Sub topic 7
Variance at Completion: The Forecast Gap to Budget
Assume you know the basic earned value measures: Budget at Completion (BAC), Earned Value (EV), Actual Cost (AC), and Estimate at Completion (EAC). This chapter uses those measures to interpret the project’s expected cost at the finish.
What VAC measures
Variance at Completion (VAC) compares the approved project budget with the forecast final cost:
VAC = BAC - EAC- BAC is the total budget approved for the project.
- EAC is the forecast of the total cost when the project finishes.
- VAC is the expected budget variance at completion.
VAC uses the same cost units as the budget, such as dollars or euros.
| Result | Meaning |
|---|---|
| Positive VAC | The project is forecast to finish under budget |
| Zero VAC | The project is forecast to finish exactly on budget |
| Negative VAC | The project is forecast to finish over budget |
The sign matters. A negative VAC is not a negative cost. It means the forecast cost is greater than the approved budget.
Calculating VAC from EAC
Suppose a project has:
- BAC = $100,000
- EAC = $120,000
Applying the formula:
VAC = 100{,}000 - 120{,}000 = -20{,}000The project is forecast to finish $20,000 over budget.
You can also express the gap as a percentage of the budget:
VAC\% = \frac{VAC}{BAC} \times 100For this project:
VAC\% = \frac{-20{,}000}{100{,}000} \times 100 = -20\%The forecast is therefore 20% over the approved budget.
A percentage helps stakeholders compare projects of different sizes. The dollar value is still needed for funding and decision-making.
How VAC connects to current performance
VAC depends on the EAC method. Different assumptions about future performance produce different EAC values, and therefore different VAC values.
Assume the following status data:
- BAC = $100,000
- PV = $50,000
- EV = $40,000
- AC = $48,000
The cost performance index is:
CPI = \frac{EV}{AC} = \frac{40{,}000}{48{,}000} \approx 0.8333If current cost efficiency continues, use:
EAC = \frac{BAC}{CPI}This gives:
EAC = \frac{100{,}000}{0.8333} \approx 120{,}000The corresponding VAC is:
VAC = 100{,}000 - 120{,}000 = -20{,}000The same data could support an atypical-variance EAC:
EAC = AC + (BAC - EV)EAC = 48{,}000 + (100{,}000 - 40{,}000) = 108{,}000That method produces:
VAC = 100{,}000 - 108{,}000 = -8{,}000Both VAC values are mathematically correct for their selected EAC methods. They answer different questions:
- -$8,000 assumes the past cost problem will not repeat.
- -$20,000 assumes the project will continue earning value at its current cost efficiency.
Reporting and interpreting VAC
Do not report VAC without naming the EAC method and the date of the data. A useful report might say:
> Based on performance through week 10, the current-performance EAC is $120,000 against a BAC of $100,000. VAC is therefore -$20,000, or 20% over budget. This forecast assumes the current CPI continues.
This wording separates the calculation from the assumption. It also prevents stakeholders from treating a forecast as a guaranteed result.
VAC does not explain the cause of a variance. A negative value could result from scope growth, incorrect estimates, inflation, rework, low productivity, or a one-time event. Investigate the cause before deciding whether the selected EAC method is reasonable.
Common mistakes
- Reversing the formula and reporting
EAC - BACwhile labeling it VAC. - Treating a negative VAC as a negative project cost.
- Comparing VAC with the wrong budget baseline.
- Mixing an EAC forecast with BAC from a different scope or approval period.
- Reporting only the dollar gap and hiding the percentage or forecasting assumption.
- Updating EAC without recording the reason for the change.
VAC is most useful as a concise forecast signal. Pair it with CPI, SPI, the EAC method, and an explanation of major risks.
Exercise
A project has a BAC of $250,000 and an EAC of $275,000. What are its VAC and VAC percentage, and what do they mean?
Show answer
VAC = $250,000 - $275,000 = -$25,000. VAC percentage = -$25,000 / $250,000 × 100 = -10%. The project is forecast to finish $25,000, or 10%, over budget.