EAC when Cost and Schedule Both Drive the Outcome
When this method applies
This chapter assumes you know the earned value measures planned value (PV), earned value (EV), actual cost (AC), and budget at completion (BAC). You should also be comfortable with the cost performance index (CPI) and schedule performance index (SPI).
Sometimes a project is over budget because work is taking longer than planned. Delays can create overtime, extra management effort, extended contractor contracts, or inflation exposure. In this situation, cost performance alone may give an overly optimistic forecast. The cost-and-schedule method includes both types of performance when estimating the final cost.
The formula is:
EAC = AC + (BAC - EV) / (CPI × SPI)
EAC means estimate at completion. It is the forecast of the total project cost when all planned work is finished.
CPI measures cost efficiency:
CPI = EV / AC
SPI measures progress against the planned schedule:
SPI = EV / PV
An index below 1.0 indicates underperformance. For example, a CPI of 0.83 means the project is earning about 83 cents of planned value for each dollar spent. An SPI of 0.80 means the project has completed about 80% of the work that was planned by the status date.
Worked example
Assume a project has these status-date values:
| Measure | Value |
|---|---|
| BAC | $100,000 |
| PV | $50,000 |
| EV | $40,000 |
| AC | $48,000 |
First calculate the indices:
- CPI = $40,000 / $48,000 = 0.8333
- SPI = $40,000 / $50,000 = 0.8000
The remaining budgeted work is BAC - EV, or $60,000. Adjusting that remaining work by both indices gives:
EAC = $48,000 + $60,000 / (0.8333 × 0.8000)
EAC is approximately $138,000.
This forecast says the project may finish about $38,000 above its original $100,000 budget. The result is higher than a forecast based only on CPI because the schedule problem is also assumed to increase future costs.
def eac_cost_schedule(bac, pv, ev, ac):
cpi, spi = ev / ac, ev / pv
return ac + (bac - ev) / (cpi * spi)
bac, pv, ev, ac = 100000, 50000, 40000, 48000
eac = eac_cost_schedule(bac, pv, ev, ac)
print(round(eac)) # 138000How the combined adjustment works
The formula treats the remaining work as affected by two conditions:
- The project is spending inefficiently, reflected by CPI.
- The project is progressing more slowly than planned, reflected by SPI.
When both indices are below 1, their product is smaller than either index alone. Dividing the remaining budgeted work by that product increases the forecasted remaining cost.
This method is useful when schedule delay has a credible cost effect. It is less suitable when SPI reflects only the timing of measured work and does not affect the dollars needed to finish. For example, a project may be late because a non-cost-critical approval is delayed, while the remaining work can still be completed for its original estimate.
Comparing forecasts
For the example, three methods produce different results:
| Forecast method | Formula | EAC |
|---|---|---|
| One-time variance | AC + (BAC - EV) | $108,000 |
| Continuing cost trend | BAC / CPI | $120,000 |
| Cost and schedule trend | AC + (BAC - EV) / (CPI × SPI) | $138,000 |
The combined method is a risk-based forecast, not a guaranteed outcome. It assumes the observed cost and schedule relationship will continue. Use it when historical data, root-cause analysis, and the project team support that assumption.
Common errors
- Using SPI as a percentage instead of a ratio. Use 0.80, not 80, in the formula.
- Applying the method without checking whether schedule delay drives cost.
- Mixing status dates or currency values between PV, EV, and AC.
- Presenting $138,000 as a fact instead of labeling it as a forecast based on explicit assumptions.
Exercise
A project has BAC = $200,000, PV = $120,000, EV = $90,000, and AC = $100,000. What is the EAC using the cost-and-schedule method?
Show answer
CPI = 0.90 and SPI = 0.75. EAC = $100,000 + ($200,000 - $90,000) / (0.90 × 0.75) = about $263,000.