Sub topic 6
From EAC to ETC: how much is left to spend
This chapter assumes you can compute BAC, PV, EV, AC, CPI and SPI. It also assumes you have seen the EAC formulas from the previous chapters. Here the focus is the Estimate to Complete (ETC): what it measures, how to derive it two ways, and where people get it wrong.
What ETC answers
The Estimate at Completion (EAC) answers "what will the whole project cost?" The ETC answers a narrower question: "how much more money will we spend from today until the work is finished?"
The two are linked by one identity:
EAC = AC + ETC
ETC = EAC - ACAC is the actual cost to date. It is already spent and no forecast can change it. Every forecasting method therefore differs only in its ETC. The method decides how much the remaining work will cost, and the EAC is that figure added to the cost already incurred.
The running example
The chapter uses the same project as the rest of the tutorial:
| Measure | Value |
|---|---|
| BAC | 100,000 |
| PV | 50,000 |
| EV | 40,000 |
| AC | 48,000 |
| CPI (EV / AC) | 0.8333 |
| SPI (EV / PV) | 0.8 |
The project has earned 40,000 of value and spent 48,000 to do it. Under the plan, 60,000 of work remains, because BAC - EV = 100,000 - 40,000.
Deriving ETC by subtraction
The most general route is to pick an EAC method first and subtract AC. This always works, whatever method produced the EAC.
| Method | EAC | ETC = EAC - AC |
|---|---|---|
| Atypical variance | 108,000 | 60,000 |
| Typical (current CPI continues) | 120,000 | 72,000 |
| Cost and schedule combined | 138,000 | 90,000 |
Subtraction is the safest habit when you are checking someone else's forecast. You only need the published EAC and the actual cost from the ledger.
Deriving ETC directly
Each EAC formula has the shape AC + something. The "something" is the direct ETC, so you can write it without computing the EAC first.
| Situation | Direct ETC |
|---|---|
| Past variance was a one-off | BAC - EV |
| Current cost efficiency continues | (BAC - EV) / CPI |
| Cost and schedule both drive the outcome | (BAC - EV) / (CPI x SPI) |
| Bottom-up re-estimate | The new estimate for the remaining work |
Why the typical form works
The typical EAC is BAC / CPI. Because CPI = EV / AC, we can write AC = EV / CPI. Subtract:
ETC = EAC - AC
= BAC / CPI - EV / CPI
= (BAC - EV) / CPIThe formula has a plain reading. The remaining work is worth BAC - EV in budget terms, and each unit of budget costs 1 / CPI actual currency units at the current efficiency. In the example, 60,000 / 0.8333 = 72,000.
The same steps work for the combined formula. EAC = AC + (BAC - EV) / (CPI x SPI), so subtracting AC leaves (BAC - EV) / (CPI x SPI) directly. For the atypical case, EAC = AC + (BAC - EV), so ETC = BAC - EV with no efficiency adjustment at all.
Reading the three results
The direct forms show what each assumption means for the remaining work:
- Atypical (60,000): the remaining work costs exactly what was budgeted. The 8,000 overrun to date is treated as a sunk loss.
- Typical (72,000): the remaining work costs 20% more than budgeted, because CPI is 0.8333 and 1 / 0.8333 = 1.2.
- Combined (90,000): the remaining work costs 50% more than budgeted, because CPI x SPI = 0.6667 and 1 / 0.6667 = 1.5.
Computing it in code
The script below computes each ETC directly and checks that it equals the EAC-minus-AC result.
def etc_atypical(bac, ev):
return bac - ev
def etc_typical(bac, ev, ac):
cpi = ev / ac
return (bac - ev) / cpi
def etc_cost_schedule(bac, pv, ev, ac):
cpi, spi = ev / ac, ev / pv
return (bac - ev) / (cpi * spi)
def eac_from_etc(ac, etc):
return ac + etc
bac, pv, ev, ac = 100000, 50000, 40000, 48000
results = {
"atypical": etc_atypical(bac, ev),
"typical": etc_typical(bac, ev, ac),
"cost+schedule": etc_cost_schedule(bac, pv, ev, ac),
}
for name, etc in results.items():
eac = eac_from_etc(ac, etc)
# EAC - AC must give back the same ETC
assert abs((eac - ac) - etc) < 1e-6
print(f"{name:14} ETC={round(etc):>6} EAC={round(eac):>6}")Running it prints:
atypical ETC= 60000 EAC=108000
typical ETC= 72000 EAC=120000
cost+schedule ETC= 90000 EAC=138000The assertion is a cheap consistency test. If a spreadsheet's EAC and ETC columns fail this identity, one of them was computed from different inputs.
The bottom-up case
A bottom-up ETC comes from a fresh estimate of the remaining work, made task by task. The estimating team prices what is left, using current rates, known risks and what has been learned so far. The identity still holds, but the direction of derivation flips. You have the ETC first and compute the EAC from it:
ac = 48000
new_etc = 65000 # estimate from the team for remaining work
eac = ac + new_etc
print(eac) # 113000Here the EAC (113,000) is a result of the estimate. It is not an input to it. The CPI and SPI play no part in the number, though they remain useful as a sanity check. If the bottom-up ETC is far below what the typical formula gives (72,000), the team should be able to explain what will change.
