Why SPI Drifts Toward 1.0 as a Project Ends
Assume you understand the performance measurement baseline, planned value (PV), earned value (EV), and actual time elapsed. You should also be comfortable reading cumulative values from a project schedule.
The problem with cumulative SPI
The Schedule Performance Index (SPI) is:
SPI = EV / PVBoth EV and PV are cumulative measures. PV is the budgeted value of work planned by a status date. EV is the budgeted value of work actually completed by that date.
An SPI below 1.0 usually means the project has earned less value than planned. However, SPI does not measure calendar time directly. It compares the value of completed work with the value that was planned.
Near project completion, the planned value reaches the total approved budget, called the budget at completion (BAC). When the project eventually completes, earned value also reaches the BAC:
EV = BAC
PV = BAC
SPI = BAC / BAC = 1.0This happens even if the project finished late. A project that should have finished in period 6 but finishes in period 8 will report an SPI of 1.0 at completion. The index has lost its ability to show the delay.
How SPI loses schedule sensitivity
Imagine a project with a BAC of $100,000. At the end of period 3, the plan expected $40,000 of work, but the team had earned only $35,000.
SPI = 35,000 / 40,000 = 0.875The project is behind the value-based plan. If the team finishes the remaining work late, EV gradually rises to $100,000. At the final status date, PV also equals $100,000. Traditional SPI therefore moves toward 1.0 as completion approaches.
| Project condition | EV | PV | SPI |
|---|---|---|---|
| Behind during execution | $35,000 | $40,000 | 0.875 |
| Completed late | $100,000 | $100,000 | 1.000 |
This does not mean the delay disappeared. It means the cumulative value comparison can no longer express when the work was completed.
Earned schedule and time-based SPI
Earned schedule (ES) translates EV into the amount of planned time needed to earn that value. It asks:
- At what point in the baseline schedule would the current EV have been achieved?
- How does that planned time compare with the actual elapsed time?
The time-based Schedule Performance Index is:
SPI(t) = ES / ATHere, AT means actual time elapsed. If ES is 6 periods and AT is 8 periods, then:
SPI(t) = 6 / 8 = 0.75Unlike traditional SPI, SPI(t) can remain below 1.0 after the project finishes late. It compares the time represented by the earned work with the actual calendar duration.
To estimate ES, locate the interval in the cumulative PV curve where the current EV falls. Interpolate within that interval when necessary. If EV is $35,000 and the baseline reached $25,000 at period 2 and $40,000 at period 3, ES is about 2.67 periods. At actual time 3:
SPI(t) = 2.67 / 3 = 0.89Reporting the limitation honestly
Report traditional SPI during execution, but pair it with milestone dates, forecast completion dates, and, when late completion matters, SPI(t). Explain whether a change in SPI reflects real schedule recovery or simply the mathematical effect of approaching BAC.
Exercise
A project completes in period 8 instead of the baseline period 6. At completion, EV and PV both equal $200,000. What are the traditional SPI and the time-based SPI(t), assuming ES equals 6 periods?
Show answer
Traditional SPI is 1.00 because EV/PV = 200,000/200,000. SPI(t) is 0.75 because ES/AT = 6/8, showing that the project took 25% longer than planned.