same number. Since CPI = EV / AC, we have EV / CPI = AC. Then:
AC + (BAC - EV) / CPI
= AC + BAC / CPI - EV / CPI
= AC + BAC / CPI - AC
= BAC / CPIThe longer form is useful because it shows the structure that every EAC formula shares: actual cost plus an estimate of the remaining cost. The short form is useful for quick calculation. When you later study other methods, they differ only in what they put in the second term.
The cost of the remaining work is the ETC (Estimate to Complete), so this chapter's method gives:
ETC = (BAC - EV) / CPIWith the example: (100,000 - 40,000) / 0.8333 = 72,000. Check: AC + ETC = 48,000 + 72,000 = 120,000.
Computing it in code
The functions below guard against the division problems covered later. They also confirm that the short and long forms agree.
def eac_typical(bac, ev, ac):
"""EAC assuming cumulative cost performance continues: BAC / CPI."""
if ev <= 0 or ac <= 0:
raise ValueError("EV and AC must both be positive to compute CPI")
cpi = ev / ac
return bac / cpi
def eac_from_remaining(bac, ev, ac, cpi_future):
"""Long form: actual cost plus remaining budgeted work at cpi_future."""
if cpi_future <= 0:
raise ValueError("cpi_future must be positive")
return ac + (bac - ev) / cpi_future
bac, ev, ac = 100000, 40000, 48000
cpi = ev / ac
print(round(eac_typical(bac, ev, ac))) # 120000
print(round(eac_from_remaining(bac, ev, ac, cpi))) # 120000
print(round((bac - ev) / cpi)) # 72000 (ETC)The long form takes the CPI as a parameter. That makes it the more flexible of the two, because you can pass in a CPI other than the cumulative one, as the next section explains.
Which CPI should you use?
The textbook formula uses the cumulative CPI: total EV to date divided by total AC to date. That is a choice, and a reasonable one. It is the most stable number available, and it uses all the evidence so far. But it has a weakness. It averages old and new performance. If the team was efficient early and has been slipping recently, the cumulative CPI looks better than the current trend and the forecast comes out too low.
Practitioners often compare the cumulative CPI with a recent CPI, computed from the change in EV and AC over the last few periods. A recent CPI uses only the increments:
recent CPI = (EV_now - EV_start_of_window) / (AC_now - AC_start_of_window)The following program applies this to four months of cumulative data:
history = [ # (cumulative EV, cumulative AC) at the end of each month
(8000, 8000),
(18000, 19000),
(29000, 33000),
(40000, 48000),
]
def windowed_cpi(history, periods):
"""CPI over the last `periods` periods, from cumulative figures."""
h = [(0, 0)] + history
ev0, ac0 = h[-periods - 1]
ev1, ac1 = h[-1]
return (ev1 - ev0) / (ac1 - ac0)
bac = 100000
ev, ac = history[-1]
for label, cpi in [
("cumulative", ev / ac),
("last 3 months", windowed_cpi(history, 3)),
("last month", windowed_cpi(history, 1)),
]:
eac = ac + (bac - ev) / cpi
print(f"{label:14s} CPI={cpi:.4f} EAC={eac:,.0f}")The output is:
cumulative CPI=0.8333 EAC=120,000
last 3 months CPI=0.8000 EAC=123,000
last month CPI=0.7333 EAC=129,818Cost performance has been getting worse each month. The cumulative figure is the most optimistic of the three, and the single-month figure is the most pessimistic. A spread of about 10,000 between them is useful information. It tells the sponsor that the forecast depends on which period you trust.
A few rules of thumb help here:
- Use the cumulative CPI as the default and as the number you report consistently from period to period.
- Compute a recent CPI over about three periods as a sensitivity check.
- A single-period CPI is noisy. One large invoice or one milestone credited late can swing it. Do not forecast from it alone.
- If the cumulative and recent CPI diverge, find out why before choosing. The cause may be a real change, such as a new vendor, a rate increase or a team change. It may also be a timing artifact in how costs were recorded.
A decision flow for this method
This method is one of several. The diagram below shows the questions that point you to it.
When the formula behaves badly
CPI equal to zero or undefined
If AC is zero, CPI is undefined, because you cannot divide by it. If EV is zero while AC is positive, CPI is zero and BAC / CPI is a division by zero. In both cases the project is too early or too broken for this method. Spend a period or two gathering data, or use a bottom-up estimate.