ETC is not the same as remaining budget
The most common error is treating BAC - AC as the ETC. That figure is the budget that remains, not the cost to finish.
bac, ev, ac = 100000, 40000, 48000
remaining_budget = bac - ac # 52000
work_remaining = bac - ev # 60000 of budgeted work still to earn
print(remaining_budget, work_remaining)The project has 52,000 of budget left but 60,000 of work still to earn. Even if everything from here goes exactly to plan, the project needs 8,000 more than it has. A forecast of 52,000 would hide a shortfall that already exists. The gap between the two figures equals the cost variance: 60,000 - 52,000 = 8,000, which is |CV| = |40,000 - 48,000|.
Edge cases
Work complete
When EV = BAC, all planned work is earned. The typical and combined ETC formulas give 0, and the EAC equals AC. The project's final cost is its actual cost.
No earned value yet
If EV = 0 then CPI = 0 and the typical formula divides by zero. At project start there is no performance record, so there is nothing to extrapolate. Use the atypical form (ETC = BAC) or a bottom-up estimate until there is real progress to measure.
Almost no spend
If AC = 0 and EV > 0, CPI cannot be computed. This usually means costs are not being recorded, so check for unbooked invoices before trusting any forecast.
Very early or very small percent complete
CPI computed at 5% complete can swing widely, and the ETC inherits that swing. The typical ETC at 5% complete multiplies a large remaining amount by a noisy factor. Treat early typical forecasts as a range, and use one of the other methods for comparison.
EV above BAC
EV should never exceed BAC. If a worksheet reports it, the BAC is out of date after a change request, or progress is overstated. The ETC formulas would then return negative values, which is a signal to fix the inputs. Do not clamp the result to zero.
Negative ETC from subtraction
An ETC from EAC - AC is negative if the EAC is lower than what has already been spent. A negative ETC is impossible, since spent money cannot be returned. It means the EAC was computed from stale or mismatched figures, for example an EAC calculated last month compared with this month's AC.
Common errors
- Mixing periods. The EAC from last month's report minus this month's AC gives a meaningless ETC. Take both from the same status date.
- Applying CPI to the whole budget but subtracting only part of the cost. Using BAC / CPI - AC is correct. Using BAC / CPI - EV is not, because EV is value earned, not money spent.
- Adding AC twice. If the ETC already includes a contingency or accrual that is also in AC, the EAC double-counts it. Keep accruals in one place.
- Forgetting unbooked commitments. Purchase orders already placed but not yet invoiced are real future spend. Either include them in AC as accruals or make sure the ETC covers them.
- Quoting ETC without naming the method. An ETC of 72,000 means little unless the reader knows it assumes current CPI continues.
- Confusing ETC with time. The ETC is an amount of money. It says nothing about how long the remaining work takes. A time-phased version (how much is spent each month) needs a separate cash-flow plan.
How ETC feeds the next steps
The ETC is the bridge to the checks covered in the following chapters. Variance at Completion (BAC - EAC) compares the forecast with the budget. The To-Complete Performance Index (TCPI) compares the work remaining with the money remaining. Both depend on getting AC, EAC and ETC right.
Exercise
A project has BAC = 200,000, EV = 80,000, AC = 100,000 and PV = 90,000. Management believes the overrun to date was caused by a one-off supplier error and that the remaining work will cost what was budgeted. (a) Compute the ETC and EAC. (b) Compute the ETC and EAC if instead current cost efficiency will continue.
Show answer
(a) Atypical: ETC = BAC - EV = 200,000 - 80,000 = 120,000. EAC = AC + ETC = 100,000 + 120,000 = 220,000. (b) CPI = EV / AC = 80,000 / 100,000 = 0.8. Typical: ETC = (BAC - EV) / CPI = 120,000 / 0.8 = 150,000. EAC = 100,000 + 150,000 = 250,000, which also equals BAC / CPI = 200,000 / 0.8.
Exercise
A manager reports the ETC of a project as BAC - AC, where BAC = 150,000 and AC = 70,000. EV is 60,000 and the team expects the remaining work to cost what was budgeted. What is the correct ETC, and by how much did the manager's figure understate it?
Show answer
The correct atypical ETC is BAC - EV = 150,000 - 60,000 = 90,000. The manager reported 150,000 - 70,000 = 80,000. The figure is understated by 10,000, which equals the cost overrun to date (AC - EV = 70,000 - 60,000).
Exercise
The finance team published an EAC of 125,000 last month. This month AC is 61,000 and the EAC was recalculated as 128,000. A colleague computes ETC = 125,000 - 61,000. What is wrong with this, and what is the right ETC?
Show answer
The colleague mixed periods: the old EAC was paired with this month's AC. Both figures must come from the same status date. The right ETC is the current EAC minus the current AC: 128,000 - 61,000 = 67,000.