Sub topic 8
EAC when cost and schedule both drive the outcome
This chapter assumes you can already compute CV, SV, CPI, and SPI from BAC, PV, EV, and AC. It also assumes you know the two simpler EAC formulas from earlier chapters: AC + (BAC - EV) for a one-off overrun and BAC / CPI for a continuing cost trend. Here you will learn the third formula, which lets schedule performance push the forecast as well. You will also learn when that formula helps and when it misleads.
Why a third formula exists
The typical formula, BAC / CPI, assumes that the cost efficiency seen so far will continue. It says nothing about schedule. In many projects, though, a late project costs more to finish. Delays extend the time that staff, equipment, and overhead are charged. Late work may need overtime, expediting fees, or rework to catch up. In those cases cost and schedule pull on the final number together.
The combined formula folds both indices into the work that remains:
EAC = AC + (BAC - EV) / (CPI x SPI)Read it in two parts:
ACis money already spent. It is a sunk fact, so it is added unchanged.(BAC - EV)is the budgeted value of the work still to do. Dividing it byCPI x SPIinflates that remaining work according to how poorly the project has performed on both cost and schedule.
This is the same structure as the atypical formula, AC + (BAC - EV), with a performance factor in the denominator. The atypical formula uses a factor of 1. The typical formula, BAC / CPI, is the same as AC + (BAC - EV) / CPI. Only the divisor differs between the three, so you can think of the divisor as your assumption about future efficiency.
Worked example
Use the same project data as the earlier chapters:
| Measure | Value |
|---|---|
| BAC | 100,000 |
| PV | 50,000 |
| EV | 40,000 |
| AC | 48,000 |
| CPI (EV / AC) | 0.8333 |
| SPI (EV / PV) | 0.8 |
The product CPI x SPI is 0.8333 x 0.8 = 0.6667. The remaining budgeted work is 100,000 - 40,000 = 60,000. Dividing gives 60,000 / 0.6667 = 90,000. Adding actual cost gives 48,000 + 90,000 = 138,000.
The same calculation in Python, with the derived figures alongside:
def evm_indices(pv, ev, ac):
return {"CPI": ev / ac, "SPI": ev / pv}
def eac_cost_schedule(bac, pv, ev, ac):
idx = evm_indices(pv, ev, ac)
return ac + (bac - ev) / (idx["CPI"] * idx["SPI"])
bac, pv, ev, ac = 100000, 50000, 40000, 48000
eac = eac_cost_schedule(bac, pv, ev, ac)
etc = eac - ac
vac = bac - eac
tcpi_eac = (bac - ev) / (eac - ac)
print(round(eac)) # 138000
print(round(etc)) # 90000
print(round(vac)) # -38000
print(round(tcpi_eac, 4)) # 0.6667Compare this with the other methods on the same data:
| Method | Formula | EAC |
|---|---|---|
| Atypical variance | AC + (BAC - EV) | 108,000 |
| Typical, cost trend | BAC / CPI | 120,000 |
| Cost and schedule | AC + (BAC - EV) / (CPI x SPI) | 138,000 |
The forecast rises from 108,000 to 138,000 because each method makes a stronger assumption about the future. The combined method projects that the remaining 60,000 of work will cost 90,000, a 50% overrun on the remaining work. The typical method projects 72,000, a 20% overrun.
Notice the TCPI result. Against the new EAC, the required efficiency is 0.6667, which equals CPI x SPI. This is not a coincidence. If you assume the future will run at CPI x SPI, then the efficiency needed to hit that forecast is exactly that value. A TCPI against EAC that equals your assumed efficiency is a useful consistency check on your arithmetic.
How the formula behaves
Three properties of the formula matter in practice.
- Both indices below 1 compound. With CPI 0.83 and SPI 0.8 the divisor is 0.67, which is lower than either index. The forecast is therefore always at least as high as the typical forecast when both indices are under 1.
- The indices can cancel. If one index is above 1 and the other is below 1, the product moves toward 1 and the forecast moves toward the atypical value. This is the most common source of misleading results, covered next.
- SPI is a poor predictor late in the project. EV and PV both reach BAC at the end of the project, so SPI drifts toward 1.0 even for a project that finished months late. The schedule signal weakens as work completes.
Gotcha: when the indices cancel
Consider a project that is ahead of schedule but over cost:
bac, pv, ev, ac = 100000, 40000, 50000, 62500
cpi = ev / ac # 0.8
spi = ev / pv # 1.25
eac_typical = bac / cpi
eac_combined = ac + (bac - ev) / (cpi * spi)
print(round(cpi, 2), round(spi, 2)) # 0.8 1.25
print(round(eac_typical)) # 125000
print(round(eac_combined)) # 112500Here CPI x SPI equals exactly 1.0. The combined formula reports 112,500, which is the same as assuming no future inefficiency at all. Yet the project is spending 1.25 for each 1.0 of value earned. Being ahead of schedule did nothing to make the remaining work cheaper. The combined formula has treated an early finish as a cost offset, which is rarely true.
