From EAC to ETC: How Much Is Left to Spend
Assume you already know the earned value measures planned value (PV), earned value (EV), actual cost (AC), and budget at completion (BAC). You should also be comfortable with ratios such as the cost performance index (CPI). This chapter uses those measures to calculate the money still expected to be spent.
The relationship between EAC, AC, and ETC
Estimate at completion (EAC) is the forecast of the project’s total cost when all work is finished. Estimate to complete (ETC) is the forecast of the additional cost needed to finish the remaining work.
The relationship is:
EAC = AC + ETC
Therefore:
ETC = EAC - AC
AC records money already spent. ETC covers only future spending. Adding them gives the forecast total cost.
For example, suppose a project has:
- BAC: $100,000
- EV: $40,000
- AC: $48,000
- EAC: $120,000
The ETC is:
ETC = $120,000 - $48,000 = $72,000
The project has already spent $48,000 and expects to spend another $72,000. The total forecast is $120,000.
Calculating ETC directly from performance data
You can calculate ETC by first choosing an EAC method. Each method makes a different assumption about future performance.
If past cost and schedule problems were unusual and will not continue:
ETC = BAC - EV
For the example:
ETC = $100,000 - $40,000 = $60,000
This method treats the remaining budgeted work as a reasonable estimate of remaining spending. It ignores the current cost inefficiency because that inefficiency was considered temporary.
If current cost performance will continue, use the CPI:
ETC = (BAC - EV) / CPI
The CPI is EV divided by AC:
CPI = $40,000 / $48,000 = 0.8333
Therefore:
ETC = $60,000 / 0.8333 ≈ $72,000
This matches the result from EAC = BAC / CPI, which produces an EAC of about $120,000.
If both cost and schedule performance will influence the remaining cost:
ETC = (BAC - EV) / (CPI × SPI)
For example, if SPI is 0.8:
ETC = $60,000 / (0.8333 × 0.8) ≈ $90,000
This larger ETC reflects the possibility that schedule delays will create additional costs.
| Assumption about the future | Direct ETC calculation | Example ETC |
|---|---|---|
| Past variance was atypical | BAC - EV | $60,000 |
| Cost efficiency continues | (BAC - EV) / CPI | $72,000 |
| Cost and schedule effects continue | (BAC - EV) / (CPI × SPI) | $90,000 |
Using a bottom-up ETC
A bottom-up ETC is a fresh estimate of the remaining work. The project team reviews each unfinished activity, estimates its remaining labor, materials, and other costs, and adds those estimates together.
This approach is useful when the original forecast formulas no longer describe the project. For example, a major design change may make earlier CPI and SPI values less relevant. A bottom-up ETC can account for known contract prices, revised staffing, supplier quotes, and newly identified risks.
Its main weakness is effort and judgment. Team members may underestimate remaining work to appear confident, or they may count costs already included in AC. Check that the estimate includes future costs only.
Checking the result
After calculating ETC, recompute EAC:
EAC = AC + ETC
If the direct ETC is $72,000, then:
EAC = $48,000 + $72,000 = $120,000
Compare this EAC with BAC. A forecast above BAC indicates a projected overrun. Also explain the assumption behind the ETC. Stakeholders can interpret $72,000 differently depending on whether it came from continuing cost performance, a schedule-adjusted model, or a detailed re-estimate.
bac, ev, ac = 100000, 40000, 48000
cpi = ev / ac
etc = (bac - ev) / cpi
eac = ac + etc
print(round(etc)) # 72000
print(round(eac)) # 120000Exercise
A project has BAC of $80,000, EV of $30,000, AC of $36,000, and an EAC of $96,000. What are the ETC and the expected cost overrun against BAC?
Show answer
ETC is $96,000 - $36,000 = $60,000. The expected overrun is $96,000 - $80,000 = $16,000.