What EAC and ETC Are, and How They Fit Together
Prerequisites and the basic idea
This chapter assumes that you know basic project management terms such as scope, budget, schedule, and baseline. You should also be comfortable with simple arithmetic and ratios.
Earned value management uses several measures to compare a project’s plan with its actual progress:
- Budget at Completion (BAC) is the approved total budget for the project.
- Planned Value (PV) is the budgeted value of work that should be complete by a date.
- Earned Value (EV) is the budgeted value of work that is actually complete.
- Actual Cost (AC) is the amount spent for the work completed so far.
Estimate at Completion (EAC) is the forecast of the project’s total cost when all planned work is finished. EAC includes both money already spent and money expected to be spent.
Estimate to Complete (ETC) is the forecast of the additional cost needed to finish the remaining work. ETC excludes costs already recorded in AC.
The core relationship is:
EAC = AC + ETC
Rearranging the same relationship gives:
ETC = EAC - AC
These formulas work when AC, EAC, and ETC use the same reporting date and the same cost scope.
A worked example
Suppose a project has a BAC of $100,000. At the reporting date:
- AC is $48,000.
- EV is $40,000.
- The cost performance index (CPI) is
EV / AC, or40,000 / 48,000 = 0.8333.
A CPI below 1 means the project is receiving less budgeted value than the amount it spends. If this cost performance continues, a simple EAC forecast is:
EAC = BAC / CPI
So:
EAC = 100,000 / 0.8333 = 120,000
The forecast total cost is therefore $120,000. The ETC is:
ETC = EAC - AC
ETC = 120,000 - 48,000 = 72,000
The project has already spent $48,000 and forecasts another $72,000, producing a total forecast cost of $120,000.
def forecast_remaining_cost(ac, eac):
return eac - ac
ac = 48_000
eac = 120_000
etc = forecast_remaining_cost(ac, eac)
print(f"EAC: ${eac:,.0f}")
print(f"ETC: ${etc:,.0f}")The output is:
EAC: $120,000
ETC: $72,000EAC is a total-project measure. ETC is a remaining-work measure. Confusing them can make a forecast appear much smaller than it really is.
How the measures fit together
The reporting date divides the project into two parts:
AC is historical data. It records what the project has already spent. ETC is a forward-looking forecast. It estimates the cost of the unfinished work. EAC combines both.
| Measure | Time orientation | Main question |
|---|---|---|
| AC | Past and present | How much have we spent? |
| ETC | Future | How much more will we spend? |
| EAC | Entire project | What will the project cost in total? |
| BAC | Baseline plan | What was the approved total budget? |
Do not treat EAC as a single formula
There is no single EAC formula that fits every project. The right method depends on why the project’s current performance differs from its plan.
If the past variance was a one-time event, a manager may use:
EAC = AC + (BAC - EV)
If current cost efficiency is expected to continue, a manager may use:
EAC = BAC / CPI
If both cost and schedule performance are expected to influence the remaining work, a combined formula may be used. A bottom-up EAC instead asks the team to estimate each remaining activity again.
The method is a management assumption, not just a mathematical choice. The forecast should state which assumption produced it.
Check the result
Before reporting an ETC, verify that:
- AC and EAC use the same cutoff date.
- ETC covers only unfinished work.
- The forecast includes expected labor, materials, contracts, and other relevant costs.
- The selected EAC method matches the reason for the current variance.
- The numbers are not mixing different currencies or cost categories.
Exercise
A project has an AC of $35,000 and an EAC of $90,000. What is its ETC, and what does that number mean?
Show answer
ETC is $55,000, calculated as $90,000 - $35,000. It is the forecast additional cost required to finish the remaining work.