Sub topic 5
EAC When Current Cost Performance Will Continue
Assume you know the project baseline and can calculate planned value (PV), earned value (EV), and actual cost (AC). This chapter focuses on the case where the project's current cost efficiency is likely to continue for the remaining work.
The formula
Estimate at Completion (EAC) is the forecast of the project's total cost when all planned work is finished.
When current cost performance will continue, use:
EAC = \frac{BAC}{CPI}Here:
- BAC, or Budget at Completion, is the approved total budget.
- CPI, or Cost Performance Index, measures cost efficiency.
- EAC includes both money already spent and the expected cost of the remaining work.
CPI is calculated as:
CPI = \frac{EV}{AC}If CPI is below 1, the project has earned less value than the money it has spent. For example, a CPI of 0.80 means the project earns $0.80 of planned value for every $1.00 spent.
The formula assumes that this pattern is a useful predictor of future performance. It does not assume that the current dollar overrun is a one-time event.
A worked example
Suppose a project has these values:
| Measure | Value |
|---|---|
| BAC | $100,000 |
| EV | $40,000 |
| AC | $48,000 |
First calculate CPI:
CPI = \frac{40{,}000}{48{,}000} = 0.8333Then calculate EAC:
EAC = \frac{100{,}000}{0.8333} \approx 120{,}000The forecast is therefore about $120,000. If the same cost efficiency continues, the project is expected to finish about $20,000 over its original budget.
def eac_when_cost_trend_continues(bac, ev, ac):
cpi = ev / ac
eac = bac / cpi
return cpi, eac
bac, ev, ac = 100000, 40000, 48000
cpi, eac = eac_when_cost_trend_continues(bac, ev, ac)
print(f"CPI: {cpi:.4f}")
print(f"EAC: ${eac:,.0f}")The output is:
CPI: 0.8333
EAC: $120,000The same result can be written directly as:
EAC = \frac{BAC \times AC}{EV}For this example:
EAC = \frac{100{,}000 \times 48{,}000}{40{,}000} = 120{,}000The CPI form is usually easier to explain because it makes the performance assumption visible.
When this method fits
Use BAC divided by CPI when:
- The cause of the current cost performance is expected to remain.
- The work left is similar to the work already completed.
- The existing cost data is reliable.
- You need a quick, objective forecast based on measured performance.
For example, continuing labor inefficiency, recurring material waste, or an ongoing productivity problem may justify this method.
Do not use it automatically. A single unusual event, such as a one-time equipment failure, can make CPI look poor even though future work will return to the original cost rate. In that situation, applying the current CPI to all remaining work may overstate the final cost.
Checking the assumption
Ask what caused the current CPI:
- Is the cause recurring?
- Does the remaining work resemble the completed work?
- Is enough work complete for CPI to be meaningful?
- Have scope, rates, or delivery conditions changed?
Document the answers with the forecast. A stakeholder should be able to see both the number and the reason the formula was selected.
Exercise
A project has a BAC of $80,000, EV of $30,000, and AC of $36,000. If current cost performance will continue, what are the CPI and EAC?
Show answer
CPI = 30,000 / 36,000 = 0.8333. EAC = 80,000 / 0.8333 = $96,000.