Sub topic 9
Bottom-up EAC: re-estimating the remaining work
This chapter assumes you know BAC, PV, EV, AC, CPI and SPI. It also assumes you have used the formula-based EAC methods from earlier chapters, and that you know the relation EAC = AC + ETC. It covers the one forecast that does not rely on a performance ratio: the bottom-up estimate.
What a bottom-up EAC is
A formula-based EAC takes the project's history and extrapolates it. The atypical formula assumes the past overrun will not repeat. The typical formula assumes the current CPI will continue. The combined formula assumes cost and schedule efficiency both carry forward. Each of these predicts the future from a number computed on the past.
A bottom-up EAC drops that assumption. You ask the people who will do the remaining work to estimate it again, item by item, using what they know today. The sum of those estimates is a new Estimate to Complete (ETC). You then add the money already spent:
EAC = AC + bottom-up ETCThe formula is the same one you use everywhere else: EAC = AC + ETC. What differs is where ETC comes from. In the other methods ETC is derived from EAC (ETC = EAC − AC). Here you build ETC directly, and EAC follows from it.
Some sources call this method "EAC with a new estimate to complete" or "bottom-up ETC". All of these names describe the same calculation.
Why you would use it
Formula methods fail when the future differs from the past in ways a ratio cannot capture. Common cases:
- The project was in a design phase with low labor rates, and the next phase is construction with high ones.
- A problem was found and fixed, so the old CPI no longer predicts anything.
- Scope changed, so the remaining work is not the work originally budgeted.
- A vendor contract fixed the price of part of the remaining work, so part of it cannot overrun.
- A risk that drove the earlier overrun has been retired, or a new one has appeared.
In each case the remaining work has its own cost profile, and only an estimate of that work can reflect it.
The cost of the method is effort. You must break the remaining scope into items, find owners, collect estimates, and review them. For that reason it is usually done at set intervals, such as at phase gates or when a variance threshold is crossed, instead of at every status date.
The procedure
- Identify the remaining scope. Start from the work breakdown structure (WBS). List every work package that is not finished. For a package that is partly done, estimate only what is left in it.
- Estimate each remaining item. Ask the person who will do the work for the effort and cost still needed, in the same cost terms as the baseline (labor, materials, contracts).
- Check for gaps and overlaps. Compare your list to the budget for the remaining work, which is BAC − EV. Every budgeted item that is not done should appear once. Items in the WBS that nobody listed are the most common source of an optimistic forecast.
- Sum to get ETC. Add the estimates, including any reserve you have decided to hold for the remaining work.
- Add actual cost. EAC = AC + ETC.
- Derive the checks. Compute VAC = BAC − EAC and the TCPI values, as in the earlier chapters.
Worked example
Use the same project as in the earlier chapters: BAC = 100,000, PV = 50,000, EV = 40,000, AC = 48,000. The remaining budgeted work is BAC − EV = 60,000. It sits in five work packages. Each owner has re-estimated what is left.
| Work package | Remaining budget | New estimate to complete | Difference |
|---|---|---|---|
| Database migration | 15,000 | 18,000 | +3,000 |
| API integration | 20,000 | 26,000 | +6,000 |
| User interface | 15,000 | 14,000 | −1,000 |
| Testing | 7,000 | 9,000 | +2,000 |
| Release and project management | 3,000 | 3,000 | 0 |
| **Total** | **60,000** | **70,000** | **+10,000** |
The remaining budgets add up to 60,000, which matches BAC − EV. That match is the gap check from step 3. If it had not matched, you would first find out which budgeted work is missing from the list.
The new estimates add up to 70,000, so ETC = 70,000 and EAC = 48,000 + 70,000 = 118,000. The code below runs the whole calculation.
packages = [
# (name, remaining budget, new estimate to complete)
("Database migration", 15000, 18000),
("API integration", 20000, 26000),
("User interface", 15000, 14000),
("Testing", 7000, 9000),
("Release and project management", 3000, 3000),
]
bac, ev, ac = 100000, 40000, 48000
remaining_budget = sum(budget for _, budget, _ in packages)
assert remaining_budget == bac - ev, "remaining work does not match BAC - EV"
etc = sum(estimate for _, _, estimate in packages)
eac = ac + etc
vac = bac - eac
tcpi_bac = (bac - ev) / (bac - ac)
tcpi_eac = (bac - ev) / (eac - ac)
for name, budget, estimate in packages:
print(f"{name}: {estimate - budget:+d}")
print(etc, eac, vac)
print(round(tcpi_bac, 4), round(tcpi_eac, 4))
# 70000 118000 -18000
# 1.1538 0.8571Reading the results:
- ETC = 70,000. The team expects to spend 70,000 more, against 60,000 of budget left for the work.
- EAC = 118,000. The project is forecast to finish 18,000 over budget, so VAC = −18,000.
- TCPI against BAC = 1.1538. To finish on the original budget, the remaining work would need to earn 1.15 of value for each unit spent. The project has been earning 0.83 so far, so this is not plausible without a change in approach.
- TCPI against EAC = 0.8571. The new forecast assumes the remaining work will run at about 0.86 efficiency. That is slightly better than the current CPI of 0.8333, which is a claim you must be able to support.
The second TCPI figure is how you test a bottom-up forecast. It is the CPI implied by the team's own estimates. If it is far better than the current CPI, the estimators are betting on a recovery, and you should ask what has changed.
