Sub topic 6
Schedule and Cost Variance as Absolute Differences
Assume you can read a project schedule and budget and understand scope, work breakdown structure, and basic arithmetic with ratios and percentages. This chapter uses three earned value measurements at one status date:
- Planned value (PV) is the budgeted value of work scheduled to be complete by the status date.
- Earned value (EV) is the budgeted value of work actually completed by the status date.
- Actual cost (AC) is the money actually spent for that completed work.
An absolute variance is a difference between two values. It uses the same unit as the measurements, usually dollars, euros, or labor-hours. It tells you the size and direction of a problem, but not its percentage or efficiency.
Schedule variance
Schedule variance (SV) compares the value of completed work with the value of work that should have been completed:
SV = EV − PV
The usual interpretation is:
| Schedule variance | Meaning |
|---|---|
| SV > 0 | More budgeted work is complete than planned |
| SV = 0 | Completed work matches the plan |
| SV < 0 | Less budgeted work is complete than planned |
For example, suppose a project has:
- PV = $40,000
- EV = $35,000
- AC = $42,000
The schedule variance is:
SV = $35,000 − $40,000 = −$5,000
The negative sign means the project has completed $5,000 less budgeted work than planned at this status date.
SV is expressed in money because EV and PV are budget values. It is not a statement that the project is exactly a certain number of days late. Two projects can have the same SV but different calendar delays because their activities have different durations and budgets.
Cost variance
Cost variance (CV) compares the value of completed work with what that work actually cost:
CV = EV − AC
The usual interpretation is:
| Cost variance | Meaning |
|---|---|
| CV > 0 | The completed work cost less than its budgeted value |
| CV = 0 | Cost matches the budgeted value of completed work |
| CV < 0 | The completed work cost more than its budgeted value |
Using the same measurements:
CV = $35,000 − $42,000 = −$7,000
The negative result means the project spent $7,000 more than the budgeted value of the work completed.
A positive CV does not automatically mean the project is healthy. The team may have completed less work than planned, or it may have used an unreliable method for measuring completion. Check the scope and earned value rules before treating a favorable variance as a success.
Read the two variances together
SV and CV describe different comparisons. SV compares progress with the plan. CV compares progress value with spending.
For the example, both values are negative:
- SV = −$5,000: progress is behind the time-phased plan.
- CV = −$7,000: completed work has cost more than its budgeted value.
This combination needs investigation. Possible causes include underestimated work, expensive resources, rework, late activities, or progress reported more optimistically than the evidence supports.
Use variance thresholds and trends
A single variance is a signal, not a diagnosis. Compare it with an agreed threshold, identify the cause, and examine earlier status dates. A small unfavorable variance that is shrinking may need less action than a small variance that has worsened for three reporting periods.
Exercise
A work package has PV = $18,000, EV = $15,000, and AC = $12,000. What are SV and CV, and what do they mean?
Show answer
SV = $15,000 − $18,000 = −$3,000, so less work is complete than planned. CV = $15,000 − $12,000 = $3,000, so the completed work cost less than its budgeted value.