Sub topic 1
The inputs: BAC, PV, EV, and AC
Prerequisites
Assume you know basic project management terms such as scope, budget, schedule, baseline, and reporting date. You should also be comfortable with simple arithmetic and ratios. This chapter introduces the four earned value inputs used later to forecast final project cost.
Earned value management (EVM) is a method for comparing planned work, completed work, and actual spending. It uses a time-phased baseline, which means the approved budget is distributed across the project schedule. The comparison is made at a specific reporting date, sometimes called the data date.
The four measures
The measures use the same currency and refer to the same scope:
| Measure | Meaning | Key question |
|---|---|---|
| BAC | Budget at Completion | What was the approved budget for all work? |
| PV | Planned Value | How much budgeted work should be complete by the reporting date? |
| EV | Earned Value | How much budgeted work is actually complete by the reporting date? |
| AC | Actual Cost | How much has the completed work actually cost? |
Budget at Completion: BAC
Budget at Completion (BAC) is the approved total budget for the project or the part of the project being measured. It includes the planned budget for all authorized work.
For example, a project may have a BAC of $100,000. BAC does not change merely because the project is spending more or less than expected. If the approved baseline changes, record that change clearly. Otherwise, performance comparisons can become misleading.
Planned Value: PV
Planned Value (PV) is the budgeted value of the work scheduled to be complete by a particular date. It is sometimes called the budgeted cost of work scheduled.
Suppose the project has a BAC of $100,000 and the baseline says that 50% of the work should be complete today. The PV is:
PV = 100{,}000 \times 0.50 = 50{,}000PV describes the plan, not what actually happened. It comes from the approved schedule and cost baseline.
Earned Value: EV
Earned Value (EV) is the budgeted value of the work actually completed by the reporting date. It is sometimes called the budgeted cost of work performed.
If the team has completed 40% of the total scope, and the BAC is $100,000:
EV = 100{,}000 \times 0.40 = 40{,}000EV is not the amount invoiced and not the amount spent. It values completed work using the baseline budget.
Actual Cost: AC
Actual Cost (AC) is the cost recorded for the work completed by the reporting date. It is sometimes called the actual cost of work performed.
AC can include labor, materials, supplier payments, and other approved project costs. Use the same scope and cutoff date as PV and EV. Including invoices from outside the period, or omitting committed costs according to the project’s accounting rules, can distort the comparison.
def earned_value_inputs(bac, planned_percent, completed_percent, actual_cost):
pv = bac * planned_percent
ev = bac * completed_percent
ac = actual_cost
return {"BAC": bac, "PV": pv, "EV": ev, "AC": ac}
inputs = earned_value_inputs(100_000, 0.50, 0.40, 48_000)
for name, value in inputs.items():
print(f"{name}: ${value:,.0f}")The example produces BAC of $100,000, PV of $50,000, EV of $40,000, and AC of $48,000. These four values describe the project’s position at one point in time. They do not, by themselves, explain why the project differs from its plan.
How the measures fit together
The relationships can be viewed as three comparisons:
PV and EV use budget rates, so they can be compared directly even when actual spending differs. AC uses real spending. For example, EV of $40,000 means the team completed work worth $40,000 according to the baseline. AC of $48,000 means that work required $48,000 in recorded costs.
The reporting date matters. A value without its date, scope, and baseline version is incomplete. A project can have the same BAC throughout its life while its PV, EV, and AC change each reporting period.
> callout note > Keep the measurement basis consistent. PV, EV, and AC must cover the same scope and stop at the same reporting date. Mixing dates or scope boundaries makes later forecasts unreliable.
A short interpretation
In this example, PV is $50,000 and EV is $40,000, so less budgeted work is complete than planned. AC is $48,000, which is more than EV. The project has spent $48,000 to produce $40,000 of budgeted work.
The next chapter turns these differences into cost and schedule measures. Those measures help select a suitable forecast method, but they are only as reliable as the BAC, PV, EV, and AC data behind them.
Exercise
A project has a BAC of $80,000. By the reporting date, 60% of the work was planned, 50% was complete, and actual spending was $46,000. What are PV, EV, and AC?
Show answer
PV is $48,000, EV is $40,000, and AC is $46,000.