Weighted variants
Some organizations do not trust an equal weighting of cost and schedule. A common variation gives each index a weight:
EAC = AC + (BAC - EV) / (w1 x CPI + w2 x SPI)The weights w1 and w2 sum to 1. Typical choices are 0.8 for CPI and 0.2 for SPI, or 0.5 and 0.5. This is an addition of two terms rather than a product, so the divisor stays between the two indices instead of falling below both. It also avoids the cancellation problem to a degree, because a high SPI only lifts the divisor in proportion to its weight.
def eac_weighted(bac, pv, ev, ac, w_cpi=0.8, w_spi=0.2):
cpi, spi = ev / ac, ev / pv
return ac + (bac - ev) / (w_cpi * cpi + w_spi * spi)
print(round(eac_weighted(100000, 50000, 40000, 48000))) # 120581For the main example, the weighted forecast is 120,581. That is close to the typical forecast of 120,000 because the 0.8 weight makes CPI dominant. The weights are a judgment call, not a standard. If you use them, record the weights and the reason for them alongside the result. A stakeholder who sees 120,581 will otherwise have no way to tell it from the typical result.
Choosing the combined method
The combined formula suits a project when these conditions hold:
- Schedule delay carries a cost of its own, such as time-based staffing, rented equipment, or contractual penalties.
- The causes of the past variance are likely to persist, so the trend is meaningful.
- Substantial work remains, so SPI still carries information. As a rough guide, be cautious once the project is beyond 70 to 80 percent complete.
- Both indices are below 1, or at least do not point in opposite directions.
Avoid it, or cross-check it, when:
- The delay came from a one-off cause such as a late delivery that has since arrived. Use the atypical formula.
- SPI is above 1 while CPI is below 1, as in the cancellation example.
- The remaining work is very different from the work done so far. A bottom-up estimate is then more defensible than any ratio.
When you report the figure, state the assumption in plain terms: "We forecast 138,000 because we expect the remaining work to run at both the cost efficiency and the schedule efficiency seen to date." That sentence is what lets a sponsor challenge the assumption instead of the arithmetic.
Common errors
- Using SPI from a different period than CPI. Both indices must use the same status date. Mixing a cumulative CPI with a single-period SPI produces a divisor that no one can explain.
- Applying the formula to BAC instead of remaining work. Writing
BAC / (CPI x SPI)throws away the spent money and gives 150,000 for the main example, which is wrong. TheACplus remaining-work structure is what keeps actual cost out of the inflation. - Treating the result as a point value. The combined formula is usually the pessimistic end of the range of EAC values. Present it as the upper bound, with the atypical formula as the lower bound.
- Forgetting SPI is based on value, not days. An SPI of 0.8 means 80% of planned value has been earned. It does not mean the project is 20% behind in calendar time, so do not convert it into dates.
Summary of the method
- Compute CPI and SPI at the same status date.
- Compute remaining work as
BAC - EV. - Divide it by
CPI x SPI, or a weighted blend, and addAC. - Derive ETC as
EAC - AC, and VAC asBAC - EAC. - Check TCPI against the new EAC. It should equal your assumed efficiency.
- Compare with the typical and atypical forecasts, and explain any large gap.
Exercise
A project has BAC = 200,000, PV = 120,000, EV = 90,000, and AC = 100,000. Using the combined cost and schedule method, calculate CPI, SPI, EAC, ETC, and VAC.
Show answer
CPI = 90,000 / 100,000 = 0.9. SPI = 90,000 / 120,000 = 0.75. CPI x SPI = 0.675. Remaining work = 200,000 - 90,000 = 110,000. Inflated remaining work = 110,000 / 0.675 = 162,963 (rounded). EAC = 100,000 + 162,963 = 262,963. ETC = EAC - AC = 162,963. VAC = BAC - EAC = 200,000 - 262,963 = -62,963, so the project is forecast to finish about 62,963 over budget.
Exercise
A project has BAC = 100,000, PV = 40,000, EV = 50,000, and AC = 62,500. The combined formula gives an EAC of 112,500, but the typical formula gives 125,000. Which would you report as the more cautious forecast, and why does the combined formula understate the overrun?
Show answer
Report 125,000. CPI is 0.8 and SPI is 1.25, so CPI x SPI is exactly 1.0 and the combined formula assumes the remaining work will cost its budgeted amount. Being ahead of schedule does not make the remaining work cheaper, so the schedule lead cancels a real cost inefficiency. The typical formula, BAC / CPI, keeps the 0.8 cost efficiency and is the safer figure.
Exercise
For the main example (BAC 100,000, EV 40,000, AC 48,000, combined EAC 138,000), calculate TCPI against EAC and explain why it equals CPI x SPI.
Show answer
TCPI against EAC = (BAC - EV) / (EAC - AC) = 60,000 / 90,000 = 0.6667. The EAC was built by dividing the remaining work of 60,000 by CPI x SPI = 0.6667, so the forecast remaining cost is 60,000 / 0.6667 = 90,000. Dividing the remaining work by that remaining cost returns the same 0.6667. The result confirms the forecast assumes future efficiency equals the current CPI x SPI.