The baseline that everything is measured against
Earned value analysis assumes that a project has a reliable reference point. This reference point is the performance measurement baseline (PMB). The PMB is the approved plan for the project's scope, schedule, and budget. It lets you compare the work completed and money spent with what the project should have achieved by a given date.
Prerequisites
You should know basic project management terms, including scope, schedule, budget, work breakdown structure (WBS), and work package. You should also be able to read a project schedule and perform simple arithmetic with ratios and percentages.
What the performance measurement baseline contains
The PMB combines three approved plans:
- The scope baseline defines the work the project must deliver.
- The schedule baseline says when that work should occur.
- The cost baseline assigns budget to the scheduled work.
The project team organizes scope through a WBS. A WBS divides the project into smaller deliverables and work packages. A work package is a manageable unit of work that can be scheduled, assigned, measured, and given a budget.
For example, a software project might have a work package called “Create user authentication.” That work package could have a budget of $20,000 and a planned duration from January 5 through January 23. Its budget is spread across the dates when the team expects to perform the work.
The time-phased budget is called the performance measurement baseline when it is used to measure progress. The total approved budget across the baseline is the budget at completion (BAC).
| Baseline element | Main question | Example |
|---|---|---|
| Scope | What work is included? | User authentication |
| Schedule | When should the work happen? | January 5–23 |
| Cost | How much is budgeted? | $20,000 |
How the baseline supports measurement
At each reporting date, the project team compares current results with the baseline. The baseline supplies the planned amount of work and budget for that date. This planned amount is called planned value (PV).
The project team also records:
- Earned value (EV): the budgeted value of work actually completed.
- Actual cost (AC): the money actually spent on the completed work.
These three measurements must use the same scope, reporting date, and accounting rules. If the baseline says that a work package is 50% complete at the end of the month, the team must use a consistent method to determine whether the work has earned that value.
The comparison produces performance indicators. For example, EV compared with PV shows whether progress is ahead of or behind the plan. EV compared with AC shows whether the work is costing more or less than its budgeted value. Later chapters use these comparisons to calculate SPI and CPI.
Controlling changes to the baseline
The PMB is not a prediction that must remain unchanged. It is an approved commitment. If the customer adds scope or the sponsor changes a deadline, the project team should evaluate and approve the change through change control.
After approval, the team updates the relevant scope, schedule, and budget records. It then establishes a revised baseline or documented baseline change. Do not change the baseline merely to hide poor performance. That would erase the comparison that tells stakeholders what happened.
Keep approved changes separate from the original plan when possible. This preserves the project's history and helps stakeholders distinguish performance problems from authorized scope changes.
Exercise
A project has a BAC of $100,000. An approved scope change adds $10,000 before the next reporting period. What should the project manager do before using the new target for performance reporting?
Show answer
Process and approve the change, update the affected scope, schedule, and budget information, document the decision, and establish the revised baseline according to the project's change-control process.