Sub topic 12
Pitfalls and How to Report a Forecast
Assume you understand scope, budget, schedule, the project baseline, and the basic earned value measures: budget at completion (BAC), planned value (PV), earned value (EV), and actual cost (AC). This chapter focuses on checking an earned value forecast before you present it.
An estimate at completion (EAC) is a forecast of the total project cost. An estimate to complete (ETC) is the expected cost of the remaining work. A forecast can be mathematically correct and still be misleading if its assumptions do not match the project.
Common forecasting pitfalls
Treating every variance as permanent
The formula EAC = BAC / CPI assumes that current cost efficiency will continue. It is useful when the cause of the variance is likely to remain.
For example, a continuing supplier price increase may make the current cost performance a reasonable guide. A one-time equipment failure may not. If the failure is resolved, repeating its effect across the rest of the project overstates the final cost.
For a one-time problem, use the atypical-variance formula:
EAC = AC + (BAC - EV)
This formula assumes the remaining work will follow the original budget.
Ignoring schedule effects
CPI measures cost efficiency. SPI measures schedule efficiency. Neither index explains the cause of poor performance by itself.
A project can have a low SPI because work was delayed by an approval. If the delay causes overtime, rework, or extended staffing, it can also affect the final cost. In that situation, a cost-and-schedule formula may be useful:
EAC = AC + (BAC - EV) / (CPI × SPI)
This method is sensitive to both indices. It can produce a high forecast when both cost and schedule performance are poor, but it should not be used automatically. Schedule effects may already be included in AC or in a new bottom-up estimate.
Mixing incompatible data
Earned value calculations depend on a consistent status date and a stable baseline. Do not compare EV from one reporting period with AC from another. Check that:
- PV, EV, and AC use the same status date.
- The scope and work breakdown structure have not changed without an approved baseline update.
- AC includes the same cost categories as the budget.
- Accruals, commitments, and invoices are treated consistently.
- EV reflects completed work rather than work merely started.
Relying on a small or unstable sample
An index based on one early reporting period may be volatile. Early work may contain unusual setup costs, while later work may have a different cost structure. Report the number of periods used and explain whether performance has stabilized.
A trend is more credible when the cause of the trend is understood and recent periods show similar results.
Choosing and explaining the method
Use a short decision process:
- Identify the cause of the current variance.
- Decide whether that cause will affect the remaining work.
- Select a formula whose assumption matches that decision.
- Compare the result with an independent estimate.
- Record the assumption, status date, and confidence level.
A bottom-up EAC is often preferable when the remaining work has been re-planned. It is calculated as:
EAC = AC + new ETC
The team estimates each remaining activity, includes known risks and commitments, and adds that estimate to actual cost. This method takes more effort, but it can reflect changed scope, new rates, corrected productivity assumptions, and resolved problems better than a single index.
| Method | Main assumption | Best use |
|---|---|---|
| AC + (BAC - EV) | Past variance was unusual | One-time event |
| BAC / CPI | Current cost efficiency continues | Stable cost trend |
| AC + (BAC - EV) / (CPI × SPI) | Cost and schedule jointly affect remaining cost | Persistent schedule-driven cost pressure |
| AC + new ETC | Remaining work has been re-estimated | Changed or complex project |
Reporting the forecast
A useful forecast report contains more than one number. Include:
- The status date and data source.
- BAC, PV, EV, AC, CPI, and SPI.
- The selected EAC and ETC.
- VAC, calculated as BAC - EAC.
- TCPI and the performance level needed to meet BAC or EAC.
- The method and its assumption.
- Major risks, approved changes, and unresolved data issues.
- A comparison with the previous forecast.
Explain the direction in plain language. For example: “The CPI is 0.83, so the project is earning 83 cents of planned value for each dollar spent. The CPI-based EAC is 120,000 against a BAC of 100,000. The forecast is 20,000 over budget, and the remaining work must perform at a TCPI of 0.83 against the EAC.”
The report should distinguish facts from judgments. AC is observed cost. EAC is a forecast. The explanation connects the two without presenting the forecast as certain.
Exercise
A project has a BAC of 100,000, an EV of 40,000, and an AC of 48,000. The overrun came from a one-time equipment failure that has been corrected. Which EAC method should you justify, and why?
Show answer
Use EAC = AC + (BAC - EV), giving 108,000. The equipment failure was atypical, so the formula does not extend its cost inefficiency across the remaining work.