Very early in the project
CPI computed from a few days of data can swing wildly. A common reference point in the earned value literature is that cumulative CPI tends to stabilize once a project is roughly 20 percent complete. Treat that as a guideline, not a law. Before that point, label any BAC / CPI forecast as provisional.
CPI above 1
A CPI over 1 means the project is under budget so far, and BAC / CPI gives an EAC below BAC. The arithmetic is valid. The assumption is the risky part. Projects often find the easy work first, so an early surplus can disappear. Before you report a favorable forecast, ask whether the remaining work is comparable to what has been done.
Schedule trouble hidden behind a good CPI
CPI says nothing about whether work is on time. A project can have a healthy CPI and a poor SPI, because it is cheap but late. BAC / CPI assumes the remaining work costs the same per unit, and it ignores any extra cost from finishing late, such as extended overhead, rework or overtime. When the schedule is also slipping, the next chapter's combined method is more appropriate.
Rounding and precision
Rounding CPI to two decimals before dividing changes the answer. With CPI 0.83 instead of 0.8333, the EAC becomes 120,482 instead of 120,000. Carry full precision through the calculation and round only the reported result.
Mixing units
BAC, EV and AC must all be in the same currency and use the same baseline. If the budget was re-baselined after approved changes, use the revised BAC and the EV measured against it. Mixing an old BAC with new EV values produces a CPI that means nothing.
What the result tells you
The EAC is a forecast, not a measurement. Its value comes from the assumption behind it, which you should state explicitly when you report it. A good one-line statement is:
"Assuming cost performance stays at the cumulative CPI of 0.83, the project is forecast to cost 120,000, which is 20,000 over the 100,000 budget."
That sentence names the method, the key input and the gap to budget. The gap is the Variance at Completion, which a later chapter develops.
The method also sits at a specific place among the alternatives, using the same running data:
| Method | Assumption | EAC |
|---|---|---|
| AC + (BAC - EV) | The overrun was a one-off | 108,000 |
| BAC / CPI | Current cost efficiency continues | 120,000 |
| AC + (BAC - EV) / (CPI x SPI) | Cost and schedule efficiency both continue | 138,000 |
BAC / CPI sits between the other two. It is more pessimistic than the one-off method, because it carries the inefficiency forward. It is more optimistic than the combined method, because it ignores schedule pressure. Seeing the three numbers side by side is often more valuable to a sponsor than any single one.
Common mistakes
- Using BAC / SPI by accident. SPI measures schedule efficiency, not cost.
- Dividing AC by EV, which inverts CPI and gives an EAC below BAC for a project that is over budget.
- Forgetting that BAC / CPI already includes the money spent. Adding AC on top of it double counts.
- Reporting the EAC without the CPI behind it, so that nobody can judge whether the assumption is credible.
- Using the method automatically because the formula is short. The right test is whether the cost drivers behind the variance still apply to the remaining work.
Exercises
Exercise
A project has BAC = 250,000, EV = 90,000 and AC = 100,000. Using the assumption that current cost performance continues, compute CPI, EAC and ETC.
Show answer
CPI = 90,000 / 100,000 = 0.9. EAC = 250,000 / 0.9 = 277,778 (rounded). ETC = EAC - AC = 277,778 - 100,000 = 177,778. Check with the direct form: (250,000 - 90,000) / 0.9 = 177,778.
Exercise
Show algebraically why AC + (BAC - EV) / CPI equals BAC / CPI, and say what this tells you about how the method treats money already spent.
Show answer
Since CPI = EV / AC, EV / CPI = AC. Then AC + BAC / CPI - EV / CPI = AC + BAC / CPI - AC = BAC / CPI. The method keeps actual cost exactly as spent. It applies the current inefficiency only to the work still to be done. The earlier overrun is carried into the total through AC, so it is not counted a second time.
Exercise
A project is 15 percent complete. Its cumulative CPI is 0.95, but over the last three periods the CPI was 0.80. Which CPI would you use for the headline EAC, and what would you tell the sponsor?
Show answer
Report the cumulative CPI of 0.95 as the headline, because it is stable and consistent between reporting periods. Also show the EAC at 0.80 as a downside case. The project is early, so the cumulative figure is provisional. The gap between 0.95 and 0.80 suggests cost performance is deteriorating, and the cause should be investigated. If the cause is expected to persist, the lower CPI is the better basis for the forecast.