Variance at Completion: the forecast gap to budget
This chapter assumes you can already compute BAC, PV, EV, AC, CV, SV, CPI and SPI. It also assumes you know the EAC and ETC formulas from the earlier chapters. Here you use those forecasts to answer one question: how far from the budget will the project finish?
What VAC measures
Variance at Completion (VAC) is the difference between the original budget and the forecast final cost:
VAC = BAC - EACBAC is the Budget at Completion, the approved total budget. EAC is the Estimate at Completion, your current forecast of the final cost.
The sign tells you the direction:
- A negative VAC means the forecast final cost is above budget. You expect an overrun.
- A positive VAC means the forecast is below budget. You expect an underrun.
- A VAC of zero means the forecast matches the budget.
VAC looks like the cost variance (CV), but they measure different things. CV is EV - AC, so it describes the past: how far ahead or behind on cost you are today. VAC is a forecast of the whole project. It depends on your EAC method, so changing the method changes the VAC.
CV = EV - AC (to date, a fact)
VAC = BAC - EAC (at completion, a forecast)The running example
The chapters in this tutorial share one data set:
| Measure | Value |
|---|---|
| BAC | 100,000 |
| PV | 50,000 |
| EV | 40,000 |
| AC | 48,000 |
| CPI | 0.8333 |
| SPI | 0.8 |
| CV | -8,000 |
The project is behind schedule (SPI below 1) and over cost (CPI below 1). The only question is how bad the final result will be.
Computing VAC
VAC needs only an EAC. Here is the function applied to the three formula-based EAC methods:
def vac(bac, eac):
return bac - eac
bac, pv, ev, ac = 100000, 50000, 40000, 48000
cpi, spi = ev / ac, ev / pv
eac_atypical = ac + (bac - ev)
eac_typical = bac / cpi
eac_cost_schedule = ac + (bac - ev) / (cpi * spi)
for name, eac in [
("atypical", eac_atypical),
("typical", eac_typical),
("cost and schedule", eac_cost_schedule),
]:
gap = vac(bac, eac)
print(f"{name:18} EAC={round(eac):>7} VAC={round(gap):>7} ({gap / bac:.0%} of BAC)")This prints:
atypical EAC= 108000 VAC= -8000 (-8% of BAC)
typical EAC= 120000 VAC= -20000 (-20% of BAC)
cost and schedule EAC= 138000 VAC= -38000 (-38% of BAC)All three results are negative, so every method forecasts an overrun. The size of the overrun ranges from 8% to 38% of the budget, depending on what you assume about the remaining work. VAC does not tell you which method is right. It shows how much the answer depends on that choice.
Closed forms worth knowing
Substituting the EAC formulas into BAC - EAC gives shortcuts. They are useful for sanity checks.
Atypical variance
VAC = BAC - (AC + BAC - EV)
= EV - AC
= CVIf the past overrun is a one-off and the rest of the work goes to plan, the final overrun equals the cost variance you already have. In the example, both are -8,000. You expect no further loss and no recovery.
Typical variance
VAC = BAC - BAC / CPI
= BAC x (1 - 1 / CPI)If the current efficiency continues, the overrun scales with the budget and with how far CPI is below 1. With CPI of 0.8333, 1 - 1/0.8333 is -0.2, so VAC is -20% of BAC. Note that VAC is a fixed share of BAC under this method, whatever the progress. A project at 10% complete and one at 90% complete with the same CPI forecast the same percentage overrun.
Using ETC
Because EAC = AC + ETC, you can also write:
VAC = BAC - AC - ETCThis form reads naturally: the budget left after what you have spent, minus what you still expect to spend. In the typical case, 100,000 - 48,000 - 72,000 = -20,000. If this form and BAC - EAC disagree, one of your inputs is wrong.
Bottom-up EAC and VAC
For a bottom-up forecast, the team re-estimates the remaining work from scratch. Suppose that estimate is 65,000. Then:
bac, ac = 100000, 48000
new_etc = 65000
eac = ac + new_etc # 113000
print(bac - eac) # -13000VAC is -13,000. This falls between the atypical and typical results. That is plausible: the team believes the remaining work will go better than the current trend but worse than the original plan. Compare the bottom-up VAC with the formula-based ones. If it is far outside the range, ask why. Either the team knows something the data does not, or the estimate is too optimistic.
Comparing forecasts
Putting the methods side by side shows what each one assumes:
| Method | Assumption about remaining work | EAC | VAC | VAC as % of BAC |
|---|---|---|---|---|
| Atypical | Past variance will not repeat | 108,000 | -8,000 | -8% |
| Typical | Current CPI continues | 120,000 | -20,000 | -20% |
| Cost and schedule | CPI and SPI both drive cost | 138,000 | -38,000 | -38% |
| Bottom-up | Team re-estimates remaining work | 113,000 | -13,000 | -13% |
The bottom-up row uses the 65,000 estimate from the previous section.
Interpreting the number
A raw VAC in currency units is hard to judge without context. Three habits make it more useful.
