Trends, Thresholds and Honest Reporting
Assume you can read a work breakdown structure, schedule, and budget, and can calculate planned value (PV), earned value (EV), actual cost (AC), SPI, and CPI. This chapter focuses on turning those measures into useful reports.
Report trends, not isolated numbers
A single index describes one status date. It does not explain whether performance is improving, worsening, or stable. Report at least three views:
- Current-period SPI and CPI show what happened recently.
- Cumulative SPI and CPI show the overall position.
- The direction of the values shows whether corrective action is working.
For example, a cumulative CPI of 0.88 with a current-period CPI of 1.05 may mean that recent work is efficient but has not yet recovered the earlier overrun. The project is still forecast to exceed its budget unless the improvement continues.
| Measure | Meaning | Useful reporting question |
|---|---|---|
| Current-period CPI | Cost efficiency this period | Did recent work use money efficiently? |
| Cumulative CPI | Cost efficiency since the baseline began | What is the project’s overall cost position? |
| Current-period SPI | Schedule efficiency this period | Did recent work deliver planned progress? |
| Cumulative SPI | Schedule efficiency since the baseline began | How far is the project from its planned progress? |
Show the values in a table or trend chart with the status dates. Explain important changes, such as a scope change, approved rebaseline, delayed supplier, or correction to a progress measurement.
Set thresholds before the result is known
A threshold is a predefined point that triggers investigation or action. Do not choose a threshold after seeing an inconvenient result. Agree on thresholds in the performance management plan, and record who must act when a threshold is crossed.
A common starting point is 0.95 for SPI or CPI, but this is only an example. A research project with uncertain work may need wider limits. A production project with fixed margins may need tighter limits. Use historical performance, contract terms, risk exposure, and management tolerance to set the limits.
Thresholds should answer three questions:
- What value or trend requires attention?
- Who investigates the cause?
- What action and follow-up date are required?
For example, two consecutive periods with CPI below 0.95 might require a cost analysis. A single period below 0.95 might only require monitoring if the data contains known timing effects.
Explain causes and assumptions
An honest report separates measured facts from explanations and forecasts.
- Fact: “Cumulative CPI is 0.91 at the end of period six.”
- Cause: “The index fell after specialist labor rates increased.”
- Forecast: “If the current cost efficiency continues, EAC is 110,000.”
- Action: “The team will review the labor plan by Friday.”
EAC is an estimate at completion. Its reliability depends on the assumption behind its calculation. The formula BAC divided by CPI assumes that current cost efficiency will continue. State that assumption and compare the result with a bottom-up estimate when the remaining work has different risks.
Do not hide unfavorable results by changing the baseline without approval. An approved scope or budget change may require a new baseline, but the report should preserve the previous performance history and identify the change date.
Use a reporting flow
Exercise
Exercise
Cumulative CPI is 0.90, but the current-period CPI is 1.02. What should the report say?
Show answer
The project remains 10 percent below its cumulative cost efficiency target, while recent work is slightly efficient. The report should explain the earlier overrun, state whether the improvement is expected to continue, and identify any corrective action or monitoring threshold.