Sub topic 11
TCPI: the efficiency the remaining work requires
Prerequisites and purpose
Assume you can read a performance measurement baseline and calculate planned value (PV), earned value (EV), and actual cost (AC). You should also know that the budget at completion (BAC) is the approved budget for the whole project.
The To-Complete Performance Index (TCPI) answers a forward-looking question:
> How efficiently must the remaining work be performed to meet a cost target?
The target may be the original BAC or a revised estimate at completion (EAC).
The two TCPI formulas
To finish within the original budget, use:
\[ TCPI_{BAC}=\frac{BAC-EV}{BAC-AC} \]
The numerator is the budgeted value of the remaining work. The denominator is the money remaining in the original budget.
To finish within a revised EAC, use:
\[ TCPI_{EAC}=\frac{BAC-EV}{EAC-AC} \]
The numerator stays the same because the remaining scope has not changed. The denominator changes because the cost target is now EAC.
| Result | Meaning |
|---|---|
| TCPI = 1.00 | Remaining work must meet the planned cost efficiency |
| TCPI > 1.00 | Remaining work must be more cost-efficient than the reference target |
| TCPI < 1.00 | Remaining work may be less cost-efficient than the reference target |
A TCPI of 1.20 means each $1.00 of remaining cost must produce $1.20 of earned value. That may be possible, but it deserves a specific recovery plan rather than optimistic reporting.
Worked example
Suppose a project has these status-date measurements:
- BAC = $100,000
- EV = $35,000
- AC = $42,000
- EAC = $120,000
The remaining earned value is $100,000 − $35,000 = $65,000.
The remaining original budget is $100,000 − $42,000 = $58,000. Therefore:
\[ TCPI_{BAC}=\frac{65,000}{58,000}=1.121 \]
The project would need a cost efficiency of 1.121 for the remaining work to meet BAC. Since the current CPI is only 0.833, this target is difficult.
Using EAC as the target:
\[ TCPI_{EAC}=\frac{65,000}{120,000-42,000}=0.833 \]
This target matches the current CPI because EAC was calculated as \(BAC/CPI\). It assumes the current cost efficiency continues.
def tcpi(bac, ev, ac, eac=None):
"""Calculate TCPI against BAC and, optionally, EAC."""
remaining_ev = bac - ev
tcpi_bac = remaining_ev / (bac - ac)
result = {"TCPI_BAC": tcpi_bac}
if eac is not None:
result["TCPI_EAC"] = remaining_ev / (eac - ac)
return result
values = tcpi(100_000, 35_000, 42_000, 120_000)
for name, value in values.items():
print(f"{name}: {value:.3f}")How to use TCPI in decisions
TCPI is a required future efficiency, not a forecast by itself. Compare it with the current CPI, recent CPI trend, and the work still to be performed.
A denominator of zero makes the formula undefined. A negative denominator usually means the project has already spent at least the entire reference budget, so the selected target is no longer attainable under the formula's assumptions.
Exercise
BAC is $200,000, EV is $80,000, and AC is $100,000. What is TCPI against BAC, and what does it mean?
Show answer
TCPI = (200,000 − 80,000) / (200,000 − 100,000) = 1.20. Each remaining $1.00 of cost must produce $1.20 of earned value to finish within BAC.