Sub topic 4
EAC When the Overrun Was a One-Off
Assume you know basic project-management terms, can calculate simple ratios, and understand the project baseline. This chapter focuses on one earned value forecast: Estimate at Completion (EAC) when an earlier cost overrun was unusual and will not happen again.
When this EAC method fits
Estimate at Completion is the forecast of the project’s total cost when all planned work is finished. If the project has already spent more than expected, you must decide whether that poor performance will continue.
Use the one-off, or atypical-variance, method when:
- A specific event caused the overrun.
- The event will not affect the remaining work.
- The remaining work has a reliable budget.
- The team expects future work to follow the original cost plan.
Examples include a one-time equipment replacement, an unusual legal fee, or a vendor penalty that has already been resolved.
The formula is:
EAC = AC + (BAC - EV)
The terms are:
ACis actual cost, the amount spent so far.BACis budget at completion, the approved budget for the whole project.EVis earned value, the budgeted value of the work completed so far.BAC - EVis the budgeted cost of the remaining work.
This method keeps the actual cost already incurred, then adds the original budget for the unfinished work.
Worked example
Suppose a project has these values:
| Measure | Value | Meaning |
|---|---|---|
| BAC | $100,000 | Total approved budget |
| EV | $40,000 | Budgeted value of completed work |
| AC | $48,000 | Actual cost spent so far |
The project spent $48,000 to produce $40,000 of budgeted work. The $8,000 difference came from a one-time equipment failure. The equipment has been replaced, and the team does not expect another similar cost.
The remaining budgeted work is:
BAC - EV = $100,000 - $40,000 = $60,000
The forecast total cost is:
EAC = $48,000 + $60,000 = $108,000
The $108,000 forecast includes the one-time overrun but does not assume that the overrun will repeat.
def eac_atypical(bac, ev, ac):
remaining_budget = bac - ev
return ac + remaining_budget
bac = 100_000
ev = 40_000
ac = 48_000
eac = eac_atypical(bac, ev, ac)
print(f"EAC: ${eac:,.0f}")
# EAC: $108,000How the calculation works
The method treats the past and future differently:
- Past spending is measured using
AC, even if it was higher than planned. - Future spending is estimated using the baseline budget,
BAC - EV. - The unusual event is not repeated in the forecast.
This is why you should document the cause of the overrun. Stakeholders need evidence that the event was isolated and that corrective action has removed its cause.
Check the forecast with VAC
Variance at Completion (VAC) compares the original budget with the forecast:
VAC = BAC - EAC
For this example:
VAC = $100,000 - $108,000 = -$8,000
A negative VAC means the project is forecast to finish over budget. The forecast overrun is $8,000, which matches the one-time cost already recorded.
A one-off event does not make the forecast equal to the original budget. The money has already been spent, so the final forecast still includes it.
Common errors
Do not use this method merely because the team hopes performance will improve. You need a reasoned explanation supported by project evidence.
Common mistakes include:
- Adding the one-time cost to the forecast twice.
- Using
BAC - ACas the remaining work budget. The correct expression isBAC - EV. - Treating every variance as atypical without checking its cause.
- Ignoring recurring problems such as low productivity or changing requirements.
- Reporting EAC without stating the assumption behind the formula.
If the same cost inefficiency is likely to continue, a method based on the Cost Performance Index (CPI) may be more appropriate. The formula is a modeling choice, so state why the chosen method matches the project’s conditions.
Exercise
A project has BAC = $80,000, EV = $30,000, and AC = $35,000. The $5,000 overrun came from a one-time inspection fee. What are EAC and VAC using the atypical-variance method?
Show answer
EAC = $35,000 + ($80,000 - $30,000) = $85,000. VAC = $80,000 - $85,000 = -$5,000, so the project is forecast to finish $5,000 over budget.