Earned Schedule: A Time-Based Alternative to SPI
This chapter assumes you can read a project schedule and understand planned value (PV), earned value (EV), and the status date. You should also be comfortable with ratios and simple interpolation.
Why conventional SPI becomes misleading
The Schedule Performance Index (SPI) is:
SPI = EV / PV
It compares the value earned with the value planned by the status date. An SPI below 1.0 suggests that the project has earned less work than planned.
SPI uses money or budget points as a proxy for time. That works during much of a project, but it has a late-project weakness. When all planned work is eventually completed, EV reaches the budget at completion (BAC). PV also reaches BAC. Therefore:
SPI = BAC / BAC = 1.0
A project can finish late while its final SPI appears to be exactly 1.0. Earned schedule (ES) addresses this problem by expressing earned progress in time units.
How earned schedule works
Earned schedule is the time at which the current EV should have been earned according to the performance measurement baseline. In other words, find the point on the planned-value curve where cumulative PV equals the current EV.
For example, suppose the cumulative plan is:
| Planned period | Cumulative PV |
|---|---|
| 1 | 10,000 |
| 2 | 25,000 |
| 3 | 40,000 |
| 4 | 60,000 |
| 5 | 80,000 |
| 6 | 100,000 |
At the end of period 3, the project has EV of 35,000. That value lies between the planned values for periods 2 and 3. Linear interpolation gives:
ES = 2 + (35,000 - 25,000) / (40,000 - 25,000)
ES = 2.667 periods
The project has earned about 2.667 periods of planned work, even though 3 periods have passed.
Calculating time-based SPI
The time-based Schedule Performance Index is:
SPI(t) = ES / AT
Here, AT means actual time elapsed. With ES of 2.667 periods and AT of 3 periods:
SPI(t) = 2.667 / 3 = 0.889
This says the project has earned 88.9% of the planned time progress that should have been achieved by the status date.
| Measure | Formula | Result |
|---|---|---|
| Conventional SPI | EV / PV | 35,000 / 40,000 = 0.875 |
| Earned schedule | Interpolated planned time for EV | 2.667 periods |
| SPI(t) | ES / actual time | 2.667 / 3 = 0.889 |
An SPI(t) below 1.0 indicates that progress is behind the time plan. A value of 1.0 indicates progress is on schedule. A value above 1.0 indicates progress is ahead.
Common errors and reporting practice
Do not treat ES as a revised completion date. ES describes how much planned time-equivalent progress has been earned at the current status date. Forecasting the finish date requires a separate forecasting method.
Do not compare SPI(t) directly with cost efficiency. SPI(t) is time-based, while CPI is:
CPI = EV / AC
Report both indices with their trends, the status date, and the reason for any change. A single index can hide a temporary event, a baseline change, or a measurement problem. Use thresholds agreed with stakeholders, such as investigating SPI(t) below 0.90 for two reporting periods.
Exercise
A project has an actual time of 4 periods. Its EV lies halfway between the planned cumulative PV at periods 3 and 4. What are ES and SPI(t)?
Show answer
ES is 3.5 periods. SPI(t) is 3.5 / 4 = 0.875, so the project is behind its time plan.