Sub topic 3
Earned value: what has actually been accomplished
Assume you know basic project management terms, can read a schedule and budget, and can calculate simple ratios. This chapter focuses on earned value (EV), the budgeted value of the work that is complete at a status date.
What earned value measures
Earned value answers this question:
> How much of the approved budget corresponds to the work actually completed?
EV is measured in the same money units as the project budget, even when no money has been spent yet. It is based on the performance measurement baseline, which is the time-phased plan for the approved scope, schedule, and budget.
For example, a work package has a total budget of $20,000. If the team has completed 40% of its scope, its EV is:
EV = budget at completion × completed proportion
EV = $20,000 × 0.40
EV = $8,000The $8,000 does not mean the team spent $8,000. It means the completed work was budgeted at $8,000.
Decide what “complete” means
The project team must define completion rules before reporting EV. Otherwise, people may claim progress using inconsistent or optimistic estimates.
Common methods include:
| Method | How EV is assigned | Suitable use |
|---|---|---|
| 0/100 | Earns no value until the work package is complete, then earns all value | Short tasks with clear completion |
| 50/50 | Earns half at start and half at completion | Short tasks where tracking partial progress is difficult |
| Weighted milestones | Earns set amounts when defined milestones are accepted | Complex deliverables with verifiable stages |
| Percent complete | Earns the budget multiplied by assessed completion | Longer work with measurable continuous progress |
The 0/100 method reduces arguments about partial completion, but it can make progress appear unchanged for a long time. The percent-complete method gives smoother reporting, but it requires objective evidence.
A work package is a manageable section of project scope. Its budget is called the budget at completion (BAC) for that work package. EV should be based on completed scope, not effort or hours alone. A team can work many hours and still produce little accepted output.
Worked example
A software work package has a budget of $30,000. Its completion rules assign value to three accepted deliverables:
- Design approved: 25%
- Code complete: 50%
- Tests accepted: 25%
At the status date, the design and code are accepted, but testing has not finished. The earned value is:
EV = $30,000 × (0.25 + 0.50)
EV = $22,500If the team spent $24,000, the actual cost (AC) is $24,000. If the baseline said that $27,000 worth of this work should be complete by now, the planned value (PV) is $27,000.
These three measurements support performance analysis:
- EV compared with PV shows whether the project has completed as much work as planned.
- EV compared with AC shows whether the completed work cost more or less than its budgeted value.
- EV does not replace inspection, acceptance, or schedule analysis. It summarizes progress using the approved measurement rules.
Check your measurement rule
For each work package, ask:
- What output proves completion?
- Who accepts that output?
- Which method assigns EV?
- Can the result be reproduced from the project records?
These decisions make later SPI and CPI calculations meaningful. If EV is inflated, both indices can look better than the project’s real performance.
Exercise
A work package has a $12,000 budget. It uses the 50/50 method, and the work started but is not complete at the status date. What is its EV?
Show answer
The EV is $6,000, or half of the work package budget.