- Express it as a percentage of BAC. An overrun of 20,000 on a 100,000 project is serious. The same figure on a 10,000,000 project is within normal noise. Many organizations set thresholds on the percentage, such as amber at 5% and red at 10%. Use your own organization's thresholds if it has them.
- Compare it with reserves. If a contingency or management reserve exists, a negative VAC smaller than the reserve may be absorbable. The reserve is not part of BAC, so check how your organization defines it before relying on this.
- Track it over time. A VAC that moves from -3% to -8% to -15% over three reporting periods shows a trend that a single value hides. A VAC that is stable around -8% suggests the overrun is contained.
Cross-checking VAC with TCPI
VAC tells you the size of the forecast gap. It does not tell you whether the forecast is believable. The To-Complete Performance Index (TCPI) covers that, and a later chapter treats it in full. Here is the connection.
Use TCPI against BAC:
TCPI(BAC) = (BAC - EV) / (BAC - AC)In the example this is 60,000 / 52,000 = 1.1538. To finish on budget, the team must get 1.1538 units of value for each unit spent from now on. Its record so far is 0.8333. If you also reported a VAC of zero, you would be claiming that the team will improve its efficiency by about 38%. A negative VAC is the honest counterpart of a TCPI well above the current CPI.
Use this as a quick plausibility test:
- If VAC is near zero and TCPI(BAC) is far above CPI, the forecast is probably too optimistic.
- If VAC is negative and TCPI(EAC) is close to the current CPI, the forecast is internally consistent. In the example, TCPI(EAC) is
60,000 / 72,000 = 0.8333, which equals CPI.
Common errors
- Reversing the subtraction.
EAC - BACgives the opposite sign. Always writeBAC - EAC, and check that a forecast overrun produces a negative number. - Mixing EAC methods across periods. If you report VAC from the typical method in March and the atypical method in April, the change in VAC reflects the method and not the project. Record which method produced each value.
- Treating VAC as a prediction of the rework. VAC is the total gap at completion. It includes the overrun already incurred. In the atypical case, the whole VAC is the overrun already in the past.
- Dividing by zero. CPI needs a non-zero AC, and SPI needs a non-zero PV. Early in a project, guard these calculations. The typical EAC also fails when EV is zero, because CPI is then zero.
- Using unreliable inputs. VAC inherits every error in EV, AC and BAC. If progress is reported optimistically, EV is too high, CPI looks better than it is, and VAC understates the overrun.
- Ignoring baseline changes. If the baseline is formally changed, BAC changes with it. VAC must then be computed against the current approved BAC, and the earlier values are not comparable without a note.
A reusable function
This function guards against the division errors above and reports the sign in words:
def vac_report(bac, ac, ev, pv, method="typical", new_etc=None):
if ac <= 0 or pv <= 0 or ev <= 0:
raise ValueError("AC, PV and EV must be greater than zero")
cpi, spi = ev / ac, ev / pv
if method == "atypical":
eac = ac + (bac - ev)
elif method == "typical":
eac = bac / cpi
elif method == "cost_schedule":
eac = ac + (bac - ev) / (cpi * spi)
elif method == "bottom_up":
if new_etc is None:
raise ValueError("bottom_up needs new_etc")
eac = ac + new_etc
else:
raise ValueError("unknown method: " + method)
gap = bac - eac
direction = "over budget" if gap < 0 else "under budget" if gap > 0 else "on budget"
return round(eac), round(gap), round(gap / bac * 100, 1), direction
print(vac_report(100000, 48000, 40000, 50000, "typical"))
print(vac_report(100000, 48000, 40000, 50000, "bottom_up", new_etc=65000))The output is:
(120000, -20000, -20.0, 'over budget')
(113000, -13000, -13.0, 'over budget')Summary
VAC is BAC - EAC. A negative value means a forecast overrun. It equals CV under the atypical method and BAC x (1 - 1/CPI) under the typical method. State the method used, give the figure as a percentage of BAC, and check it against TCPI.
Exercise
A project has BAC = 200,000, EV = 80,000 and AC = 100,000. (a) Compute CPI. (b) Compute EAC and VAC using the typical method. (c) Compute VAC using the atypical method and say how it relates to CV.
Show answer
(a) CPI = 80,000 / 100,000 = 0.8. (b) EAC = 200,000 / 0.8 = 250,000, so VAC = 200,000 - 250,000 = -50,000, a 25% forecast overrun. (c) Atypical EAC = 100,000 + (200,000 - 80,000) = 220,000, so VAC = -20,000. This equals CV = 80,000 - 100,000 = -20,000, because the atypical method assumes no further variance.
Exercise
A manager reports VAC = 0 for a project with CPI = 0.85 and TCPI(BAC) = 1.20. Is the forecast credible? What does it imply about the team's future performance?
Show answer
It is not credible without a specific reason. A VAC of 0 means the project finishes exactly on budget, which requires an efficiency of 1.20 on the remaining work. The team has delivered only 0.85 so far, so it would need to improve by about 41% (1.20 / 0.85). Unless something concrete has changed, such as a fixed cause, new staffing or a renegotiated contract, the forecast should be revised to a negative VAC.