Sub topic 9
Reading SPI and CPI Together
Prerequisites and the two indices
This chapter assumes you can read a project schedule, understand a work breakdown structure, and calculate simple ratios. You should also know the three earned value measurements:
- Planned value (PV) is the budgeted value of work scheduled by the status date.
- Earned value (EV) is the budgeted value of work actually completed.
- Actual cost (AC) is what the completed work actually cost.
The Schedule Performance Index (SPI) compares accomplished work with scheduled work:
\[ SPI = \frac{EV}{PV} \]
The Cost Performance Index (CPI) compares accomplished work with actual spending:
\[ CPI = \frac{EV}{AC} \]
An index of 1.0 means performance matches the baseline. An SPI above 1.0 means the project has completed more planned work than expected by the status date. A CPI above 1.0 means the project produced more budgeted value than it spent.
A worked example
Suppose a project has these measurements at the end of period three:
| Measurement | Amount |
|---|---|
| Planned value (PV) | $40,000 |
| Earned value (EV) | $35,000 |
| Actual cost (AC) | $42,000 |
Calculate the indices:
- SPI = $35,000 / $40,000 = 0.875
- CPI = $35,000 / $42,000 = 0.833
The SPI of 0.875 means the team has earned 87.5% of the value that the plan expected by now. The project is behind schedule against its performance measurement baseline.
The CPI of 0.833 means the team earns about $0.83 of budgeted value for every $1.00 spent. The project is over budget for the work completed.
These indices describe different dimensions. Do not combine them into one average. A project can be ahead of schedule but over budget, or behind schedule but under budget.
Interpret both indices together
Use the pair of values to start a diagnosis:
| SPI | CPI | Initial interpretation |
|---|---|---|
| Above 1.0 | Above 1.0 | Ahead of schedule and under budget |
| Above 1.0 | Below 1.0 | Ahead of schedule but spending inefficiently |
| Below 1.0 | Above 1.0 | Behind schedule but spending efficiently |
| Below 1.0 | Below 1.0 | Behind schedule and over budget |
The pair does not explain the cause. For example, an SPI below 1.0 and CPI below 1.0 could result from rework, late materials, poor estimates, or a change that has not entered the baseline. Investigate the work packages and assumptions before choosing corrective action.
Read trends, not isolated values
A single reporting period can contain noise. A late invoice can temporarily reduce CPI, while a newly accepted milestone can raise SPI. Compare current values with earlier periods and look for direction:
- A rising SPI suggests schedule performance is improving.
- A falling SPI suggests the delay is growing.
- A rising CPI suggests better cost efficiency.
- A falling CPI suggests worsening cost efficiency.
Set reporting thresholds with stakeholders. For example, an organization might require an explanation when either index falls below 0.90. The threshold is a management rule, not a universal definition of failure.
Exercise
A project has PV = $80,000, EV = $72,000, and AC = $60,000. What do SPI and CPI indicate?
Show answer
SPI = 0.90, so the project is behind the planned rate of work. CPI = 1.20, so it is earning $1.20 of budgeted value for each dollar spent. It is behind schedule but under budget.