01Chapter 1: The inputs: BAC, PV, EV, and ACEvery earned value forecast starts from four numbers. If any of them is wrong, every later result is wrong too: the variances, the indices, the Estimate at Completion (EAC) and the Estimate to Complete (ETC). This chapter defines each input, shows where its value comes from, and gives you checks to 7 min read
02Chapter 2: Reading performance: CV, SV, CPI, and SPIThis chapter assumes you know the four inputs from the previous chapter: Budget at Completion (BAC), Planned Value (PV), Earned Value (EV), and Actual Cost (AC). It also assumes you can work with ratios and know what a baseline is. Here you turn those inputs into four performance measures. Every EAC8 min read
03Chapter 3: What EAC and ETC are, and how they fit togetherThis chapter defines Estimate at Completion (EAC) and Estimate to Complete (ETC), shows how they relate to actual cost, and explains why every forecasting method in the later chapters is a different way of estimating the same thing. It assumes you know the four earned value inputs from the earlier c7 min read
04Chapter 4: EAC when the overrun was a one-offThis chapter assumes you can already compute BAC, PV, EV, AC, CV, SV, CPI and SPI from earlier in the tutorial. It also assumes you know that Estimate at Completion (EAC) is the forecast of total project cost. Here you will learn the first of the EAC formulas, the one for variances that will not rep7 min read
05Chapter 5: EAC when current cost performance will continueThis chapter assumes you can already read the four earned value inputs (BAC, PV, EV, AC) and compute CV, SV, CPI and SPI. It also assumes you know what a baseline is. If CPI as "earned value per dollar spent" is not yet familiar, review the earlier chapters on those measures first.8 min read
06Chapter 6: From EAC to ETC: how much is left to spendThis chapter assumes you can compute BAC, PV, EV, AC, CPI and SPI. It also assumes you have seen the EAC formulas from the previous chapters. Here the focus is the Estimate to Complete (ETC): what it measures, how to derive it two ways, and where people get it wrong.7 min read
07Chapter 7: Variance at Completion: the forecast gap to budgetThis chapter assumes you can already compute BAC, PV, EV, AC, CV, SV, CPI and SPI. It also assumes you know the EAC and ETC formulas from the earlier chapters. Here you use those forecasts to answer one question: how far from the budget will the project finish?6 min read
08Chapter 8: EAC when cost and schedule both drive the outcomeThis chapter assumes you can already compute CV, SV, CPI, and SPI from BAC, PV, EV, and AC. It also assumes you know the two simpler EAC formulas from earlier chapters: AC + (BAC - EV) for a one-off overrun and BAC / CPI for a continuing cost trend. Here you will learn the third formula, which l7 min read
09Chapter 9: Bottom-up EAC: re-estimating the remaining workThis chapter assumes you know BAC, PV, EV, AC, CPI and SPI. It also assumes you have used the formula-based EAC methods from earlier chapters, and that you know the relation EAC = AC + ETC. It covers the one forecast that does not rely on a performance ratio: the bottom-up estimate.8 min read
10Chapter 10: TCPI: the efficiency the remaining work demandsThe To-Complete Performance Index (TCPI) is the cost efficiency the team must achieve on the remaining work to hit a chosen financial target. This chapter assumes you can already calculate BAC, PV, EV, AC, CPI, EAC, ETC and VAC from the earlier chapters. It also assumes you know the standard EAC for6 min read
11Chapter 11: Choosing and justifying a methodThis chapter assumes you can already compute CPI, SPI, BAC, PV, EV and AC, and that you know the three formula-based EAC methods and the bottom-up method from earlier chapters. The question here is which one to report and how to defend that choice. The formulas are quick to calculate. The judgment b9 min read
12Chapter 12: Pitfalls and how to report a forecastThis chapter assumes you can compute BAC, PV, EV, AC, CPI, SPI, the three formula-based EAC methods, ETC, VAC, and TCPI. Here you will learn where those numbers go wrong and how to present a forecast so stakeholders can trust it and act on it.7 min read