Schedule Performance Index: EV divided by PV
Prerequisites and working model
Assume you can read a project schedule and budget, understand a work package, and calculate simple ratios. This chapter uses cumulative values measured at the same status date.
The Schedule Performance Index (SPI) is a ratio that compares the value of completed work with the value of work planned by a particular date:
\[ SPI = \frac{EV}{PV} \]
- Planned value (PV) is the budgeted value of work that should be complete by the status date.
- Earned value (EV) is the budgeted value of work that is actually complete.
- SPI is unitless. It does not have a currency or time unit.
For example, suppose a project has:
| Measurement | Value |
|---|---|
| PV | $40,000 |
| EV | $35,000 |
| SPI | 0.875 |
The project has earned $35,000 of planned work, although the baseline expected $40,000 by this date. An SPI of 0.875 means the project is progressing at 87.5% of its planned rate.
Calculating SPI
Use cumulative PV and cumulative EV for the same scope and status date. The calculation is:
def schedule_performance_index(ev, pv):
"""Calculate SPI from cumulative earned and planned value."""
if pv <= 0:
raise ValueError("PV must be greater than zero.")
return ev / pv
pv = 40_000
ev = 35_000
spi = schedule_performance_index(ev, pv)
print(f"SPI: {spi:.3f}")
print(f"Progress rate versus plan: {spi * 100:.1f}%")This code prints:
SPI: 0.875
Progress rate versus plan: 87.5%The same measurements can produce schedule variance:
\[ SV = EV - PV \]
In this example, schedule variance is $35,000 − $40,000 = −$5,000. The negative value shows that less budgeted work has been completed than planned. SPI expresses the same relationship as a ratio instead of a currency difference.
Interpreting the result
| SPI value | Meaning |
|---|---|
| Greater than 1.0 | More work is complete than the baseline planned by this date |
| Exactly 1.0 | Work completed matches the baseline plan |
| Less than 1.0 | Less work is complete than the baseline planned by this date |
An SPI of 1.10 does not mean the project will finish 10% early. It means the measured earned value is 10% greater than the planned value at the status date. The result may reflect work completed early, an inaccurate baseline, or an earned value measurement problem.
An SPI of 0.80 does not identify the cause of the delay. Investigate the schedule, dependencies, resources, approved changes, and the method used to measure completion.
Common errors
- Using actual cost (AC) in the formula. AC belongs in CPI, not SPI.
- Comparing current-period EV with cumulative PV, or reversing the comparison.
- Including different scope in PV and EV.
- Treating SPI as a percentage of total project completion. SPI compares progress by the status date, not total completion.
- Ignoring the baseline. If planned value is changed without proper change control, SPI becomes difficult to interpret.
- Treating one data point as a trend. Review several reporting periods and investigate sustained movement.
Exercise
A work package has cumulative PV of $60,000 and cumulative EV of $54,000. Calculate SPI and interpret it.
Show answer
SPI = 54,000 / 60,000 = 0.90. The work package has earned 90% of the value planned by the status date, so it is behind the baseline. Investigate the cause before predicting a finish date.