Bottom-up EAC: Re-estimating the Remaining Work
Assume you know basic project vocabulary, simple ratios, and the project baseline. This chapter uses AC for actual cost, BAC for budget at completion, and EAC for estimate at completion. A bottom-up estimate is useful when the remaining work can be examined in detail.
What a bottom-up EAC is
Estimate at completion is the expected total project cost:
EAC = AC + ETCETC, or estimate to complete, is the expected cost of all remaining work. In a bottom-up EAC, the team re-estimates that remaining work instead of extending the project’s past cost performance with a single ratio.
The team breaks the unfinished scope into work packages or activities. It estimates the cost left for each item, adds those estimates, and then adds the result to the actual cost already recorded.
This method is different from calculating EAC as BAC divided by CPI. A CPI-based forecast assumes that past cost efficiency will continue. A bottom-up forecast asks what the remaining work actually requires now.
Re-estimating the remaining work
Start with the current status date. Confirm which work is complete, which work is partly complete, and which work remains. Do not estimate unfinished work from the original budget alone. Review current quantities, rates, contracts, risks, and known changes.
For each remaining work package, estimate the cost still needed. The estimate can include labor, materials, vendor charges, travel, and other approved project costs. If a work package is partly complete, include only its remaining cost. Its recorded cost is already part of AC.
For example, a software project has an AC of $48,000. The team reviews the remaining work:
| Remaining work package | Estimated cost to finish |
|---|---|
| User interface design | $12,000 |
| Application build | $28,000 |
| System testing | $10,000 |
| Deployment and handover | $5,000 |
| Total ETC | $55,000 |
The bottom-up forecast is:
EAC = AC + ETC
EAC = $48,000 + $55,000
EAC = $103,000If the BAC is $100,000, the forecast is $3,000 over budget. The team can explain that forecast by showing the cost of each remaining package rather than reporting only a ratio.
Making the estimate credible
A bottom-up EAC is only as good as its assumptions. Record the basis for each estimate. For example, a labor estimate might use 160 remaining hours multiplied by a loaded rate of $75 per hour. A vendor estimate might use a signed quotation. A testing estimate might include the number of planned test cycles and the cost per cycle.
Separate known remaining cost from uncertainty. A team might estimate $50,000 for planned work and add a documented $5,000 risk allowance. Do not hide an unexplained buffer inside every work package because that can double-count risk.
Ask the people responsible for the work to review the estimates. Compare the new ETC with the remaining baseline budget:
Remaining baseline budget = BAC - EVIf BAC is $100,000 and EV is $40,000, the remaining baseline budget is $60,000. The new ETC of $55,000 is $5,000 below that amount, even though the project has already spent more than the value earned. This can happen when the remaining work is now expected to be more efficient than the work completed so far.
A bottom-up EAC should also state its date and assumptions. Estimates change when scope, rates, suppliers, or delivery plans change.
When to choose this method
Use a bottom-up EAC when:
- The remaining scope is understood well enough to estimate.
- Current conditions differ from the conditions that produced past performance.
- A major one-time event distorted the historical CPI.
- The project has experienced a design, supplier, staffing, or scope change.
- Stakeholders need an accountable forecast from the people doing the remaining work.
The method takes more effort than a formula-based forecast. It can also introduce optimism if the team ignores risks or understates unfinished work. Compare it with CPI-based EACs, explain the differences, and document why the selected forecast best represents current conditions.
Exercise
A project has AC of $72,000 and a team re-estimates the remaining work at $34,000. What is the bottom-up EAC, and what is the forecast variance if BAC is $100,000?
Show answer
EAC is $106,000 because $72,000 + $34,000 = $106,000. The forecast variance is -$6,000 because BAC - EAC = $100,000 - $106,000.