Sub topic 11
Choosing and justifying a method
This chapter assumes you can already compute CPI, SPI, BAC, PV, EV and AC, and that you know the three formula-based EAC methods and the bottom-up method from earlier chapters. The question here is which one to report and how to defend that choice. The formulas are quick to calculate. The judgment behind the choice is where forecasts succeed or fail.
Why the choice matters
One set of project data can produce very different forecasts. Take a project with BAC 100,000, PV 50,000, EV 40,000 and AC 48,000. CPI is 0.8333 and SPI is 0.8. The three formula methods then give:
| Method | Formula | EAC | ETC (EAC - AC) | VAC (BAC - EAC) |
|---|---|---|---|---|
| Atypical variance | AC + (BAC - EV) | 108,000 | 60,000 | -8,000 |
| Typical variance | BAC / CPI | 120,000 | 72,000 | -20,000 |
| Cost and schedule | AC + (BAC - EV) / (CPI x SPI) | 138,000 | 90,000 | -38,000 |
The spread between the lowest and highest forecast is 30,000, which is 30% of BAC. The arithmetic is not in dispute. What differs is the assumption each formula makes about the remaining work. Choosing a method means choosing an assumption, and you must be able to state it.
What each method assumes
Each formula encodes a claim about the future. Your job is to decide which claim the evidence supports.
Atypical: AC + (BAC - EV)
This method assumes the remaining work will cost exactly what the baseline said it would. The overrun so far is treated as sunk and unrepeated. The remaining budget is BAC - EV, the baseline value of unfinished work, and you add it to what you have already spent.
Use it when you can name a specific, finished cause for the overrun. Examples are a one-time equipment failure, a vendor price correction that has already been absorbed, or a defect that was found and fixed. The key test is that the cause is over and will not recur.
Typical: BAC / CPI
This method assumes every remaining unit of work will cost as much, relative to plan, as the work done so far. It is equivalent to AC + (BAC - EV) / CPI. A CPI of 0.8333 means each planned dollar of work costs about 1.20 dollars.
Use it when the cause of the overrun is systemic: a consistently optimistic estimate, a productivity problem, a rate that applies to all remaining work. It is also the default when you have no evidence that performance will change.
Cost and schedule: AC + (BAC - EV) / (CPI x SPI)
This method assumes that both cost efficiency and schedule efficiency affect the final cost. Falling behind can raise cost through overtime, extended overhead, crashing or rework to catch up. Dividing by CPI x SPI inflates the remaining work for both effects.
Use it when schedule pressure has a real cost mechanism, for example a fixed deadline with penalties, or level-of-effort resources that keep billing while work slips. Be careful. When SPI is low only because work started late, and the team is not paying extra to recover, this formula overstates the forecast.
Bottom-up: AC + new estimate to complete
This method discards the index-based assumption. People who know the work re-estimate what remains, task by task, and you add that estimate to AC. It is the most accurate method when the baseline no longer describes the work, and the most expensive to produce.
Use it when scope has changed, when the original estimate is clearly obsolete, or when CPI is so far from 1 that extrapolating it is not credible. It also serves as a check on the formula methods.
A decision flow
The questions below turn the choice into a repeatable procedure rather than a preference.
The flow asks about the remaining work, not the past. Past variance is only evidence. What you forecast is the cost of work not yet done.
Compute all of them, then compare
A sound practice is to calculate every method and report a range, with one method marked as your recommendation. The code below does this and adds TCPI as a reasonableness check.
def forecasts(bac, pv, ev, ac):
cpi, spi = ev / ac, ev / pv
eac = {
"atypical": ac + (bac - ev),
"typical": bac / cpi,
"cost_schedule": ac + (bac - ev) / (cpi * spi),
}
rows = {}
for name, value in eac.items():
rows[name] = {
"EAC": round(value),
"ETC": round(value - ac),
"VAC": round(bac - value),
"TCPI_EAC": round((bac - ev) / (value - ac), 4),
}
return rows
bac, pv, ev, ac = 100000, 50000, 40000, 48000
for name, row in forecasts(bac, pv, ev, ac).items():
print(name, row)
print("TCPI to hit BAC:", round((bac - ev) / (bac - ac), 4))Running it prints one line per method and then the BAC-based TCPI of 1.1538. The TCPI against each method's own EAC shows the efficiency the remaining work must achieve to meet that forecast. For the typical method it is 0.8333, equal to the current CPI, which is exactly what that method assumes. For the atypical method it is 1.0, since the remaining work is assumed to go to plan. For the cost and schedule method it is about 0.6667, a worse efficiency than any seen so far.
That last number is useful as a sanity check. If a method requires the team to be much less efficient than they have ever been, the assumption behind it needs evidence.
Testing the assumption with TCPI
TCPI against BAC is (BAC - EV) / (BAC - AC). Here it is 1.1538. The team has delivered 0.8333 so far and would need 1.1538 on all remaining work to finish within budget. Compare this with history.
- If TCPI to BAC is close to the current CPI, finishing on budget is plausible.
- If it is far above anything the team has achieved, an atypical forecast near BAC is hard to defend.
- If it is far above 1.10 and the evidence for a one-off is weak, treat the on-budget claim with suspicion.
This test makes the atypical method's claim concrete. It says that CPI will jump from 0.83 to 1.0 on the remaining work. A forecast that implies a sudden improvement needs a reason.
