Choosing and Justifying an EAC Method
Assume you know the basic project terms scope, budget, baseline, planned value (PV), earned value (EV), and actual cost (AC). You should also be comfortable interpreting the cost performance index (CPI) and schedule performance index (SPI). This chapter focuses on choosing a forecast method, not on recalculating every earned value measure.
Why the method matters
Estimate at completion (EAC) is the forecast of the total project cost when all work is finished. Different EAC formulas make different assumptions about the future.
For example, suppose a project has:
- Budget at completion (BAC): $100,000
- EV: $40,000
- AC: $48,000
- PV: $50,000
- CPI: $0.8333
- SPI: $0.8
The project has earned $40,000 of planned work but has spent $48,000. It is both over cost and behind schedule. The following methods produce different forecasts:
| Method | Formula | EAC |
|---|---|---|
| Atypical variance | `AC + (BAC - EV)` | $108,000 |
| Typical cost performance | `BAC / CPI` | $120,000 |
| Cost and schedule influence | `AC + (BAC - EV) / (CPI × SPI)` | $138,000 |
| Bottom-up estimate | `AC + ETC` | Depends on re-estimate |
The difference is not a mathematical error. Each result answers a different question about what will happen next.
Use the atypical-variance method for a one-off event
Use this formula when the past overrun was unusual and will not affect the remaining work:
EAC = AC + (BAC - EV)
Examples include:
- A one-time equipment failure
- An exceptional legal or regulatory cost
- An approved correction that will not recur
- A vendor problem that has been permanently resolved
The formula assumes that the remaining budget is still a reasonable estimate for the remaining work. It does not carry the current CPI into the future.
This method can be justified to stakeholders only when you can identify the cause of the variance and show why it will not recur. Saying that the team “expects to do better” is not enough. Document the event, its financial effect, and the evidence that the risk has been removed.
Use the CPI method when cost performance is likely to continue
Use this formula when the project’s cost efficiency reflects an ongoing condition:
EAC = BAC / CPI
This method assumes that future work will be completed with the same cost efficiency as completed work. It is appropriate when the cause of the overrun remains active, such as:
- Low productivity
- Persistent labor-rate differences
- Repeated rework
- A continuing supplier price increase
- A consistently inaccurate estimate
With a CPI below 1, the forecast is higher than the original budget. In the example, 100,000 / 0.8333 gives an EAC of about $120,000.
Do not use this method automatically after one bad reporting period. A single unusual period may not represent a stable trend. Review several periods, the causes of variance, and the reliability of the EV measurement first.
Include schedule influence when delay raises cost
Use this formula when schedule performance directly affects future spending:
EAC = AC + (BAC - EV) / (CPI × SPI)
This method treats both cost efficiency and schedule efficiency as predictors of the remaining cost. It may fit a project where delay causes overtime, extended site rental, inflation exposure, or additional management overhead.
It can produce a much higher forecast because it compounds two performance problems. Use it carefully. SPI is based on value earned against time and does not always measure calendar delay accurately, especially near project completion. Explain the causal link between schedule delay and cost before using this formula.
Use a bottom-up EAC when the remaining work has changed
A bottom-up EAC starts with a new estimate to complete (ETC):
EAC = AC + ETC
The team reviews each remaining activity, resource need, risk, and commitment. This method takes more effort, but it is often the strongest choice when:
- Scope has changed
- The original estimate is no longer realistic
- The project has entered a different phase
- Corrective actions have changed productivity
- Remaining work is substantially different from completed work
The bottom-up estimate should include assumptions and risk allowances. Compare it with formula-based forecasts. A large difference is a signal to investigate, not a reason to choose the more comfortable number.
A practical selection process
Use this sequence when presenting a forecast:
- Identify the main causes of current cost and schedule variance.
- Decide whether each cause is one-off, continuing, or already corrected.
- Check whether schedule delay creates additional cost.
- Select the formula whose assumptions match that evidence.
- Compare the result with at least one alternative method.
- Record the method, data date, assumptions, and confidence level.
Worked decision
In the example, the CPI is 0.8333 and the SPI is 0.8. If the overrun came from a single failed machine that has been replaced, the atypical forecast of $108,000 may be appropriate. If low productivity continues, use the CPI forecast of $120,000. If the schedule delay requires additional site and labor costs, consider the combined forecast of $138,000. If the remaining work has been replanned, create a bottom-up ETC and use that result.
Exercise
A project is over budget because of a one-time supplier dispute. The dispute is settled, and future prices are stable. Which EAC method is the best starting point, and what must you document?
Show answer
Use EAC = AC + (BAC - EV). Document the dispute, its cost, evidence that it will not recur, and any remaining risks.