Sub topic 4
Actual Cost: What the Work Has Cost So Far
Assume you know the work breakdown structure, the approved budget baseline, and how to read a project schedule. You should also be comfortable with basic arithmetic and percentages.
What actual cost measures
Actual cost (AC) is the cost incurred for the work performed by a specified status date. It answers this question:
How much has the completed work cost us so far?
AC can include:
- Labor charged to the project
- Materials and equipment
- Subcontractor invoices
- Travel and other direct expenses
- An allocated share of indirect costs, when the project’s accounting rules require it
AC is recorded in the same currency and for the same scope as planned value (PV) and earned value (EV). This common basis makes comparison possible.
An invoice date does not always equal the date when the cost belongs in AC. A project may need an accrual, which is an estimated cost recorded before an invoice arrives. For example, if a subcontractor completed work in March but will invoice in April, the March status report should include the March cost when the accounting rules require it.
AC must have a reliable cutoff
A status date is the agreed point in time at which project performance is measured. AC should include costs incurred through that date, while excluding costs belonging to later periods.
Common errors include:
- Including an invoice for work that has not been performed
- Omitting labor because timesheets are late
- Counting a purchase commitment as a cost when the accounting method records cost only when goods are received
- Mixing actual costs from one period with EV from another period
- Changing cost categories during the project without documenting the change
A purchase order or commitment may help forecast future cost, but it is not automatically AC. Follow the project’s approved accounting rules.
Worked example
Suppose the project team reports the following cumulative values at the end of period 3:
| Measure | Amount | Meaning |
|---|---|---|
| PV | $40,000 | Budgeted value of work planned by now |
| EV | $35,000 | Budgeted value of work actually completed |
| AC | $42,000 | Cost incurred for that completed period of work |
The project has spent $42,000, but the completed work is valued at only $35,000 in the baseline. The cost variance is:
CV = EV - AC CV = $35,000 - $42,000 = -$7,000
A negative cost variance means the project has spent more than the budgeted value of the work completed.
The Cost Performance Index (CPI) expresses the same relationship as an efficiency ratio:
CPI = EV / AC CPI = 35,000 / 42,000 = 0.833
A CPI of 0.833 means the project is receiving about $0.83 of budgeted value for every $1.00 of actual cost. CPI is covered in detail when the three measurements are interpreted together.
A small calculation in Python
ev = 35_000
ac = 42_000
cost_variance = ev - ac
cpi = ev / ac
print(f"Cost variance: ${cost_variance:,.0f}")
print(f"CPI: {cpi:.3f}")The code prints a cost variance of negative $7,000 and a CPI of 0.833. The calculation does not determine whether the result is acceptable. The project’s thresholds and trend provide that judgment.
Exercise
A project has EV of $18,000 and AC of $20,000 at the status date. What are its cost variance and CPI, and what do they indicate?
Show answer
CV = $18,000 - $20,000 = -$2,000. CPI = $18,000 / $20,000 = 0.900. The project is over budget for the work completed and earns $0.90 of budgeted value per $1.00 of actual cost.