Sub topic 5
Measuring Earned Value: 0/100, 50/50, Weighted Milestones, and Percent Complete
Earned value (EV) is the budgeted value of work that has actually been completed. This chapter assumes you understand work packages, budgets, schedules, and the difference between planned value (PV) and actual cost (AC).
EV depends on how you measure completion. If the method is inconsistent or too optimistic, SPI and CPI will be misleading even when their formulas are correct.
The basic rule
Assign each work package a budget. Then apply a completion rule to decide how much of that budget has been earned.
For example, a work package has a budget of $20,000. If the approved method says it is 50% complete, its EV is:
budget = 20_000
percent_complete = 0.50
ev = budget * percent_complete
print(f"Earned value: ${ev:,.0f}")The $10,000 EV represents planned-budget value. It does not mean that the team spent $10,000. Spending is measured by AC.
0/100 method
The 0/100 method earns no value until the work package is fully complete.
- Before completion: EV = $0.
- At completion: EV = the full work package budget.
For a $20,000 package, a package that is 90% finished still earns $0. When the acceptance criteria are met, it earns $20,000.
This method works well for short tasks with clear completion evidence, such as installing a component or approving a document. It prevents teams from claiming value for unfinished work. It can make progress appear delayed when work packages are large.
50/50 method
The 50/50 method earns half the budget when work starts and the remaining half when work finishes.
For a $20,000 package:
- At start: EV = $10,000.
- While active: EV remains $10,000.
- At completion: EV = $20,000.
This method gives early recognition without requiring a detailed progress estimate. Use it for short-duration packages where starting work is meaningful evidence. Avoid it for long or expensive packages. A project can receive too much EV merely because many packages were opened.
Weighted milestones
Weighted milestones divide a work package into observable results. Each milestone receives part of the budget.
Suppose a $20,000 design package has these approved milestones:
| Milestone | Weight | Earned value |
|---|---|---|
| Requirements approved | 20% | $4,000 |
| Detailed design complete | 50% | $10,000 |
| Design accepted | 30% | $6,000 |
If the first two milestones are complete, EV is $14,000. The weights should reflect the relative effort or value of the results, and each milestone should have objective acceptance evidence.
Weighted milestones are useful for complex work where “percent complete” would otherwise depend on opinion.
Percent complete
With a percent-complete method, EV equals the work package budget multiplied by an approved completion percentage. The percentage should come from measurable evidence, such as completed quantities, tested functions, or accepted deliverables.
Do not calculate completion from money spent. Spending 70% of the budget does not prove that 70% of the work is complete. This mistake can hide cost overruns because AC is being used to justify EV.
Choosing a method
Use 0/100 for short, clear tasks. Use 50/50 for short tasks where starting is meaningful but intermediate measurement is difficult. Use weighted milestones for complex deliverables with distinct acceptance points. Use percent complete only when progress can be measured objectively and reviewed regularly.
Exercise
A $40,000 work package uses the 50/50 method. It has started but is not complete. What are its EV and AC if the team has spent $25,000?
Show answer
EV is $20,000 because the package has started. AC is $25,000 because that is the recorded spending. The difference between them is not a measurement of completion.