Sub topic 10
Forecasting Final Cost with EAC and ETC
Assume you can read a project schedule and budget, understand the performance measurement baseline, and calculate planned value (PV), earned value (EV), and actual cost (AC). This chapter uses those measurements to forecast the project’s final cost.
Estimate at completion
Estimate at completion (EAC) is the expected total cost when all project work is finished. It combines the cost already recorded with a forecast for the remaining work.
The simplest forecast assumes that the project’s current cost efficiency will continue:
EAC = BAC / CPIHere, budget at completion (BAC) is the approved total budget, and the Cost Performance Index (CPI) is:
CPI = EV / ACIf CPI is below 1.0, the project is producing less value for each unit of cost than planned. The EAC will therefore be greater than BAC.
Estimate to complete (ETC) is the expected cost of the remaining work:
ETC = EAC - ACFor example, suppose:
| Measurement | Value |
|---|---|
| BAC | 100,000 |
| EV | 35,000 |
| AC | 42,000 |
| CPI | 0.833 |
The forecast is:
EAC = 100,000 / 0.833 = approximately 120,000
ETC = 120,000 - 42,000 = 78,000The project is forecast to finish at about 120,000, which is 20,000 above its approved budget.
Choosing the forecasting formula
The CPI-based formula is suitable when current cost performance represents the conditions that will affect the remaining work. It is a useful management forecast, but it is not a prediction with certainty.
Other situations call for different formulas:
- If the original cost variance was unusual and will not recur, use
EAC = AC + (BAC - EV). - If both cost and schedule performance will affect remaining costs, use
EAC = AC + (BAC - EV) / (CPI × SPI). - If a new bottom-up estimate exists, use
EAC = AC + remaining work estimate.
The bottom-up method can be more accurate after a major scope change, redesign, or recovery plan. It requires the team to estimate each remaining work package again.
Computing EAC and ETC in Python
This function uses the CPI-continuation forecast:
def forecast_cost(bac, ev, ac):
"""Return CPI, EAC, and ETC using current cost efficiency."""
if bac <= 0 or ev <= 0 or ac <= 0:
raise ValueError("BAC, EV, and AC must be positive")
cpi = ev / ac
eac = bac / cpi
etc = eac - ac
return cpi, eac, etc
cpi, eac, etc = forecast_cost(100_000, 35_000, 42_000)
print(f"CPI: {cpi:.3f}")
print(f"EAC: {eac:,.0f}")
print(f"ETC: {etc:,.0f}")TCPI and the required recovery effort
The To-Complete Performance Index (TCPI) measures the efficiency required for the remaining work.
To finish within BAC:
TCPI = (BAC - EV) / (BAC - AC)With the example values:
TCPI = (100,000 - 35,000) / (100,000 - 42,000)
= 1.121The project must achieve a CPI of about 1.121 for the remaining work to meet the original budget. Compare this requirement with the current CPI of 0.833. The difference signals that the original budget may no longer be realistic without corrective action.
Exercise
A project has BAC 200,000, EV 90,000, and AC 100,000. Using EAC = BAC / CPI, calculate CPI, EAC, and ETC.
Show answer
CPI = 0.900, EAC = approximately 222,222, and ETC = approximately 122,222.