Sub topic 2
Reading Performance: CV, SV, CPI, and SPI
This chapter assumes you know basic project management terms, such as scope, budget, schedule, and baseline. You should also be comfortable with simple arithmetic and ratios. The examples use earned value management (EVM), a method for comparing planned work, completed work, and spending at a specific status date.
The four core measures
EVM uses three values at the status date:
- Planned value (PV) is the budgeted cost of the work that should be complete.
- Earned value (EV) is the budgeted cost of the work that is actually complete.
- Actual cost (AC) is what the completed work has actually cost.
For example, suppose a project has planned $50,000 of work by today. The team has completed $40,000 of budgeted work and has spent $48,000.
The project’s total approved budget is called the budget at completion (BAC). BAC is useful for the whole forecast, but CV, SV, CPI, and SPI use PV, EV, and AC at the current status date.
| Measure | Formula | Meaning |
|---|---|---|
| Cost variance (CV) | EV - AC | Whether completed work cost more or less than planned |
| Schedule variance (SV) | EV - PV | Whether completed work is ahead of or behind the plan |
| Cost performance index (CPI) | EV / AC | Budgeted value earned for each unit of cost |
| Schedule performance index (SPI) | EV / PV | Progress achieved compared with planned progress |
Reading variances
Cost variance (CV) is expressed in currency.
With EV of $40,000 and AC of $48,000:
CV = $40,000 - $48,000 = -$8,000
A negative CV means the project spent more than the budgeted value of the work completed. A positive CV means the completed work cost less than its budgeted amount. A CV of zero means the completed work matches its budget.
Schedule variance (SV) is also expressed in currency, because it compares two budget values:
SV = $40,000 - $50,000 = -$10,000
A negative SV means less work has been completed than the plan expected by the status date. A positive SV means more work has been completed than planned.
SV does not mean “ten thousand dollars late” in calendar time. It shows the budgeted value of the work that is ahead or behind. Use the schedule model to translate that gap into dates or days.
Reading performance indices
The indices are ratios. A value of 1.00 means performance matches the plan.
For cost:
CPI = $40,000 / $48,000 = 0.8333
The project earns about $0.83 of budgeted value for every $1.00 spent. Because CPI is below 1, cost performance is unfavorable.
For schedule:
SPI = $40,000 / $50,000 = 0.80
The project has achieved 80% of the progress planned by this date. Because SPI is below 1, progress is behind the baseline.
A value above 1 is favorable. For example, a CPI of 1.10 means the project earns $1.10 of budgeted value for each $1.00 spent. An SPI of 1.10 means the project has achieved 110% of the planned progress at that status date.
def evm_indices(pv, ev, ac):
return {"CPI": ev / ac, "SPI": ev / pv}
pv, ev, ac = 50000, 40000, 48000
indices = evm_indices(pv, ev, ac)
cv = ev - ac
sv = ev - pv
print(f"CV: ${cv:,.0f}")
print(f"SV: ${sv:,.0f}")
print(f"CPI: {indices['CPI']:.4f}")
print(f"SPI: {indices['SPI']:.4f}")The output is:
CV: $-8,000
SV: $-10,000
CPI: 0.8333
SPI: 0.8000Interpreting the measures together
Looking at only one measure can hide the cause of a problem. In this example, both variance measures are negative and both indices are below 1. The project is behind the plan and spending inefficiently.
However, the measures do not explain why. Possible causes include inaccurate estimates, incomplete work measurement, scope changes, rework, supplier problems, or a baseline that no longer represents the approved plan. Investigate the underlying work packages before treating an index as a prediction.
Exercise
A project has PV of $80,000, EV of $72,000, and AC of $75,000. Calculate CV, SV, CPI, and SPI. What do they indicate?
Show answer
CV is -$3,000, SV is -$8,000, CPI is 0.96, and SPI is 0.90. The project is over cost for the completed work and behind the planned progress.