Evidence that supports each choice
When you present a choice, attach evidence to it. The table lists what a reviewer should expect to see.
| Method | Evidence that supports it | Evidence that argues against it |
|---|---|---|
| Atypical | Named, closed cause; corrective action completed; CPI trend recovering | CPI flat or falling across several periods |
| Typical | Stable CPI over several periods; systemic cause; no change planned | Cause identified as temporary; work type changes in later phases |
| Cost and schedule | Deadline penalties, overtime or crashing already visible in AC; resources tied to duration | Slippage from late start only; no extra cost to recover |
| Bottom-up | Scope change; obsolete baseline; large inconsistency between CPI and team's own view | Little time or access to estimators; small remaining work |
Stability of CPI
CPI drifts early in a project and tends to stabilize later. A common rule of thumb says that once a project is roughly 20% complete, the cumulative CPI rarely improves by much. So the typical method is often the right default once a project is past its early stage and no one-off cause exists. Early in a project, a single month of poor CPI can mislead. Look at the trend across periods, not one reading.
Cumulative CPI and period CPI also differ. Cumulative CPI smooths noise but responds slowly. Period CPI reacts faster but swings. If the last three periods average 0.78 and the cumulative figure is 0.83, a forecast based on the cumulative figure may be optimistic. State which one you used.
Different methods for different parts
A single project does not need a single method. If one work package had a one-off failure and the rest is running at CPI 0.9, you can forecast each part separately: atypical for the package with the closed cause, typical for the rest, and sum the results. Apply the index at the level where the cause operates. This is also how a partial bottom-up works: re-estimate only the packages whose baseline is invalid and use an index for the others.
Document the split clearly, because blended forecasts are harder to audit.
Justifying the choice to stakeholders
A defensible justification has four parts.
- State the method and the one-sentence assumption behind it, such as "We assume the current cost efficiency continues for all remaining work."
- Give the evidence, such as the CPI by period and the named causes.
- Show the range from the other methods, so no one suspects hidden alternatives.
- State what would change your mind, such as a corrective action completing or a change in CPI over two periods.
A short example: "We forecast 120,000 using BAC / CPI. CPI has been between 0.82 and 0.85 for four periods, and the cause is a consistently low productivity rate that applies to all remaining work. The one-off view gives 108,000 but would need CPI to jump to 1.0. The cost and schedule view gives 138,000 but we see no recovery spending. We will revise if CPI exceeds 0.9 for two consecutive periods."
That statement can be challenged, and that is a strength. A forecast that cannot be challenged cannot be checked.
Common errors in choosing
- Using the atypical formula by habit because it gives a smaller overrun.
- Using the cost and schedule formula whenever SPI is below 1, without a cost mechanism for slippage.
- Mixing periods, such as a cumulative EV with a period AC.
- Applying CPI when AC is near zero or EV is zero, which produces a meaningless or undefined result.
- Reporting a single number with no range and no assumption.
- Forgetting that a change in scope needs a revised BAC. Without it, every method measures the wrong baseline.
- Changing methods between reports without saying so, which makes trends meaningless.
Edge cases
- CPI above 1. The typical method gives an EAC below BAC. Be cautious. Underspending can come from delayed invoices or unrecorded accruals, so check that AC is complete before claiming a saving.
- EV equals BAC. The work is complete and all methods give EAC = AC. No assumption is needed.
- SPI very low with CPI near 1. The cost and schedule formula inflates EAC sharply. Confirm that cost really rises with delay before using it.
- Very small EV. Early in the project, CPI is based on little data. Any index-based method is fragile, and a bottom-up estimate or a range is more honest.
- AC greater than BAC. TCPI to BAC is negative or undefined. BAC can no longer be met, so only a forecast-based TCPI is meaningful.
Exercise
A project has BAC 200,000, PV 120,000, EV 90,000 and AC 100,000. A supplier price error added 10,000 to AC last month. It has been corrected and affects nothing else. Which EAC method fits, what is the EAC, and what is the TCPI against that EAC?
Show answer
The cause is a closed one-off, so use the atypical method. EAC = AC + (BAC - EV) = 100,000 + (200,000 - 90,000) = 210,000. ETC = 110,000 and VAC = -10,000. TCPI against EAC = (BAC - EV) / (EAC - AC) = 110,000 / 110,000 = 1.0, which matches the assumption that the remaining work goes exactly to plan. For comparison, CPI is 0.9, so the typical method would give 200,000 / 0.9 = about 222,222. You would justify the lower figure by pointing to the corrected price error.
Exercise
For the same project, a reviewer asks why you did not use the cost and schedule method, since SPI is 0.75. What is that method's EAC, and what evidence would you need before using it?
Show answer
CPI = 0.9 and SPI = 0.75, so CPI x SPI = 0.675. EAC = 100,000 + 110,000 / 0.675 = about 262,963. You would need evidence that the schedule delay itself adds cost, such as overtime, crashing, penalties or standing resources that keep billing while work slips. Because the overrun in AC came from a closed price error and no recovery spending is visible, the evidence is missing, so the method would overstate the forecast.
Exercise
A team reports atypical EAC = 108,000 for a project with BAC 100,000, EV 40,000 and AC 48,000. Using TCPI, explain what the forecast requires and why a reviewer might doubt it.
Show answer
TCPI against EAC = (100,000 - 40,000) / (108,000 - 48,000) = 1.0, so the remaining work must run at exactly plan efficiency. The project's CPI so far is 0.8333. Unless the team can name a closed one-off cause and show corrective action, a reviewer should doubt a sudden jump from 0.83 to 1.0.