Comparing with the formula methods
A bottom-up result should never be reported alone. Put it next to the other EACs for the same project and explain the gaps.
| Method | EAC | VAC |
|---|---|---|
| Atypical: AC + (BAC − EV) | 108,000 | −8,000 |
| Typical: BAC / CPI | 120,000 | −20,000 |
| Cost and schedule: AC + (BAC − EV) / (CPI × SPI) | 138,000 | −38,000 |
| Bottom-up: AC + new ETC | 118,000 | −18,000 |
The bottom-up figure lands close to the typical forecast and well above the atypical one. That is informative. It tells you the estimators do not believe the overrun was a one-off, even though they expect slightly better efficiency than the current CPI. It also lands far below the combined forecast, which is consistent with the schedule delay being a weaker predictor of final cost than the combined formula assumes.
The code below computes the implied efficiency and the differences, so the comparison is repeatable at each review.
bac, pv, ev, ac = 100000, 50000, 40000, 48000
cpi, spi = ev / ac, ev / pv
forecasts = {
"atypical": ac + (bac - ev),
"typical": bac / cpi,
"cost_schedule": ac + (bac - ev) / (cpi * spi),
"bottom_up": ac + 70000,
}
bottom_up = forecasts["bottom_up"]
for name, eac in forecasts.items():
print(f"{name}: EAC {eac:.0f}, bottom-up minus this {bottom_up - eac:+.0f}")
implied_cpi = (bac - ev) / (bottom_up - ac)
print(round(cpi, 4), round(implied_cpi, 4))
# atypical: EAC 108000, bottom-up minus this +10000
# typical: EAC 120000, bottom-up minus this -2000
# cost_schedule: EAC 138000, bottom-up minus this -20000
# bottom_up: EAC 118000, bottom-up minus this +0
# 0.8333 0.8571Edge cases and common errors
Partly finished packages. For a package that is half done, the estimate is the cost to finish it, not the original budget and not the original budget minus EV taken as a given. The owner may know that the last 20 percent will cost more than the first 80 percent did, and the estimate should say so.
Scope that is not in the baseline. If approved changes added work, the remaining scope is larger than BAC − EV. Update the baseline through change control first, or your gap check will flag a difference that is really a scope change. If the new work has not been approved, report it separately instead of folding it silently into ETC.
Missing items. Integration, rework, handover, training, and project management often have no work package of their own, and nobody estimates them. A list of estimates that sums neatly can still be incomplete. Walk the WBS, not the list the team volunteers.
Optimism and sandbagging. Owners who are told "the project is over budget" may shrink their estimates to look good, or pad them to protect themselves. Ask for the basis of each estimate (quantities, rates, quotes) and use a second reviewer for the largest items.
Spent money inside the estimate. ETC covers only future cost. If an owner's number includes work already paid for, the cost is counted twice, because AC already holds it. Ask each owner for "cost from today" and state the cut-off date.
Committed but unpaid cost. Purchase orders and signed contracts will be spent even if no invoice has arrived. Whether they sit in AC or ETC depends on your accounting rules. Pick one rule and apply it to every package, or you will drop some cost or count it twice.
Stale estimates. A bottom-up EAC is correct on the day it is built. If you keep reporting it for months without updating it, it becomes a fixed number in a project that is still moving. Set a refresh trigger, such as every phase gate or whenever CPI moves by more than a stated amount.
Ignoring risk. Estimates tend to describe the expected case for each item. The project as a whole may still need a reserve for risks that none of the packages own. Decide explicitly whether the reserve belongs in ETC or is held separately, and state which.
When to choose it
Use the bottom-up method when:
- the remaining work is different in kind from the work done so far,
- a known event has made past performance a poor guide,
- the project is far enough along that the remaining scope is small and well understood,
- a stakeholder or contract requires a detailed forecast, or
- the formula forecasts disagree widely and you need an independent view.
Prefer a formula method when the project is early, the remaining scope is not yet detailed, the status date comes often, or the effort of re-estimating is not worth the accuracy gain. In practice many teams run a formula EAC at each status date and a bottom-up EAC at phase gates, and treat a large gap between the two as a signal to investigate.
Exercise
A project has BAC = 200,000, EV = 120,000, and AC = 130,000. The remaining work has been re-estimated bottom-up at 95,000. Calculate the bottom-up EAC, the VAC, the remaining budget, and the TCPI against EAC. What does the TCPI tell you about the estimate, compared with the current CPI?
Show answer
EAC = AC + ETC = 130,000 + 95,000 = 225,000. VAC = BAC − EAC = 200,000 − 225,000 = −25,000, so the project is forecast to finish 25,000 over budget. The remaining budget (BAC − EV) is 200,000 − 120,000 = 80,000. TCPI against EAC = (BAC − EV) / (EAC − AC) = 80,000 / 95,000 = 0.8421. The current CPI is 120,000 / 130,000 = 0.9231. The estimate implies the remaining work will run at 0.84, which is worse than the project's current 0.92. The team is forecasting that performance will decline, so you should ask why, for example harder work ahead or items the original budget missed.
Exercise
Two owners each hand you a number for a package that is 60 percent complete, with a budget of 10,000. Owner A says "ETC is 4,000, the rest of the budget". Owner B says "ETC is 5,500, because the hardest part is left". Both owners have spent 6,000 so far. What should you check before accepting either number, and how does each choice change the package's forecast final cost?
Show answer
Check that each number is cost from today only, that it covers all remaining effort including rework and commitments, and that it has a stated basis. Owner A's number simply assumes the remaining budget is enough, which is not a fresh estimate. With A, the package's final cost is 6,000 + 4,000 = 10,000. With B it is 6,000 + 5,500 = 11,500, which is 1,500 over budget. Owner B's number is more useful if backed by a reason, such as the remaining tasks being more complex. Neither number should be accepted without that basis.