TCPI: the efficiency the remaining work demands
Assume you know the earned value measures BAC, EV, and AC, and can calculate CPI. The To-Complete Performance Index (TCPI) is a forecast measure. It shows the cost efficiency the remaining work must achieve to meet a chosen target.
TCPI does not describe the project's performance so far. CPI does that. TCPI describes the performance required from this point forward.
The two TCPI targets
You can calculate TCPI against either the original budget or the current forecast:
- To meet BAC:
TCPI(BAC) = (BAC - EV) / (BAC - AC) - To meet EAC:
TCPI(EAC) = (BAC - EV) / (EAC - AC)
The numerator is the budgeted value of the work remaining. The denominator is the money available for that remaining work.
| Target | Meaning | When to use it |
|---|---|---|
| BAC | Efficiency needed to finish at the original budget | Evaluate whether the budget target is still realistic |
| EAC | Efficiency needed to finish at the current estimate | Evaluate whether the forecast is achievable |
A TCPI of 1.00 means the remaining work must produce one dollar of earned value for every dollar spent. A value above 1.00 requires better efficiency than that. A value below 1.00 means the remaining work can be less efficient than one-to-one and still meet the target.
Worked example
Suppose a project has these values:
- BAC: $100,000
- EV: $40,000
- AC: $48,000
- EAC: $120,000
The project has completed $40,000 of budgeted work but has spent $48,000. Its CPI is:
CPI = EV / AC = 40,000 / 48,000 = 0.8333
To finish within the original BAC:
TCPI(BAC) = (100,000 - 40,000) / (100,000 - 48,000)
TCPI(BAC) = 60,000 / 52,000 = 1.1538
The remaining work would need a cost efficiency of about 1.15. That is much better than the current CPI of 0.83, so the original budget is difficult to defend without a major change.
To finish within the EAC of $120,000:
TCPI(EAC) = (100,000 - 40,000) / (120,000 - 48,000)
TCPI(EAC) = 60,000 / 72,000 = 0.8333
This target matches the current CPI. The forecast assumes that the project will continue at its present cost efficiency.
bac, ev, ac, eac = 100000, 40000, 48000, 120000
tcpi_bac = (bac - ev) / (bac - ac)
tcpi_eac = (bac - ev) / (eac - ac)
print(f"TCPI against BAC: {tcpi_bac:.4f}")
print(f"TCPI against EAC: {tcpi_eac:.4f}")How to interpret the result
Compare TCPI with the project's historical CPI and with the team's realistic capacity.
- If TCPI is close to the historical CPI, the target may be credible.
- If TCPI is substantially higher, the team needs corrective action, such as reducing scope, improving productivity, or increasing resources.
- If TCPI is below the historical CPI, the target has more cost flexibility than the original budget.
- If the denominator is zero or negative, interpret the result carefully. For example,
BAC - ACcan be zero when actual cost already equals the budget, making the BAC target mathematically undefined or impossible.
>callout note > TCPI is a target, not a promise. A low TCPI does not prove that the forecast is safe. Check whether the remaining work has risks, dependencies, or scope changes that the historical numbers do not capture.
Common errors
Do not use EV / AC as TCPI. That is CPI, which measures completed performance.
Do not use the BAC formula when stakeholders have approved a different completion forecast. State the target explicitly in the report.
Do not interpret TCPI without context. A value of 1.10 may be achievable for routine work but unrealistic for a technically difficult final phase.
Report both the selected target and the comparison that supports it. For example: “TCPI against EAC is 0.83, equal to the current CPI of 0.83. The forecast assumes current cost efficiency continues.”
Exercise
A project has BAC = $80,000, EV = $30,000, AC = $36,000, and EAC = $90,000. What are TCPI against BAC and TCPI against EAC, and which target is more consistent with the current CPI?
Show answer
TCPI(BAC) = 50,000 / 44,000 = 1.1364. TCPI(EAC) = 50,000 / 54,000 = 0.9259. The current CPI is 30,000 / 36,000 = 0.8333, so the EAC target is closer to current performance.